{{advert|date=August 2012}}{{Use Indian English|date=March 2017}}{{Use dmy dates|date=July 2012}}{{Infobox company
| name = Odisha Power Generation Corporation Limited
| logo =
| type = State-owned enterprise
Public company
| foundation = 1984
| location = Bhubaneswar, Odisha, India
| key_people = Hemant Sharma (Chairman)
Indranil Dutta(Managing Director)
| num_employees = 900 (2012)
| industry = Electric utility
| products = Electric power
| services = Electricity generation
| revenue = {{profit}} {{INRConvert|7059.54|m}} (2015-16)
| homepage = {{URL|http://www.opgc.co.in/}}
}}

Odisha Power Generation Corporation Limited (OPGC) is the only thermal power generating company owned by Government of Odisha.[1] It was incorporated under the Companies Act 1956 on 14 November 1984. OPGC started as a solely owned Government Company of the state of Orissa. It owns and operates 2 units of 210 MW power plant at Ib Thermal Power Station (ITPS), Banharpali in Jharsuguda District of Odisha.The entire generation from these units is committed to GRIDCO on the basis of a long-term Power Purchase Agreement.

After divestment of 49% of the equity shares in favour of AES Corporation, USA in early 1999, OPGC with its present ownership structure is unique of its kind in the country.

During 1990, OPGC started construction of 7 Mini Hydel Projects in different locations of Orissa for generation of pollution free power by utilizing canal falls to meet the increasing demand of power with the major funding from MNES and IREDA. The details are as follows:

Project Name Capacity (KW) Status as on 2009
Biribati MHP 2 X 325 Under Operation
Kendupatna MHP 2 X 250 Under Operation
Andharibhangi MHP 1 X 325 Under Operation
Badanala MHP 2 X 325 Revival Proposal in Phase II
Banpur MHP 2 X 150 Revival Proposal in Phase II
Harabhangi MHP 2 X 1000 Revival Proposal in Phase III
Barboria MHP 2 X 325 Revival Proposal in Phase III

Share holding pattern

Share holding pattern of OPGC are as follows

Share Holders Percentage
Government of Odisha51
AES India Pvt. Ltd. (AES Corporation)16.25
AES OPGC Holding (AES Corporation)32.75

Operational highlights

Year Generation (MU) PLF (%) Aux. Consumption (%)
2007-07 3317.81 90.18 10.15
2007-08 3047.187 82.6 10.11
2008-09 3190.634 86.72 10.34
2009-10 2961.114 80.48 10.44
2010-11 3184.697 86.56 10.51
2011-12 2950.149 80.17 10.44
2012-13 3181.000 86.48 10.58

OPGC Expansion Project

OPGC’s expansion project consists of addition of 2x660 MW (1320 MW) to existing Ib Thermal Power Station. Captive coal mine and dedicated railway line for transportation of coal, are in advanced stage of development. All clearances for the power plant have been obtained. Contract has been awarded to M/s BHEL for supply of Main Plant and to M/s BGRE for balance of plant. Civil work at site has been successfully commenced.

50% of power to be generated from the proposed capacity addition has been tied up with GRIDCO under a long term power purchase agreement. Financing agreement executed with Power Finance Corporation and Rural Electrification Corporation for financing of 75% debt. Two captive coal mines (namely Manoharpur and Dip-side of Manoharpur) allocated to Odisha Coal and Power Limited for supply of coal to OPGC are in advanced stage of development, along with the dedicated railway line (MGR) of 47 km for transporting the coal from the mine to the power plant. Land acquisition process for railway line and coal mine have been significantly advanced and the Stage-1 clearance has been obtained from Ministry of Environment and Forest, Government of India for Forest Diversion for coal mine and MGR alignment.

The power plant will depend on coal from the captive coal mine allocated to Odisha Coal and Power Limited. The Coal from the coal mines of Odisha Coal and Power Limited shall be transported through the dedicated railway line to OPGC for commissioning and operation of the expansion power project thereafter. Based on the anticipated receipt of forest and environment clearance from MoEF, progress on land acquisition for railway line and sanction of tapered linkage from Ministry of Coal, GoI, the project is expected to be commissioned in the 12th Five Year Plan.

In addition to Units 3&4, based on the coal reserves available from the captive mines, OPGC is in a position to pursue Units 5&6 of 2x660 MW (1320 MW) at the same location, which is proposed to be pursued after award for commencement of construction is placed for units 3&4.

References

1. ^http://218.248.11.68/energy/Department.asp?lnk=3

External links

  • {{Official website|http://www.opgc.co.in/}}
{{State agencies of Odisha}}

8 : Electric-generation companies of India|Energy in Odisha|State electricity agencies of India|State agencies of Odisha|Energy companies established in 1984|Non-renewable resource companies established in 1984|Indian companies established in 1984|Companies based in Bhubaneswar

随便看

 

开放百科全书收录14589846条英语、德语、日语等多语种百科知识,基本涵盖了大多数领域的百科知识,是一部内容自由、开放的电子版国际百科全书。

 

Copyright © 2023 OENC.NET All Rights Reserved
京ICP备2021023879号 更新时间:2024/9/22 10:39:30