The Central Asia-South Asia power project, commonly known by the acronym CASA-1000, is a $1.16 billion project currently under construction that will allow for the export of surplus hydroelectricity from Tajikistan and Kyrgyzstan to Pakistan and Afghanistan.[1] Groundbreaking for the project took place on May 12, 2016 in Tajikistan in a ceremony attended by the Kyrgyz, Tajik, and Pakistani Prime Ministers,[2] and is expected to be completed by the end of 2018.[2] The project initially also included transfer of electricity to Afghanistan, however the country abandoned its share of electricity due to dearth of demand, hence Pakistan will receive 1,300 megawatts of electricity.[3][4]

Project Details

The project will allow for the export of 1,300 megawatts of electricity during the summer months when both Tajikistan and Kyrgyzstan experience surplus electricity generation from hydroelectric dams.[5]

High voltage direct current (HVDC) converter stations will also be included as part of the project, as well as a 477 kilometer long, 500 kilovolt alternating current transmission line between Datka, Kyrgyzstan and Khujand, Tajikistan.[6][2] A 1,300 MW AC/DC converter station will be constructed in the city of Sangtuda, Tajikistan, as well as a 300 MW converter station in Kabul, Afghanistan. A 750km HVDC line will be constructed between Sangtuda, and the city of Peshawar, Pakistan, via the Salang Pass and Kabul.[7] In Peshawar, a 1,300 MW converter station will be built and connected to Pakistan's electric grid.[7]

Transmission lines are designed to transmit 1,300 MW of electricity, with Afghanistan allotted 300 MW of electricity and Pakistan 1000 MW of electricity. Initially, however, Pakistan will receive 700 MW, while Afghanistan will be supplied 300 MW.[2]

References

1. ^{{cite news|title=CASA-1000: Tajikistan to export 1,000MW hydel electricity|url=http://tribune.com.pk/story/1024352/casa-1000-tajikistan-to-export-1000mw-hydel-electricity/|accessdate=23 May 2016|agency=Express Tribune|date=9 January 2016}}
2. ^{{cite news|title=Casa-1000 formally inaugurated|url=http://dailytimes.com.pk/opinion/17-May-16/casa-1000-formally-inaugurated|accessdate=23 May 2016|agency=Daily Times (Pakistan)|date=17 May 2016}}
3. ^{{Cite web|url=http://tribune.com.pk/story/1124340/casa-1000-power-project-kabul-abandons-share-islamabad-receive/|title=Pakistan to receive more as Afghanistan abandons share in CASA-1,000 - The Express Tribune|date=2016-06-16|language=en-US|access-date=2016-06-27}}
4. ^{{Cite web|url=http://tribune.com.pk/story/1130766/casa-1000-power-project-european-firms-vying-set-converter-stations/|title=CASA-1,000 power project: European firms vying to set up converter stations - The Express Tribune|date=2016-06-26|language=en-US|access-date=2016-06-27}}
5. ^{{cite news|last1=Putz|first1=Catherin|title=World Bank Tries to Answer CASA-1000 Criticisms|url=http://thediplomat.com/2016/05/world-bank-tries-to-answer-casa-1000-criticisms/|accessdate=23 May 2016|agency=The Diplomat|date=11 May 2016}}
6. ^{{cite web|title=Central Asia South Asia Electricity Transmission and Trade Project (CASA-1000)|url=http://www.worldbank.org/projects/P145054?lang=en|website=World Bank|publisher=World Bank|accessdate=23 May 2016}}
7. ^{{cite web|title=CASA-1000: About us|url=http://www.casa-1000.org/MainPages/CASAAbout.php#objective|website=CASA-1000|accessdate=23 May 2016}}
{{Portal|Pakistan|Energy}}{{DEFAULTSORT:Electricity Sector In Pakistan}}

6 : Electric power in Pakistan|Foreign trade of Pakistan|Energy infrastructure by country|Energy infrastructure in Asia|Infrastructure in Afghanistan|2016 establishments in Pakistan

随便看

 

开放百科全书收录14589846条英语、德语、日语等多语种百科知识,基本涵盖了大多数领域的百科知识,是一部内容自由、开放的电子版国际百科全书。

 

Copyright © 2023 OENC.NET All Rights Reserved
京ICP备2021023879号 更新时间:2024/9/21 22:15:43