词条 | Sabarimala Railway |
释义 |
| box_width = 28em | name = Sabarimala Railway | other_name = | native_name = ശബരിമല റെയിൽവേ | native_name_lang = ml | color = | logo = | logo_width = | logo_alt = | image = | image_width = | image_alt = | caption = | type = Regional rail Heavy rail Light rail | system = | status = Construction (Under progress) | locale = Kerala | start = {{rws|Angamaly}}(Ernakulam) | end = Erumeli(Kottayam) {{rws|Punalur}}(Kollam)Nedumangad(Trivandrum) {{rws|Nemom}}(Trivandrum)| stations = 20 (Proposed) | routes = 1 | daily_ridership = | ridership2 = | open = | close = | owner = Indian Railways | operator = Southern Railway zone | character = | depot = Kollam Ernakulam | stock = WDP-4 | linelength_km = | linelength_mi = | linelength = {{convert|111|km|abbr=on}} | tracklength_km= | tracklength_mi= | tracklength = | tracks = 1 | gauge = {{RailGauge|1676mm}} | old_gauge = | load_gauge = | minradius = | racksystem = | routenumber = | linenumber = | electrification = | speed_km/h = | speed_mph = | speed = | elevation_m = | elevation_ft = | elevation = | website = {{URL|www.sr.indianrailways.gov.in}} | map = | map_state = hide }} Sabarimala Railway is a proposed {{convert|111|km}} railway line from {{rws|Angamaly}} to Erumeli, near Sabarimala that has been sanctioned in the year 1998 by Indian Railways. According to a Memorandum of Understanding (MoU) signed between the Kerala State and the Ministry of Railways on January 27, 2016, commercially viable railway projects will be identified and handed over to the Special Purpose Vehicle (SPV) to be fast-tracked on a 51:49 per cent equity basis. SPV has discussed about the extension to {{rws|Punalur}}. The currently proposed Sabarimala railway is under PMO - Pro active governs and timely implementation (Pragati); will be monitored by the Prime Minister's Office. Another proposal for this railway line is extend to {{rws|Trivandrum Central}}. If this proposed Sabarimala railway is connected to proposed new railway terminal at {{rws|Nemom}} near {{rws|Trivandrum Central}} via Nedumangad, several long distance trains are supposed to be operated from {{rws|Nemom}} Terminal via {{rws|Punalur}} ,Nedumangad and {{rws|Angamaly}} to Chennai/Bangalore and rest of country. Survey for new lines from {{rws|Madurai Junction}} to {{rws|Kottayam}} and {{rws|Dindigul Junction}} to Cumbum lower camp, Kumily to Sabarimala, ettumanoor to pala also started. BackgroundKerala's government started the land acquisition for the construction of this Sabarimala railway project and established special Thahasildhar offices at Perumbavoor and Palai in 2006 and at Muvattupuzha in 2010 for the land acquisition of Sabarimala railway. Railway and revenue department has conducted joint survey for the land acquisition of this railway line, laid boundary stone for the acquired land and notification for land acquisition up to proposed Ramapuram railway station in Kottayam district. 90% of railway line construction up to Kaladi railway station {{convert|7|km}} was completed by 2010. The revenue department of the Government of Kerala completed all formalities of land acquisition in Chelamattom village, Perumbavoor village, Koovapady village, Vengoor West village, Rayamangalam village, Asmannor village (on {{date|19 Aug 2008}}) and Muvattupuzha village (on {{date|28 Oct 2011}}) and declared the land value of acquired land for this railway line. But land price distribution to the land owners of these villages has not happened due to the lack of funding from the Railway Ministry of the Government of India. Although the Railway board has approved the revised estimate of Angamali- Perumbavoor reach of this railway line {{INRConvert|203|c}}, has not given any fund for the completion of revised estimate approved reach. The Railway board has written to the Kerala government that without 50% of cost sharing by the state government, they could not allocate any further funding to Sabarimala railway project. The Railways have started the pre-non interlocking works in the Angamali Railway station on August 3, 2017 which aims at connecting the Sabarimala railway to the main line of Ernakulam-Shoranur. They also have decided to open the railway offices at Perumbavoor and Muvattupuzha for the fast acquisition of lands. Idukki, one of the districts in Kerala which has no railway station, will get railway connectivity and two railway stations through the line. The railway line will help the wood–based and rice–based industries concentrated in the Perumbavoor–Kalady area, and the tourist destinations of Ernakulam, Idukki and Kottayam districts. StationsProposed new railway stations in I Phase are Kalady, Perumbavoor, Odakkali, Kothamangalam, Muvattupuzha, Vazhakulam, Thodupuzha, Karimkunnam, Ramapuram, Palai, Erattupetta, Kanjirappally and Erumeli. During II Phase stations at Ranni, Pathanamthitta, Konni, Koodal, Pathanapuram will be connected to {{rws|Punalur}} and there join Kollam–Sengottai branch line. Since it provides a railway facility to Sabarimala pilgrims and the number of pilgrims visiting Sabarimala temple is more than the total population of Kerala, this railway line was named Sabarimala railway. It is operated by {{rwd|Thiruvananthapuram}} division of the Southern Railway zone.[1] Stations in Phase-1
Stations in Phase-2
Stations in Phase-3
Complete alignment[3][ {"type": "Feature", "properties": { "marker-symbol": "rail", "marker-color": "46ea5f", "marker-size": "medium", "title": "Angamali"}, "geometry": { "type": "Point", "coordinates": [76.378,10.183] } }, {"type": "Feature", "properties": { "marker-symbol": "rail", "marker-color": "46ea5f", "marker-size": "medium", "title": "Kalady"}, "geometry": { "type": "Point", "coordinates": [76.4389,10.1661] } }, {"type": "ExternalData", "service": "geoline", "ids": "Q24945382", "properties": { "title": "Sabarimala Railway", "stroke": "#ffb100", "stroke-width": 8 } } ] References1. ^{{cite news|last1=Radhakrishnan|first1=S. Anil|title=State nod to share Sabari rail costs|url=http://www.thehindu.com/news/cities/Thiruvananthapuram/state-nod-to-share-sabari-rail-costs/article7939318.ece|accessdate=4 February 2016|work=The Hindu|date=2 December 2015|location=Thiruvananthapuram}} 2. ^New India Express, date:29 May/2017, Kottayam Edition 3. ^http://www.sr.indianrailways.gov.in/cris//uploads/files/1450773109216-TVCmap-2015-Model.pdf External links{{osmrelation-inline|5929431}}{{Thiruvananthapuram railway division |state=expanded}} 7 : Rail transport in Kerala|Thiruvananthapuram railway division|Proposed railway lines in India|Transport in Ernakulam district|Transport in Kottayam district|Transport in Kollam district|5 ft 6 in gauge railways in India |
随便看 |
|
开放百科全书收录14589846条英语、德语、日语等多语种百科知识,基本涵盖了大多数领域的百科知识,是一部内容自由、开放的电子版国际百科全书。