词条 | Stuttgart Hauptbahnhof | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
释义 |
| name = Stuttgart Hauptbahnhof | native_name = | native_name_lang = de | symbol = rail | symbol_location = de | symbol2 = s-bahn | symbol_location2 = stuttgart | symbol3 = stadtbahn | symbol_location3 = stuttgart | type = Terminal station | image = 2018-08-30 EC 218 "Chiemgau" Salzburg - Stuttgart (42581205930).jpg | alt = | caption = Station building (2018) | other_name = | address = | borough = Stuttgart, Baden-Württemberg | country = Germany | coordinates = {{coord|48|47|02|N|9|10|54|E|region:DE-BW_type:railwaystation|format=dms|display=inline,title}} | line = * Fils Valley Railway (KBS 750, 790.1)
| platforms = 22 (16 above ground terminal, 2 S-Bahn, 4 U-Bahn)[1][2] | tracks = | connections = | code = {{Deutsche Bahn station codes|code=6071[3]|ds100=TS[3]|ibnr=8000096|category=1[4]}} | architect = Paul Bonatz and Friedrich Eugen Scholer | architectural_style = | opened = {{Start date and age|1922|10|23|df=y}} | closed = | electrified = {{Start date and age|1933|05|15|df=y}} | passengers = 220,000 daily[6] | pass_year = | zone = Verkehrs- und Tarifverbund Stuttgart | website = [https://www.bahnhof.de/bahnhof-de/Stuttgart_Hbf-1038338 www.bahnhof.de] | map_type = Baden-Württemberg | map_caption = Location within Baden-Württemberg | services ={{s-rail|title=DB Fernverkehr}}{{s-line|system=DB-IC|line=87|previous=Böblingen|next=}}{{s-rail|title=SBS}}{{s-line|system=SBS|line=S1|previous=Stadtmitte|next=Bad Cannstatt|type=North|type2=South}}{{s-line|system=SBS|line=S2|previous=Stadtmitte|next=Bad Cannstatt|type=North|type2=South}}{{s-line|system=SBS|line=S3|previous=Stadtmitte|next=Bad Cannstatt|type=North|type2=South}}{{s-line|system=SBS|line=S4|previous=Stadtmitte|next=North|type=North|type2=South}}{{s-line|system=SBS|line=S5|previous=Stadtmitte|next=North|type=North|type2=South}}{{s-line|system=SBS|line=S6|previous=Stadtmitte|next=North|type=North|type2=South}}{{s-line|system=SBS|line=S60|previous=Stadtmitte|next=North|type=North|type2=South}} }} Stuttgart Hauptbahnhof is the primary railway station in the city of Stuttgart, the state capital of Baden-Württemberg, in southwestern Germany. It is the largest regional and long-distance railway station in Stuttgart, the main node of the Stuttgart S-Bahn network, and, together with the station at Charlottenplatz, it is the main node of the Stuttgart Stadtbahn. Located at the northeastern end of the Königstraße, the main pedestrian zone of the city centre, the main line station is a terminus, whilst the subterranean S-Bahn and Stadtbahn stations are through-stations. The station is well known for its 12-storey tower with a large, rotating and illuminated Mercedes-Benz star insignia on top; the tower and station building are city landmarks. Plans for the controversial Stuttgart 21 project to convert the main line terminus station into an underground through station include the demolition of the side wings of the building, together with the elimination of the platforms, tracks, and apron of the terminus station. The planned underground through station is configured at a 90-degree angle to the present station. Construction is scheduled from 2010 to 2019. In November 2009, preservationists of the International Council on Monuments and Sites nominated the building for inclusion in UNESCO's World Cultural Heritage list, an occasion that opponents of the Stuttgart 21 project picked to urge the city and Deutsche Bahn to stop the project which implies demolition of parts of the complex designed by Paul Bonatz.[5] HistoryFirst and second CentralbahnhofUntil 1922, the central station (Centralbahnhof or Zentralbahnhof) was located on the Schlosstrasse (the precise location of the former station is on what is today called the Bolzstrasse), near the Schlossplatz. The first station building, a terminus station with 4 tracks, was built by Karl Etzel for the opening of the Württemberg Central Railway (Zentralbahn), with its two branches to Ludwigsburg and Esslingen. The wooden station hall was not unusual at the time and covered four tracks. The first train, arrived at the station from Canstatt on 26 September 1846. The first phase of railway construction in the Kingdom of Württemberg, with routes to Heilbronn, Bretten, Ulm, and Friedrichshafen, was completed by 1854. Due to increasing railway traffic,{{sfn|Kübler|1905}} the first building was replaced by new construction at the same spot in the 1860s. Between 1863 and 1867, the engineers Klein, Georg Morlok, Carl Julius Abel and later city architect Adolf Wolff[6] created this second station, with 8 tracks, featuring a building with grandiose arches in the Renaissance Revival style. Parts of the façade of this building are now part of the Metropol, an events centre and cinema complex. Sprickerhof through stationWith a steadily increasing traffic volume and the connection of additional lines, the station had increasingly reached its capacity limits in the early 20th century.{{sfn|Kübler|1905}} By 1905, there were three designs for the redevelopment of the station:{{sfn|Kübler|1905}}
The concept of Sprickerhof through station was introduced in 1901. The Gäu Railway and the line from Feuerbach were to run through the Kriegsberg (a hill to the northwest of the current station) to the central station in three parallel twin-track tunnels at a gradient of 1:100 from Wolframstraße in an arc with a radius of 300 metres. This would have run to Bahnhofstraße via Kriegsbergstraße and the tracks would have been in the area of the road to Ludwigsburg. The crossover tracks would have run into the tunnel for about 150 metres. The entrance building would have been built in the area of the main customs office. The above-ground areas between Schloßstraße and Schillerstraße would have been demolished for this project. A commission of external experts opposed the project.{{sfn|Kübler|1905}} The current HauptbahnhofThe present Hauptbahnhof was built between 1914 and 1928 on the street now called Arnulf-Klett-Platz, only about 500 metres east of the former station. In 1910, the Royal Württemberg State Railways (Königlich Württembergischen Staats-Eisenbahnen or K.W.St.E.) financed an architectural contest, which drew 70 participants. The competition was won by the architects Paul Bonatz and Friedrich Eugen Scholer with their plans for umbilicus sueviae—the Navel of Swabia.[7] After undergoing numerous changes, including moving the station tower from the main façade to the wing at the Schlossgarten, construction began in 1914 on Cannstatter Strasse. Changes to the plan also occurred in the construction phase.[7] Due to the route of the tracks to the old station, construction needed to be done in two phases, with the first stage, including tracks 9 to 16,[8] going into service on 22 October 1922. The tracks to the old station were cut at the same time. As further construction of the new station was delayed for financial reasons, the city of Stuttgart loaned Deutsche Reichsbahn two million Reichsmark (equivalent in current values to €{{Inflation|DE|2|1925|r=1}} million) in 1925 and a further loan of 5 million Reichsmark (equivalent to €{{Inflation|DE|5|1927|r=1}} million) in 1927.[9] The second stage was completed in 1928 and the electrification of the 16 tracks was completed on 15 May 1933. In the bombing of Stuttgart in the Second World War, the Hauptbahnhof was severely damaged several times, although from 1940 to 1942 a decoy target at Lauffen am Neckar diverted many raids. The reconstruction took several years. Stuttgart Hauptbahnhof has been listed as a cultural heritage site of special significance (under section 12 of the Baden-Württemberg heritage protection act) since 20 August 1987. S-Bahn and StadtbahnA plan developed in the mid-1950s for a S-Bahn proposed a four-track station with two 175-metre-long island platforms under the Hauptbahnhof, which would be linked by two tracks towards the city centre and four towards Feuerbach/Bad Cannstatt.[10] Between 1971 and 1978, an underground Hauptbahnhof station was built for the S-Bahn in the central Neckar area, which was a cut-and-cover construction under the main hall in the area of the small ticket hall. This station has two tracks and an island platform. The first S-Bahn services ran on 1 October 1978. After four years of planning, construction commenced on a new central signalling centre of class SpDrL 60 at the Hauptbahnhof on 3 October 1973. The signalling infrastructure was gradually put into operation: first for the train depot on 1 and 2 October 1977, then for the passenger station and freight yard on 5 and 6 November 1977 respectively. The S-Bahn connecting line was opened as far as the former terminus at Schwabstraße on 1 October 1978. A total of 95 stop signals, 93 distant signals, 583 shunting signals, 506 point machines, 530 track circuits and 169 axle counters were integrated into the track layout. The new signalling centre replaced twelve old signal boxes.[11] DM 68 million was spent on the signalling centre and its outdoor facilities.[12] Today, five to seven dispatchers work in the signalling centre.[13] The underground Stadtbahn station, called Hauptbahnhof (Arnulf-Klett-Platz), in front of the station hall under Arnulf-Klett-Platz was opened to traffic on 9 April 1976. Today, ten Stuttgart Stadtbahn lines serve the station. The S-Bahn station was used (as of 1993) by about 120,000 passengers per day. This included 55,000 transfers to long-distance, regional and Stadtbahn services, about 15,000 passengers transferring between the S-Bahn lines via Feuerbach and Bad Cannstatt and around 50,000 passengers entering or exiting at the station.[14] The Stadtbahn station was used by around 75,000 passengers a day.[15] In 2016, 140,000 passengers used the S-Bahn station each day. With the commissioning of Stuttgart 21, the volume is expected to decline by about 20 percent.[16] The S-Bahn station is called Stuttgart Hbf tief (deep) and is 20 m below the Hauptbahnhof. BuildingThe station building consists of cubes nested symmetrically and asymmetrically. It is characterised by cubes of different size, dimension and design.[17] Concrete and steel were used during the construction of the station building and the rough-hewn Muschelkalk ("mussel chalk") blocks were laid as a facade over bricks. The Muschelkalk comes from the Trochitenkalk Formation of the Upper Muschelkalk from the Crailsheim area.[18] Inside, sandstone, tuff and brick dominate the walls. These are partly designed as flat wooden ceilings and partly designed as reinforced concrete structures. The pillars in the terminal station hall are made of exposed concrete. The station is also integrated into the urban planning of the city of Stuttgart. The structure adapts to the sloping terrain (there is a difference in height of almost five metres between the tower and the north exit). The original plans called for a road leading directly to the building, but Bonatz eliminated this in favour of the Lautenschlagerstraße, as it is now known, which ends at the Kleine Schalterhalle (small ticket hall). The tracks for the local commuter traffic are behind this hall and the central exit is between the hall and the main building, which is useful for the control of passenger flow. Underneath the tracks area, three tunnels running at right angles to the tracks provide highly functional access points: the mail tunnel runs from the post office annex to the northwestern station area, a passenger tunnel eases the task of changing platforms and a third tunnel is meant for the transit of express freight. The construction has some highly regarded features. The façade is made of limestone, which was covered with bricks; on the inside, sandstone, tuff, and bricks form the walls. The roof structures consist partly of flat wood and partly of reinforced concrete panels. The use of exposed concrete on the pillars lends a modern flair to the main hall. The structure features conservative elements, shown in the monumentality and the reserved decorations, as well as progressive elements, as shown by the flat roof structures, for example. The design is considered an important example of the Stuttgart School. Christoph Ingenhoven, the architect of the new station, expressed the opinion that much of Bonatz's original visions, which tended towards "a knight's castle or Valhalla", can still be found in the current building.[19] The Stuttgart Regional Court, in its decision to permit the demolition of the side wings, stated that only the terminal train shed, the tower, the ticket halls and the portico were decisive for the architectural recognition of the work, but not the side wings.[17] Tracks and platformsSince the existing tracks to the old station continued in use until the commissioning of the new one, the competition plan proposed, at the suggestion of the Generaldirektion der Staats-Eisenbahnen (General Headquarters of the State Railways), the building of a three-span train shed. This plan was later changed to low canopies over each platforms with slots above the tracks to allow smoke to escape and the roof supports were placed on the luggage platforms. Due to the shortage of materials after the First World War, the canopies planned for tracks 1 to 16 were not executed in steel, but in wood. After the destruction in the Second World War, new canopies were built on reinforced concrete bases. During the construction of the ramp for the Stuttgart S-Bahn from 1971 to 1974, tracks 1 to 3 were not available and a platform was built on track 1a as a replacement. In preparation for the Stuttgart 21 project, the platforms were extended towards the track apron from May 2010 and track 1a was removed in September 2010. Services on lines S1 to S6 and S60 of the Stuttgart S-Bahn stop on two tracks (tracks 101 and 102) in the underground S-Bahn station (third basement). S-Bahn services towards Schwabstraße stop on track 101, while services towards Bad Cannstatt and Stuttgart North stop on 102. The track apron connects five tracks of the regional and long-distance traffic (one track towards the Gäu Railway and two tracks each towards Bad Cannstatt and Feuerbach) with the station tracks;{{sfn|Planning approval|2005}} five further tracks connect the station with the storage facility at Rosenstein Park.[20] The set of tracks is protected as an object of cultural heritage under the Baden-Württemberg heritage act,{{sfn|Planning approval|2005}} although this protection will be removed after the completion of Stuttgart 21.{{sfn|Planning approval|2005|page=176}} The necessary flying junctions were built according to plans by Karl Schaechterle between 1908 and 1914.{{sfn|Stiglat| 2004 | page= 358}} At the opening of the station, it had two dispatcher's signal boxes:[21] Signal box 1 provided routings for tracks 1 to 4 to and from the suburban tracks to Cannstatt and for tracks 4 to 7 to and from the suburban tracks to Feuerbach.[21] Signal box 2 provided routings for the tracks for long-distance traffic. Entry and exit of trains to the Gäu Railway and their exit to the mainline tracks to Feuerbach was possible from tracks 7 to 12. The entrance of trains from the long-distance tracks from Cannstatt was possible on tracks 8 to 13.[21] The entrance of long-distance services from Feuerbach and the exit of long-distance services to Cannstatt was possible on tracks 12 to 16.[21] In addition, there were other signal boxes for connecting to the storage yard (signal boxes 3 and 5) and the freight yard (signal box 4).[21] In 1977, the signal boxes were replaced by a central signalling centre to the south of track 16.[22] Since then there have been standard routes to and from the S-Bahn tracks to Bad Cannstatt from tracks 1 to 6 as well as from and to the S-Bahn tunnel and Zuffenhausen from and to tracks 3 to 12.[23] Entrance from the mainline tracks from Zuffenhausen to tracks 3 to 16 is possible, as is exit towards Zuffenhausen from tracks 3 to 12.[23] Moves from the long-distance tracks from Bad Cannstatt can continue to tracks 12 to 16 and entrances from those tracks is possible to tracks 8 to 13 across the tracks.[23] Altogether Stuttgart station has over 140 kilometres of railway tracks[24] and 385 sets of points{{sfn|Planning approval|2005}} on 82 hectares of land.[24] The aboveground platforms are 76 centimetres-high and usually 8.45 metres-wide[25] and have lengths varying between 326 metres (platforms 7,[23] 13 and 14) and 470 metres (platforms 8,[23] 15 and 16). The S-Bahn platform (tracks 101/102) is 96 centimetres high and 280 metres-long.[26] The underground S-Bahn station is preceded by a 700-metre-long ramp on a 3.2 percent grade, which passes under the track and platform facilities of the main station over a length of around 500 metres.[27] Station towerThe 56 metre-high station tower is a landmark of the city of Stuttgart[28] and marks the end of Königstraße.[17] It is founded on 288–290 piles with a length of between 10 and 11 metres.[29] It is disputed whether the piles are made of reinforced concrete[30] or oak,[31] but Deutsche Bahn refused to commission test bores, as according to a report the station tower stands on reinforced concrete piles and the resolution of the issue has no decisive importance for the construction of Stuttgart 21.[32] When completed in 1916, the tower only provided a restaurant on the top floor and a waiting room for King William II.[28][33] In 1926, the café run by Eugen Bürkle (with a boardroom, tea room, wine bar, dining room and rooftop restaurant) was advertised with the slogan "The most beautiful station restaurant rooms in Germany".[34] After the Second World War, when the tower suffered little damage, a rotating Mercedes star with a diameter of five metres was installed on the turret roof in 1952 and still marks the building's silhouette.[28] The advertising revenue was used for the reconstruction of the station. From 1955 to 1976, the station tower was used as a hotel and at times as accommodation for rail employees.[28][35] The Turmforum (tower forum) Stuttgart 21 project information display has been established on four levels since 1998.[28] The Stuttgart-Mitte registry office has carried out marriages in the conference room on level 9 since 2000.[35] In addition, a bistro and a viewing terrace (lift and entrance free) is located in the tower. The tower clock has a dial with a diameter of five and a half metres. Terminal station hallThe terminal station hall connects directly to the cross-platform hall at the end of platforms tracks 1 to 16. The terminal station hall was built with a reinforced concrete wall on the side near the platforms to reduce the effects of a possible brake failure.[36] The eight arches leading to the cross-platform hall are divided into three parts: at the top they each have a window forming a round arch, the middle parts that are at the level of the platform canopies are solid and are built to full width in their lower parts, while at the bottom of each arch there is a passage to the cross-platform hall, which originally had a platform gate.{{sfn|Planning approval|2005}}[56] A similar arrangement can be found on the opposite side, towards the city. The original ceiling was destroyed during the Second World War and the current ceiling was completed in 1950.[37] Originally there were waiting rooms and restaurants, separated by class, between the small and large ticket halls on the side facing away from the tracks.[38] Some of the 40 shops and catering services that are now occupy the station were inserted in the terminal station hall, while the others are accessible from it. The building ends with an arcade to Arnulf-Klett-Platz. A raised wire cage has been erected in the hall as a dovecote that serves to limit the propagation of feral pigeons. In the course of the Stuttgart 21 project, the passageways that now lead to the cross-platform hall are to be closed by a glass structure, but the basic tripartite division of the round arches is to be retained.{{sfn|Planning approval|2005}} On the side facing the city, the wall panels in the middle of the arches are to be partially removed in order to illuminate the offices behind.{{sfn|Planning approval|2005}} Two future staircases and three skylights are to be created for the distribution level below the aboveground station hall so that the station hall will remain "accessible and experienceable."{{sfn|Planning approval|2005}} However, with the loss of its current function, it will also lose some of its significance.{{sfn|Planning approval|2005}} North exitThe north exit connects the terminal station hall with Friedrichstraße (the B 27); until 2012 it was the only barrier-free access to the station. Originally, the station forecourt, which had a pavilion in the centre, lay in front of the north exit;[33] it was later used as a parking area and included an access to the passage under Arnulf-Klett-Platz. From the summer of 2012 to October 2013,[39] the north exit was closed and the direct access to the Klett passage could not be used as the engineering building for the Stuttgart 21 project was being built there. The parking area, which had also not been available since summer 2012, has been partly usable since mid-2014. Barrier-free access was only possible via a detour during the construction of the engineering building: a new passage was created on the northwest side on the side of the platforms, about 100 metres from the former north exit, which currently serves as another barrier-free access to the station. The arch above the north exit reflects the design of the remaining arches of the terminal station hall. Small ticket hallThe small ticket hall is aligned with Lautenschlagerstraße and the Zeppelin building, also designed by Bonatz and Scholer.[40] The small ticket hall was originally designed for access to suburban services on tracks 1 to 6[41] and also offered access to the adjacent Reichsbahn Hotel (now the Intercity Hotel).[33] The small ticket hall is now occasionally used for events, otherwise it is empty. Central exitThe central exit[38] connects the terminal station hall with Arnulf-Klett-Platz. It is recessed behind the pillars of the arcades.[33] In contrast to the clearly visible entrances, it is not visible from the outside.[42] A Württemberg coat of arms was installed above the exit during the demolition of Königstor (king's gate) at the end of Königstraße in 1922. From the central exit there is an access to the Klett passage, but it is not possible to cross the Arnulf-Klett-Platz above ground. As part of the Stuttgart 21 project, the staircase to the above ground station hall is to be divided into three parts and its middle section is to be demolished to provide a passage for direct access to the distribution level behind.{{sfn|Planning approval|2005|p=64}} Large ticket hallThe large ticket hall acts as an avant-corps in the façade of the entrance building, while also being an independent building.[42] The arched opening to the city reinforces its monumentality and thus acts to give direction. It also reflects the motif of a city gate, which refers to the original location of the station in front of the city.[42] The spatial effect arises not only from the size of the hall, but also from its functionality for rail travellers.{{sfn|Planning approval|2005}} The former Königstor, which had stood at the beginning of Unteren Königstraße since 1809 and actually fulfilled the function of a city gate, was perceived as a traffic obstacle after the construction of the station and was removed in 1922. Paul Bonatz rescued the shield of Königstor and had it mounted above the central entrance in the platform hall. The large ticket hall was originally intended for long-distance traffic, which was handled on tracks 7 to 16.[41] It receives the traffic coming from the Königstraße, but it is not aligned with the axis of the Königstraße.[33] The interior of the hall has a vestibule character and the path to the station hall leads up a flight of steps.[42] The original staircase was removed in the 1970s and replaced by a new staircase and two escalators.[17] Around that time, the ground was broken to provide access to the Klett passage.[17] DB's travel centre and the AIRail check-in desks are now located in the large ticket hall and Königstraße is connected to the hall via the underground Klett passage. In the course of the Stuttgart 21 project, the wall of the large ticket hall facing the station is to be breached in order to make a direct access to the planned distribution level behind it.{{sfn|Planning approval|2005}} The planned openings are to have the proportions of the arches above it.{{sfn|Planning approval|2005}} The staircase to the platform area would be removed, otherwise the width of the passage would not be sufficient for the expected flows of people and the spatial separation from the main hall would inevitably be obliterated by the installation of additional stairs.{{sfn|Planning approval|2005}} The main distribution system will be centered on the hub in the large ticket hall with the main pedestrian traffic flowing straight through.{{sfn|Planning approval|2005}} North wingThe approximately 20 metre-wide[43] north wing consisted of a cubic area for the railway postal service,[44] which was used by Deutsche Post until July 2010, and adjoining office space that were last used by the Intercity Hotel and the Federal Police.[45] With a length of 83 metres,[43] the north wing enclosed only part of the facilities on the platform, while the rest formed part of the freight yard,[46] which was abandoned in 1995.[47] The north wing was demolished in 2010 as part of the Stuttgart 21 project.[48] Kurt-Georg-Kiesinger-Platz lies between the north wing and Heilbronner Straße. The new LBBW building lines on this square, while the remaining main building of the former Reichsbahndirektion Stuttgart (Reichsbahn railway division headquarters) building is on the other side of the street. Schlossgarten wingThe Schlossgarten wing, also known as the South wing, continued the axis of the Königstraße and forms the side of the station on the Schlossgarten. The wing itself was 200 metres long[49][50] and together with the large ticket hall and the station tower formed a 277-metre-long facade[51] to the Schlossgarten. The façade was interrupted by the station tower and three 27-metre-wide avant-corps, which indicated the positions of the passenger subway and the former postal and express freight tunnels. The wing concealed the difference in height between the Mittlerer Schlossgarten (Central Palace Garden) and the railway facilities, while, during the steam era, it also protected the Schlossgarten from soot and noise from railway operations[52] and functioned as a facade preserving the view from the park.[53] The interior of the wing was used for rail services[42] and express freight operations.[23] The Schlossgarten wing was demolished in the course of the Stuttgart 21 project from January 2012.[54] According to the architect Christoph Ingenhoven, it was "technically absolutely impossible" to save the wing[19] because the new underground concourse would cut it.[52] Klett passageSeven Stadtbahn lines pass through the lower S-Bahn station under the station forecourt (Arnulf-Klett-Platz) in the second basement. The Klett passage on level −1 is the access and distribution level for the long-distance and regional services on level +1, to the S-Bahn services on level −3, to the Stadtbahn services on level −2 and to Arnulf-Klett-Platz on level 0 and the city centre. In it is also a large shopping arcade. Another part of the first basement level is used for an underground car park with 120 parking spaces, which also serves as a fallout shelter with 4,500 seats.[27] In a disaster or military emergency, part of the underground parking lot would be provided with beds (separated by pressure doors); the technical rooms, kitchen, sanitary installations, water and air conditioning for the bunker are located on the second basement level. OtherThe front of the building features a quote by Georg Wilhelm Friedrich Hegel in the form of a lit inscription—the quote reads … daß diese Furcht zu irren schon der Irrtum selbst ist.—loosely translated as "… that this fear of making a mistake is a mistake itself." The inscription is a work by the artist Joseph Kosuth from the early 1990s. In the main hall, near the south exit, there is a DB Lounge for first-class passengers, bahn.comfort (a customer loyalty program) customers and first class and "Senator" AIRail passengers. Schillerstraße (Arnulf-Klett-Platz) in front of the station is used by up to 50,000 vehicles a day.[55] OperationsIn 1994, Stuttgart Hauptbahnhof was the source of 49,400 passengers in regional traffic (excluding the S-Bahn) and 39,000 in long-distance traffic (ICE, IC, IR) each day.[56] With about 210,000 passengers per day, the station was the biggest in Baden-Wuerttemberg in 2005.[57] More than 12,000 people transferred daily between Stadtbahn and regional services in 2014. According to DB data 164 long-distance trains, 426 regional trains (as of 2009)[24] and 650 S-Bahn trains (as of 2005) serve the station daily. Long-distance connectionsThe most significant long-distance connections available at the Stuttgart Hauptbahnhof are listed here:
Regional connections
In most cases, these connection start or end in Stuttgart. This means that for most connections that go through Stuttgart Hauptbahnhof, a change of trains is necessary. As part of the Stuttgart 21 project, with Stuttgart Hbf becoming a through-station, most regional connections would no longer require the change of trains. Among the seven local regional lines starting in Stuttgart, the line to Tübingen, with an average of 32,100 passengers during the week, was the most used in 2014.[58] S-Bahn connections
The abbreviation for the Hauptbahnhof S-Bahn station underground is TST. The station is to be modernised between the end of 2019 and the end of 2020 at a cost of €9 million.[59] Freight trafficIn addition to the passenger station, there used to be a closed and already demolished freight station and small shunting station, which featured a marshaling hump with rail brakes. The freight yard was used until the 1980s.[60] The goods traffic was later completely shifted to the Kornwestheim marshalling yard; the decision to move was made independently of the Stuttgart 21 project.[61] StadtbahnUnder the Arnulf-Klett-Platz (the station forecourt), the largest and most important node of the Stadtbahn features these routes:
In addition, in case of events at the NeckarPark and Cannstatter Wasen
NoteworthyThe Hauptbahnhof has been assigned the IATA code ZWS, because the station is used by Lufthansa in the AIRail concept. Passengers may travel in ICE trains, which are also assigned flight numbers, to Frankfurt Airport in Frankfurt am Main, instead of using a short-distance flight. For this reason, Lufthansa has a check-in counter near the entrance from the Arnulf-Klett-Platz. Passengers were able to both check and receive their baggage at this counter until 2007; since then, only check-in is possible. District of the city centreHauptbahnhof has also been the name of one of ten sub-districts of the district of Stuttgart-Mitte (central Stuttgart) since 2007. This district has only a few residential buildings, so its population was 287 in 2014. Previously it was called Klettplatz. Stuttgart 21{{main|Stuttgart 21}}As part of the Stuttgart 21 project, the two wings were demolished. There has been widespread resentment of the entire project to place the main lines underground, leading to significant protests, in particular in response to the felling of some 260 huge and old trees. More than 18,000 people have registered as Parkschützer (park guardians); about a thousand vowed to stay in the path of demolition crews while chaining themselves to the trees. The colourful resistance led to nearly daily demonstrations and became a major factor in the 2011 state elections. The Stuttgart architect and Bonatz expert Matthias Roser initiated an international call for the preservation of the Hauptbahnhof, including the wings, and over 400 architects, building historians, monument conservators, art historians, and city planners, such as the Pritzker Architecture Prize recipients Richard Meier and David Chipperfield, joined this effort. This group viewed the Bonatz-designed building as one of the most significant railway station structures of the 20th century in Germany and Europe as a whole, and were opposed to any structural changes. On 27 November 2011, a referendum on the project "Stuttgart 21" resulted in 58.8% voted in favor of the project, while 41.2% voted against it.[62] In order to provide necessary space for the new station's construction—next to the main building, where the ends of the platforms used to be—the platforms had to be moved away from the building, and the track layout underwent significant changes. In the process, three trains derailed on different occasions in 2012. OverviewStuttgart 21 is a transport and urban development project under construction for the complete reorganisation of the Stuttgart railway junction. The existing terminus is to be rotated by about 90° and converted into a through station with eight tracks. For this purpose, the approach track are being laid in tunnels from all directions. The aim is to increase the capacity of the station, to shorten transfer routes and to reduce maintenance costs.[63] During the debate surrounding the project, critics proposed several alternative plans, including the extensive refurbishment and the progressive redevelopment of the existing station under the concept of Kopfbahnhof 21 (terminus 21). In the feasibility study submitted in 1995, the cost of the underground station (today's planning approval section 1.1, excluding the access tracks required by its new location) was estimated at DM 930 million (€476 million).[64] In 2009, the costs were estimated at €400 million.[65] According to the overall planner Ingenhoven, the calculated costs are less than ten percent above the original cost estimate (as of 2013).[66] Deutsche Bahn AG estimates that the expenditure of approximately €110 million will be required for the continued "third-party use" of the Bonatz building, which is not part of the Stuttgart 21 project.[67] Planned measuresThe station is covered by the planning approval for section 1.1 of the Stuttgart 21 project.{{Sfn|Planning approval|2005}} The application for planning approval of the first section of Stuttgart 21 was submitted on 31 October 2001.[68] The five-day hearing of objections closed on 11 April 2003 after more than 50 hours of debate. It was considered the largest and most complicated hearing in the history of the Stuttgart regional council.[69] Planning approval was granted by the Federal Railway Authority (Eisenbahn-Bundesamt) on 28 January 2005 and became final in June 2006.[70] The Bund für Umwelt und Naturschutz Deutschland (BUND) lodged a class action against the approval.[71] By mid-2015 there had been fourteen amendments to the plan, including fundamental changes such as the doubling of the groundwater extraction rate (seventh amendment of the plan), the installation of additional escape stairs (sixth amendment) and the shortening of the channel carrying the Nesenbach (stream) and the adoption of an open design for it (14th amendment).[72] In July 2015, a further amendment to the plan was announced, which means that the smoke extraction building in Sängerstraße will remain unchanged externally, but will receive a significantly more efficient ventilation system.[73] Pedestrian networkThe four 420-metre-long island platforms will have a width of 10 metres and will be 1.60 metres wider than the platforms of the current terminus.[74] The comfort of passenger movements resulting from the planned entrances, footbridges, stairs, lifts and platforms was examined in a pedestrian flow analysis. In the peak hour, the traffic quality is mainly in the range of quality level C ("limited speed selection") and partly in the range of quality level D ("clearly limited speed choice"), outside the peak hour, quality levels A and B (free or almost free flow of traffic) is achieved.[75] Track layoutThe station is to have eight platform tracks, which are to be connected at both ends of the station to four access tracks:
The two ends of the station are planned to be grade separated with flying junctions. From each of the four directions of approach, trains will be able to reach five of the eight platform tracks. The two middle platform tracks will be able to be used by trains from all four directions. The planned entry speed on the approach tracks is 60 km/h (outer tracks), 80 km/h and 100 km/h (island platform 4 and 5). Blocked paths would also be avoided by a flexible choice of approaches from the existing lines.[76] The number of sets of points (each outside the operations of the station) will decrease compared to the current terminus from 225 to 48.[77] Already in the course of the "preliminary project" initiated in early 1995, the track plan of the planned underground station had been optimised for directional operation to such an extent that all platforms operating in each direction could be reached from all incoming tracks.{{sfn|Planning approval|2005|pages= 59–67}} The plan for the northern end of the station had been changed compared to the plan submitted to the regional planning procedure after an anhydrite deposit was found in the geotechnical investigation. The nearest entrance and exit turnouts were shifted by about 150 metres towards the station. The transition from two twin-track tunnels to four single-track tunnels was also preferred.[78] The planned station hall measures 447 metres in length and 80.58 metres in width,[71] at a height of 10 to 12 metres.[7] The building will be founded on a 1.60 to 2.50 metre thick plate and anchored by 3,700 piles.[79] The base of the building will lie between 6 and 8 metres below the water table.[80] Between the lowest point of the foundations and the groundwater, according to the promoter, there would be a water-impermeable layer more than 35 metres thick.[79] The new station can only be built as cut and cover to avoid disturbances to the level of the groundwater.[81] The planning approval section begins in the northwest at line-km -0.442. At this point, in the area of Jägerstraße 24, the connecting tunnels, which have been constructed using a mining method, open out into the station. The gradient initially drops from an altitude of 241 metres (at the railhead; ground altitude: 258 metres) to the south for 404 metres at 1.31 percent and then continues for another 459 metres at a gradient of 1.51 percent, before an inflection point (km +0.345, 230 metres above sea level at the railhead, 12 metres below ground level) at the southern end of the station from which the gradient rises to the end of the section at 0.41 percent. The section limit is at line-kilometre +0.432, in the Willy-Brandt-Platz area, at the junction with the connecting tunnels to be excavated by mining methods.[82] According to the Deutsche Bahn information, a track gradient of up to 1.51 percent is required in the platform area due to several fixed points (Stadtbahn lines and groundwater streams), which is above the ruling limit for station tracks of 0.25 percent. Safe operations are still guaranteed by a bank in the middle of the platforms of 1.0 percent.[83] In March 2016, it was announced that the proof of sufficient security required for operations had not yet been provided. This also makes it unclear what operational restrictions will be required for the increased gradient.[84] Critics see significant risks from trains moving accidentally on this gradient.[85] Station building21 different changes will be made on the remaining part of the former station building, the so-called Bonatz-Bau (Bonatz building), in parallel with the Stuttgart 21 project. The function of the building will be maintained. The building's façades will be preserved using a new structural frame and modern building technology.[127] Construction on the Bonatz building is scheduled to begin in 2018 and be completed 2021.[127] A hotel, restaurant and conference complex with 150 hotel rooms will be built in the above-ground part of the building on four levels. Levels +3 and +4 will be rebuilt, but set back from Schillerstraße so that they do not affect the overall impression of the building from that street.[86] Straßburger Platz ("Strasbourg Square") is to be created on the roof of the through station at the current level of the railway tracks and the current platform hall (the so-called "level +1"). This area, delimited to the south by the Bonatz building and to the north by a new station building, will connect Kurt-Georg-Kiesinger-Platz with the Schlossgarten.[7] Daylight will reach the platforms through 27 4.30 metre-high "high-light eyes" (Lichtaugen).[131]A distribution level with access from the station tower, Königsstraße, Königsallee (Cannstatter Straße) and the new city district is to be created below Straßburger Platz on level 0. The four platforms are to be arranged with eight platform tracks on the lower level ("level −1"). Access to the lower-lying, double-track S-Bahn station is planned below the new platform tracks. A new parking garage is to be built below the northern part of the station building and to the north of it, but underground.[7] Level −2 is to act as the S-Bahn level, including giving access to it.[87] The entrance to the station building is to be built next to the existing entrances and will run through four 23 metres-wide and up to 10 metres-high glass-mesh shells. In total, more than 35 escalators and 15 so-called "panoramic" lifts are planned.[131] The platforms are to be accessed via three distribution points (level 0) near two ticket halls and the Planetarium/Staatsgalerie. Each platform is to be accessed by three lifts, five escalators and five sets of stairs.[7] A new shortcut to the Staatsgalerie Stadtbahn stop is to be built at the eastern end.[76] The main access to the platform level is to be provided by the middle pier (pier B), which is to be accessed via the large ticket hall and the new access to the station tower in the south and the Europaviertel ("European quarter", a new commercial development) in the north. Each of the four platforms is accessed from this ramp via a lift and two escalators and sets of stairs on each side.[88] Critics have noted that the passage is just 2.04 metres wide between the outer edge of the stairs and the platform edge at the point. The western pier (pier A) is to be reached mainly via the new access at Kurt-Georg-Kiesinger-Platz and the small ticket hall. From this pier, each platform is accessed via a lift and an escalator and a set of stairs on each side.[88] The passage is 2.85 metres wide at its narrowest point.[88] The eastern pier (pier C) is appraached via the entrance from the Staatsgalerie, which can be reached by a pedestrian tunnel. An elevator as well as two escalators and two sets of stairs are planned at the exit to the Staatsgalerie. It has no access to piers A and B and thus no access to the Bonatz building. From the distribution level, each platform is connected by a lift and an escalator and a set of stairs to the west. The passage width between the stairs and the platform edge is 2.86 metres.[88] After the commissioning of Stuttgart 21, an additional station building will be built on the opposite side of the new through station, which will serve as a station access from the north and will also accommodate operating rooms. Alteration of the Stadtbahn line under Heilbronner Straße was due from mid-2011 to mid-2014[141] and of the Staatsgalerie Stadtbahn station from February 2013.[89] Among the numerous other construction measures is the relocation of the Nesenbach (construction was originally planned for late 2011 to mid-2014,[141] but started in June 2015[90]) and the West[91] main drains. Light and air conditioningThe rail infrastructure is designed as a zero-energy building: the air conditioning will be operated exclusively using geothermal energy, assisted by the cooling effect of incoming trains.[92] The temperature in the platform area should also not fall below ten degrees without artificial heating (at an external temperature of −20 degrees Celsius) or exceed 29 degrees.[147] The "high-light eyes" will also be able to be opened for ventilation and smoke extraction.[7] Experiments have shown that the station concourse will be lit naturally by the high-light eyes for up to 14 hours daily and will be able to cope during this period without artificial light. Floor lights at the edge of the platform will mark the edge of the platform next to the track bed.[7] On average, 5 percent of daylight would enter the interior, but under the high-light eyes, this proportion would rise to 10 to 15 percent.[93] HistoryPlanningOn the basis of "operational considerations", the station considered for the feasibility study at the beginning of 1995 provided for eight platforms with four 10-metre-wide and 420-metre-long island platforms. The tracks, which would be dedicated to operations in a particular direction, would have had connecting passages in the tunnels running from the platforms. To the northwest, two twin-track connecting tunnels were to run in parallel and after a sharp curve to the northeast would divide south of Mittnachtstrasse station (in the Wolframstraße area) into a branch towards Feuerbach and a branch towards Bad Cannstatt. To the southeast, four single-track tunnels were to be built directly to the turnout halls (two to Obertürkheim and Untertürkheim and two to the Airport). Under the design presented as an example, the Bonatz Building would have been preserved and an additional entrance would have been created in the side wing on Cannstatter Straße. The railway layout would be built at a gradient of up to 1.1 percent.[151] According to the feasibility study, the costs of the section including the station and the valley crossing, would amount to DM 928 million (DM 807 million plus 15 percent for planning costs, 1993 prices),[94] which on an inflation-adjusted basis would have amounted to €{{Inflation|DE|928|1993}} million. The Synergiekonzept Stuttgart 21 ("synergy concept") presented at the end of 1995 provided for an eight-track through station with three island and two outer platforms. Traffic forecasts expected an increase to 70,400 long-distance and 53,100 regional passengers each day. The share of through traffic in total traffic in 2010 was projected to be around 50 percent for long-distance and just under 20 percent for regional services (54,000 and 13,000 passengers each day).[56] The plan was later modified so that four island platforms are now planned on the concourse. A regional planning process (Raumordnungsverfahren) was carried out for the Stuttgart 21 project in 1996 and 1997. The through station solution favoured by Deutsche Bahn was examined as a proposed route with different suboptions. These included options with different platform positions, numbers of track and possibilities for further development.[154] Other options, which deviated from the basic concept of a pure through station at the location of the existing terminus station, were mentioned in the spatial planning process, but were not examined to the same depth: the "lean" option provided for a continuation of the terminal station, while the "Kombi" option provided for the construction of a through station for long-distance traffic, but the terminal station would also be maintained. In addition, a Hauptbahnhof am Rosenstein (main station on Rosenstein ridge) option was considered, which would have involved abandonment of the current station. In addition, station locations in Bad Cannstatt and Untertürkheim were considered.[95] On 28 February 1997, a Europe-wide architectural competition for the redesign of the station was announced.[96] The new station should be a "visible sign of pioneering mobility and a landmark for Stuttgart and its region".[7] In a two-stage process, 19 participants out of 118 applicants who had initially submitted a concept were selected for a second round. A jury chaired by Klaus Humpert selected four equal winners in July 1997.[97] The four award-winning designs and six other designs were displayed in Stuttgart Hauptbahnhof from 11 August to 14 September 1997.[98] All four designs provided a station rotated by 90 degrees with daylight illumination.[97] On 4 November 1997, the design of the office of Ingenhoven, Overdiek, Kahlen and Partner[96] was finally chosen from the 126 submissions.[96] Ingenhoven's concept at that time was to build the station underground at a cost of DM 350 million (equivalent to about €{{Inflation|DE|350|1997}} million) and to illuminate it with daylight from 27 light shafts, each 15 metres wide. The support structure of the station concourse was developed by Frei Otto.[99] The draft had been revised several times already in the competition.[100] Four designs were available in the final round.[96] In 2005, the design received the MIPIM Future Project Award from the magazine Architectural Review as well as a Silver Award at the regional Holcim Awards[101] and a Golden Award in the global competition the following year.[102] In 2007, the design was awarded one of 58 International Architecture Awards from the Chicago Athenaeum.[103] By 2006, the €2.8 billion estimated total cost of Stuttgart 21 included almost €800 million for the Hauptbahnhof.[104] The architect, Christoph Ingenhoven, received €36 million.[105] A modified building design was presented at the end of August 2010.[106] Among other things, the size of the four entrances was reduced and routing and acoustics were revised. Heiner Geißler, who was entrusted with the task of conciliating views in relation to the Stuttgart 21 project, suggested in his conciliatory appeal on 30 November 2010 that the safety of rail traffic, accessibility and fire safety of the through station should be improved. In addition to improvements to the track, a ninth and tenth platform track at the main station should also be investigated.[107]On 23 April 2015, the Federal Railway Authority approved, among other things, the construction of two escape staircases per platform and changes to the shells surrounding the four direct entrances from the outside.[108] The planning amendment notice for the displacement of the evacuation staircases planned on the platforms to the ends of the station hall was delayed and is now expected in the summer of 2017.[109] Ingenhoven reported that the cost of the station at the end of 2017 was "well below" €1 billion.[110] ConstructionWith the symbolic start of construction on 2 February 2010 reconstruction work began on the track apron; these were necessary for the construction of the cross-platform concourse at the end of the platforms.[111] The contract to demolish the north wing was awarded to Wolff & Müller on 18 May 2010.{{citation needed|date=July 2018}} The establishment of the worksite began on 30 July 2010 under police protection[112] and the demolition of the facade of the north wing began on 25 August 2010. Work on the denolition of the south wing began on 13 January 2012 with the gutting of the building.{{citation needed|date=July 2018}} The exterior demolition of the building began on 30 January and was due to be completed in March 2012.[54][113] After a pillar of the platform canopy was damaged on 19 March, work was suspended for about three weeks.[114][115] After further damage due to gale-force gusts on 1 July 2012, platform 15/16 was blocked off again and work started on the upgrade of the glass panes on all platform canopies.[116] The approximately 110-meter-wide excavation was due to be bridged by two ten-metre-wide bridges[117] by April 2014.[184] In addition direct access was to be provided to the cross-platform concourse from both sides. Access to the Europaviertel district on the north side has been possible since 21 October 2013[39] and on the south side[118] there has been access via the pedestrian walkways from the Mittlerer Schlossgarten since 24 January 2014. Both entrances are barrier-free.[39] The repositioning of the cross-platform concourse was postponed several times. According to the planning status of March 2012, the cross-platform concourse was to be gradually advanced between July and December 2012.[119] At the end of June 2012, just over 50 of the 61 planned construction phases had been completed on the track apron. Platform tracks 1 and 2 were re-connected without completing the planned construction of the new S-Bahn tunnel in this area.[116] Construction of the new cross-platform concourse took place from late May 2013 to 22 October 2013 in 13 phases, requiring two platform tracks were blocked off. Deutsche Bahn reduced some train services during this period to reduce congestion of trains at the station.[190] The preliminary work and the commissioning of the cross platform, 120 metres north of its original location, should have taken 18 months to complete, but actually lasted 45 months.[120][39] A two-storey underground engineering building of 1,800 square metres was built under the former parking lot at the northern exit at a planned cost of €7.6 million[121] between April 2012[194] and October 2013 (when the construction of the shell was completed)[39][122] On 12 March 2012, the construction contract for the underground station, including the West, Cannstatter Straße and Nesenbach channels and the station access tunnel, was awarded to a consortium of the Züblin (manager) and Strabag companies.[197][123] The formal award took place on 24 March 2012.[124] The contract for the construction of the new central station was let for €323.4 million,[125] which was a sliding price under the contract.[126] The internal portion being built by Züblin amounts to around €300 million.[124] Groundwater management is not part of the scope of the contract.[127] The total contract value was €347.4 million in May 2016[128] and €364 million in August 2016.[129] At the end of 2010, the lowest tender for the construction of the underground station amounted to about €360 million.[130] The first contract planned to be let in late 2011 was delayed over price negotiations.[131] Also technical questions led to delays.[127] In addition to successful negotiations, technical optimisations, such as a change in the type of concrete, would have contributed to savings, according to a media report.[132] Deutsche Bahn had calculated a price of €300 million based on its own data.[126] In July, September and October 2012[133] trains derailed on the exit towards Feuerbach, which had been rebuilt in the course of the Stuttgart 21 project.[134] Following the latest derailment, platform tracks 8, 9 and 10 were blockaded.[135] In January 2013, Deutsche Bahn justified the derailments as being the result of "malfunctioning carriage buffers".[190] A short-term technical solution developed by DB was rejected by the Federal Railway Authority.[136] The suspension also led to far-reaching delays of S-Bahn and regional services.[137] On 22 January 2013, track 10 was conditionally released for service. Only multiple units and hauled trains could use it. According to Federal Railway Authority data, the unrestricted clearance of the track was not possible on the basis of documents that had been submitted.[138] According to Deutsche Bahn in December 2014, an end to these restrictions was not foreseeable.[139] In March 2012, the beginning of civil engineering work was scheduled for early 2013.[140] The civil works on the excavation of the station began on 5 August 2014 at pit 16 in the Mittleren Schlossgarten.[141] A mid-2013 timetable for the excavation work in the Mittleren Schlossgarten was considered obsolete by mid-2014. Out of 14 construction stages planned so far, 7 had been realised and the work had been delayed by about five months.[142] An already issued statistical proof of the safety of the station has not applied since 2014 due to changed legal requirements and a renewal is pending.[143] Civil engineering work at the station was stopped at the beginning of March 2015 because a permit from the Federal Railway Authority for the construction of additional escape staircases was missing. The work was thus eight months late compared with early projections.[144] On 26 January 2016, one year later than scheduled under the August 2014 timetable, work began on casting the floor slab in the first excavation pit of the station, initially as the base plate in what is known as the Medienkanal (middle channel).[145] The concreting of the first roof stanchions was due to start in June 2017. The 28 columns are to be concreted two at a time.[146] In mid-2017, the building of the former Deutsche Bahndirektion (Deutsche Bahn divisional headquarters) was undermined and placed on a 1.3 m thick concrete slab. This rests in turn on some supports, between which the construction machinery and vehicles can operate. DB had sought the demolition and reconstruction of the building built in 1911–1912. The city of Stuttgart, however, insisted on its preservation.[147] Groundwater managementThe groundwater has been lowered by approximately seven metres by pumping for the construction of the excavations. The resulting funnel of lowered groundwater usually extends for several hundred metres. In order to reduce the disturbance, water is reintroduced (infiltration via injection well) in the vicinity of the construction excavations. The groundwater must be treated prior to being reintroduced to reduce possible pollution.[148] The management of groundwater was originally expected to involve around three million cubic metres of groundwater. Following a change in the plan at the beginning of 2011, this figure doubled to 6.8 million cubic metres, necessitating an amendment to the license in relation to its scope and impact.[149][150] The groundwater management was expected to start in January 2013.[119] On 25 June 2012, it was announced that a public hearing was required to consider Deutsche Bahn's proposal to double the groundwater withdrawal to 6.8 million cubic metres, delaying the construction work (according to media reports, to 2014). According to its own statements, Deutsche Bahn's planned to open excavation pits requiring less groundwater withdrawals in the spring of 2013 and thus comply with the planning approval decision (which stipulates lower withdrawal quantities).[151] According to a media report, however, the Federal Railway Authority and the Stuttgart Regional Council assumed that the construction work would not begin before 2014.[152] The Federal Railway Authority approved the increased groundwater abstraction on 22 September 2014.[153] FutureIt is planned to successively carry out the construction of the valley crossing and the station in 25 subsections.[154] The shell of the station was expected to be completed by the end of 2017 (as of January 2011).[155] The Staatsgalerie Stadtbahn station is being relocated to the south side of the future station.[156] Preparatory measures started at the end of 2014, when completion was scheduled for 2019/2020 at the latest.[157] The excavated material is transported via separate construction roads and a conveyor belt to a central logistics area at Stuttgart Nord station and transported from there on freight trains. The commissioning of the new station is scheduled for December 2021. A traffic forecast for 2025 anticipates around 207,600 long-distance and regional passengers, including 118,800 from the direction of Feuerbach and Bad Cannstatt and 88,800 from the Filder Tunnel, Obertürkheim or Untertürkheim.[158] The accessibility of the Stuttgart Hauptbahnhof traffic cell by public transport from the Stuttgart region, based on weighted average traffic demand, should improve, according to a traffic forecast from 32 minutes (2010) to 31 minutes (2025).[159] Stuttgarter Netz AG, a consortium of several private railway companies, intends to operate part of the existing terminal station. The company expects up to 100 trains to stop at the station every working day. Eight tracks of the terminal station, the access tracks from Bad Cannstatt, Feuerbach and Vaihingen and the existing signal box would be preserved for this purpose. Overall, a quarter of the existing area would be preserved. The calculated annual costs of €1.6 million are expected to be offset by revenue from train and station operations of €1.8 million. Among other things, secondary lines such as the Schönbuch and the Wieslauf Valley Railways would be connected with Stuttgart Hauptbahnhof.[160]Rail operationsAccording to a simulation commissioned by the promoters, the optimum performance range of the through station lies between 42 and 51 trains per hour, while for an upgraded terminal station (the Kopfbahnhof 21 concept) it would be 28 to 38 trains per hour. The maximum flow will be 72 trains in the through station or 43 trains per hour in the terminal station.[161] In 2002, Deutsche Bahn estimated a capacity increase of 50 percent for the 8-track through station compared to the 16-track terminal station; with an upgrade of the approach tracks from Feuerbach, 125 percent more trains would be able to run during the peak.[77] Critics doubt these claims.[162] Nahverkehrsgesellschaft Baden-Württemberg (a state agency that helps coordinate public transport operations) confirmed its opinion that the existing terminal station could already carry 50 trains and, with improved signalling technology, it would carry 56 trains an hour.[163] ReferencesFootnotes{{Portal|Stuttgart}}1. ^{{cite map |url=http://www.openrailwaymap.org/index.php?lang=en&lat=48.7856098758287&lon=9.18339585202065&zoom=18&style=standard |title=Map of Stuttgart Hauptbahnhof |publisher=OpenRailwayMap |date=28 September 2014 |map=OpenRailwayMap |mapurl=http://www.OpenRailwayMap.org |cartography=OpenStreetMap |accessdate=19 October 2014}} 2. ^{{cite web |url=http://www.bahnhof.de/file/6745348/data/Stuutgart_Hbf_Lageplan_PDF.pdf |title=Lageplan Hauptbahnhof Stuttgart |language=German |publisher=Deutsche Bahn AG |year=2014 |format=PDF |type=orientation map |accessdate=19 October 2014}} 3. ^{{cite book|title=Eisenbahnatlas Deutschland (German railway atlas)| edition=2009/2010 |publisher= Schweers + Wall|date=2017|isbn= 978-3-89494-146-8}} 4. ^1 {{DBCatsURL}} 5. ^{{cite web |url=http://content.stuttgarter-nachrichten.de/stn/page/2290375_0_6767_-plan-von-denkmalschuetzern-bonatzbau-soll-weltkulturerbe-werden.html |title=Bonatzbau soll Weltkulturerbe werden |language=German| author= |date=11 November 2009 |work=Stuttgarter Nachrichten |publisher= |accessdate=21 February 2012}} 6. ^{{cite web | url = http://www.baufachinformation.de/denkmalpflege/Alter-Bahnhof-Ursprung-des-UFA-Palastes/1988017186267 | title = Kurztexte zur Denkmalpflege | language=de}} 7. ^1 2 3 4 5 6 7 8 {{cite book|publisher=DB ProjektBau GmbH |title=Stuttgart 21: Talquerung mit Hauptbahnhof |language=de}} (14 page brochure with situation in September 2005) 8. ^{{cite web | url = https://www2.landesarchiv-bw.de/ofs21/bild_zoom/zoom.php?bestand=21279&id=2203151&screenbreite=1440&screenhoehe=870 |archiveurl=https://web.archive.org/web/20160325092207/https://www2.landesarchiv-bw.de/ofs21/bild_zoom/zoom.php?bestand=21279&id=2203151&screenbreite=1440&screenhoehe=870 |archivedate=25 March 2016 |deadurl=no| title = K 412 IV DO 10735, 1 Plan Stuttgart Hbf: Empfangsgebäude 1.Bauabschnitt Lageplan Personenbahnhof | publisher= Landesarchiv Baden-Württemberg, Staatsarchiv Ludwigsburg | date = 1917 | accessdate= 5 June 2018|language=de}} 9. ^{{cite news | url = http://content.stuttgarter-zeitung.de/stz/page/1624458_0_9223_-die-chronik-der-hauptbahnhof-im-spiegel-der-zeit-2-.html | title = Der Hauptbahnhof im Spiegel der Zeit (2) | newspaper= Stuttgarter Zeitung | archiveurl = https://web.archive.org/web/20130321085237/http://content.stuttgarter-zeitung.de/stz/page/1624458_0_9223_-die-chronik-der-hauptbahnhof-im-spiegel-der-zeit-2-.html | archivedate = 25 March 2013 | date = 22 January 2008 | accessdate= 5 June 2018|language=de}} 10. ^{{cite journal | first1= Walter | last1=Lambert| first2=Willi | last2=Keckeisen | title= Stadtbahn Stuttgart | journal = Die Bundesbahn | volume= 30 | issue= 21 | date= 1956 | pages= 1159ff|language=de}} 11. ^{{cite book|publisher=Standard Elektrik Lorenz |title=Zentralstellwerk Stuttgart Hauptbahnhof|date=c. 1978|pages=9, 12f., 15, 38|language=de}} (40 page brochure) 12. ^{{cite book|publisher=Bundesbahndirektion Stuttgart |title=Der Tunnel|location=Stuttgart |year=1985 |isbn= 3-925565-01-9 |page=218|language=de}} 13. ^{{cite news | first= Michael |last=Isenberg | title= Turm steht wohl auf Eisenbetonpfählen | newspaper= Stuttgarter Nachrichten | date= 22 August 2013 | page= 20|language=de}} 14. ^{{cite journal|first=Dirk |last=Valleé |title=Nachhaltige Leistungssteigerung im Stuttgarter S-Bahn-Netz |journal=Der Nahverkehr |issue=7/8 |date=1997 |pages=35–41|language=de}} 15. ^{{cite news | first= Konstantin |last=Schwarz | title= 43000 Fahrgäste vom Umbau betroffen | newspaper= Stuttgarter Nachrichten | date= 21 October 2015 | page= 16 | url= http://www.stuttgarter-nachrichten.de/inhalt.halt-staatsgalerie-43000-fahrgaeste-von-umbau-betroffen.983dc2d7-783e-46cd-8d64-df61cde79273.html|archiveurl=https://web.archive.org/web/20171110152454/http://www.stuttgarter-nachrichten.de/inhalt.halt-staatsgalerie-43000-fahrgaeste-von-umbau-betroffen.983dc2d7-783e-46cd-8d64-df61cde79273.html|archivedate=10 November 2017|deadurl=no|accessdate=7 June 2018|language=de}} 16. ^{{cite news | title= Bus und Bahn in der Region und die Nahverkehrsgesellschaft Baden-Württemberg | newspaper = Stuttgarter Nachrichten | volume= 72 | issue= 24 | date= 30 January 2016 | page= 20|language=de}} 17. ^1 2 3 4 {{cite web | url = http://www.landgericht-stuttgart.de/servlet/PB/menu/1254450/index.html?ROOT=1169294|archiveurl=https://web.archive.org/web/20100524021221/http://www.landgericht-stuttgart.de/servlet/PB/menu/1254450/index.html?ROOT=1169294|archivedate=24 May 2010 | title = Urteilsgründe in Sachen Dübbers ./. Deutsche Bahn | publisher= Stuttgart Regional Court | date = 20 May 2010 | accessdate= 7 June 2018|language=de}} 18. ^{{cite book|first=Walter |last=Carlé |title=Geologische Karte 1:25000 von Baden-Württemberg, Erläuterungen zu Blatt 6826 Crailsheim |publisher=Geologisches Landesamt Baden-Württemberg|location= Stuttgart |date=1980|language=de}} 19. ^1 {{cite news | url = http://www.faz.net/aktuell/feuilleton/kunst/stuttgart-21-architekt-im-gespraech-der-geist-will-nicht-in-die-flasche-zurueck-1576901.html|archiveurl=https://web.archive.org/web/20120901022505/http://www.faz.net/aktuell/feuilleton/kunst/stuttgart-21-architekt-im-gespraech-der-geist-will-nicht-in-die-flasche-zurueck-1576901.html|archivedate=1 September 2012|deadurl=no | title = Der Geist will nicht in die Flasche zurück | first= Dieter |last=Bartetzko | newspaper= FAZ.NET | accessdate= 10 June 2018 | date = 23 August 2010|language=de}} 20. ^{{cite web|url=http://stredax.dbnetze.com/Dokumente/ISR/BS/NBS/T/TS_NBS.pdf|archiveurl=https://web.archive.org/web/20160304100517/http://stredax.dbnetze.com/Dokumente/ISR/BS/NBS/T/TS_NBS.pdf|archivedate=4 March 2016|deadurl=no|title=Track plan for Stuttgart Hauptbahnhof|publisher=DB Netze|accessdate=10 June 2018|language=de}} 21. ^1 2 3 4 {{cite journal | last = Reichsbahnoberrat Rempis | title= Die Vollendung der Stellwerkanlage auf dem neuen Hauptbahnhof Stuttgart | journal = Organ für die Fortschritte des Eisenbahnwesens | volume = 13 | issue = Neue Folge 65 | date = 1928|language=de}} 22. ^{{cite news | url = http://content.stuttgarter-zeitung.de/stz/page/1792902_0_9223_-stellwerk-am-hauptbahnhof-die-herrscher-ueber-hunderte-von-weichen-und-signalen.html | title = Stellwerk am Hauptbahnhof: Die Herrscher über Hunderte von Weichen und Signalen | first= Thomas |last=Thieme | newspaper= Stuttgarter Zeitung | archiveurl = https://web.archive.org/web/20110703062853/http://content.stuttgarter-zeitung.de/stz/page/1792902_0_9223_-stellwerk-am-hauptbahnhof-die-herrscher-ueber-hunderte-von-weichen-und-signalen.html | archivedate = 3 July 2011 | date = 20 August 2008 | accessdate= 10 June 2018|language=de}} 23. ^1 2 3 4 5 {{cite web | url = http://www.landesarchiv-bw.de/plink/?f=2-1946674-1 | title = K 412 IV DO 11687, 1 Plan Stuttgart Hbf: Bf. Stuttgart Hbf | publisher= Landesarchiv Baden-Württemberg, Staatsarchiv Ludwigsburg | date = 1 October 1978 | accessdate= 10 June 2018|language=de}} 24. ^1 2 3 {{cite web|url=http://www.deutschebahn.com/site/bahnhoefe/de/sued/stuttgart__hbf/daten__und__fakten/daten__und__fakten__.html |archiveurl=https://web.archive.org/web/20100608034633/http://www.deutschebahn.com/site/bahnhoefe/de/sued/stuttgart__hbf/daten__und__fakten/daten__und__fakten__.html|archivedate=8 June 2010|title=Stuttgart Hauptbahnhof: 140 Kilometer Gleise auf 82 Hektar Grund |publisher= Deutsche Bahn| accessdate= 10 June 2018|language=de}} 25. ^{{cite web | url = http://direktzu.bahnprojekt-stuttgart-ulm.de/stuttgart21/messages/umsteigen-fuer-radfahrer-29124|archiveurl=https://web.archive.org/web/20130321084611/http://direktzu.bahnprojekt-stuttgart-ulm.de/stuttgart21/messages/umsteigen-fuer-radfahrer-29124|archivedate=21 March 2013|deadurl=no | title = Umsteigen für Radfahrer | first= Udo |last=Andriof | publisher= Direktzu Stuttgart 21 | date = 21 February 2011 | accessdate= 10 June 2018|language=de}} 26. ^{{cite web | url = https://www.deutschebahn.com/de/geschaefte/infrastruktur/bahnhof/bahnsteige_uebersicht/2235752/bahnsteige_details.html?rid=6071 |archiveurl=https://web.archive.org/web/20160525063148/https://www.deutschebahn.com/de/geschaefte/infrastruktur/bahnhof/bahnsteige_uebersicht/2235752/bahnsteige_details.html?rid=6071 |archivedate=25 May 2016 | title = Platform information: Stuttgart Hbf | publisher= Deutsche Bahn | date = 20 April 2016 | accessdate= 11 June 2018|language=de}} 27. ^1 {{cite journal | first1=Rolf |last1=Grüter| first2=Karl-Heinz|last2=Böttcher | title= S-Bahn Stuttgart: Bauwerke der Tunnelstrecke Hauptbahnhof-Schwabstraße | journal = Die Bundesbahn | issue= 5 | date= 1976 | issn= 0007-5876 | pages= 317–325|language=de}} 28. ^1 2 3 4 {{cite web | url = http://www.bahnprojekt-stuttgart-ulm.de/dialog/turmforum/geschichte/ |archiveurl=https://web.archive.org/web/20120426080433/http://www.bahnprojekt-stuttgart-ulm.de/dialog/turmforum/geschichte/|archivedate=26 April 2012| title = Turm-Geschichte | publisher= Bahnprojekt Stuttgart-Ulm e. V. | accessdate= 11 June 2018|language=de}} 29. ^{{cite web | url = https://www2.landesarchiv-bw.de/ofs21/bild_zoom/zoom.php?bestand=21279&id=2203117&screenbreite=1440&screenhoehe=870 | title = K 412 IV DO 10702, 1 Plan Stuttgart Hbf: Empfangsgebäude Turm Fundament und Pfähle | publisher= Landesarchiv Baden-Württemberg, Staatsarchiv Ludwigsburg | date = May 1914 | accessdate= 11 June 2018|language=de}} 30. ^{{cite news | url = http://www.stuttgarter-zeitung.de/inhalt.sechste-schlichtungsrunde-expertenstreit-um-risiken-im-untergrund.de0977fe-98ea-4ce5-bc2c-8ce3fa43f062.html |archiveurl=https://web.archive.org/web/20161226122947/http://www.stuttgarter-zeitung.de/inhalt.sechste-schlichtungsrunde-expertenstreit-um-risiken-im-untergrund.de0977fe-98ea-4ce5-bc2c-8ce3fa43f062.html|archivedate=26 December 2016|deadurl=no| title = Expertenstreit um Risiken im Untergrund | first= Thomas |last=Braun | newspaper= Stuttgarter Zeitung | date = 20 November 2010 | accessdate= 11 June 2018|language=de}} 31. ^{{cite news | url = http://www.stuttgarter-zeitung.de/inhalt.stuttgart-21-bahnhofsturm-steht-offenbar-auf-eichenpfaehlen.9cf5872c-28ec-4950-879c-38dda5fa5c4d.html |archiveurl=https://web.archive.org/web/20170427215136/http://www.stuttgarter-zeitung.de/inhalt.stuttgart-21-bahnhofsturm-steht-offenbar-auf-eichenpfaehlen.9cf5872c-28ec-4950-879c-38dda5fa5c4d.html |archivedate=27 April 2017|deadurl=no| title = Bahnhofsturm steht offenbar auf Eichenpfählen | first = Thomas |last=Durchdenwald | newspaper= Stuttgarter Zeitung | date = 19 August 2013 | accessdate= 11 June 2018|language=de}} 32. ^{{cite news | url =http://www.stuttgarter-zeitung.de/inhalt.stuttgart-21-bahnhofsturm-bahn-haelt-bohrungen-fuer-ueberfluessig.24f05a58-e4c7-45f9-9191-6ffbb798db45.html |archiveurl=https://web.archive.org/web/20160215225119/http://www.stuttgarter-zeitung.de/inhalt.stuttgart-21-bahnhofsturm-bahn-haelt-bohrungen-fuer-ueberfluessig.24f05a58-e4c7-45f9-9191-6ffbb798db45.html|archivedate=15 February 2016|deadurl=no|title=Bahn hält Bohrungen für überflüssig |newspaper=Stuttgarter Zeitung |date=21 August 2013 | accessdate= 11 June 2018|language=de}} 33. ^1 2 3 4 {{cite web | url = http://www.hauptbahnhof-stuttgart.eu/stuttgarter_hauptbahnhof_geschichte_04.html|archiveurl=https://web.archive.org/web/20160307215114/http://www.hauptbahnhof-stuttgart.eu/stuttgarter_hauptbahnhof_geschichte_04.html|archivedate=7 March 2016|deadurl=no | title = Baubeschreibung und städtebauliche Einbindung | first= Matthias |last=Roser | publisher= Arbeitsgemeinschaft Hauptbahnhof Stuttgart | accessdate= 11 June 2018|language=de}} 34. ^{{cite journal|title=Der Stuttgarter Hauptbahnhof und die sehenswerten Gaststätten im Bahnhofsturm|journal=Das Bunte Blatt |issue=40|date=1926 |pages=649–650|language=de}} 35. ^1 {{cite web | url =http://www.stuttgart.de/item/show/315320/1 | title = Bahnhofsturm – Heiraten | publisher= Landeshauptstadt Stuttgart | accessdate= 11 June 2018|language=de}} 36. ^{{cite web | url = http://www.hauptbahnhof-stuttgart.eu/kopfbahnhofsteighalle_01.html | title = Kopfbahnsteighalle | first= Matthias |last=Roser | publisher= Arbeitsgemeinschaft Hauptbahnhof Stuttgart | accessdate= 11 June 2018|language=de}} 37. ^{{cite web | url = http://www.landesarchiv-bw.de/plink/?f=2-1945989-1 | title = K 412 IV DO 11007, 1 Plan Stuttgart Hbf: Empfangsgebäude Kopfbahnsteighalle Bauzeitenplan für Überdachung | publisher= Landesarchiv Baden-Württemberg, Staatsarchiv Ludwigsburg | date = 10 May 1950 | accessdate= 11 June 2018|language=de}} 38. ^1 2 {{cite web | url = http://www.landesarchiv-bw.de/plink/?f=2-1945857-1 | title = K 412 IV DO 10888, 1 Plan Stuttgart Hbf: Empfangsgebäude Gesamt Grundriss auf Bahnsteighöhe | publisher = Landesarchiv Baden-Württemberg, Staatsarchiv Ludwigsburg | date = 1943 | accessdate= 11 June 2018|language=de}} 39. ^1 2 3 4 {{cite news | url = http://www.stuttgarter-zeitung.de/inhalt.querbahnsteig-fuer-stuttgart-21-neue-wege-in-den-hauptbahnhof.1d81e4c0-994d-4fe6-adb9-04bb2b86d47a.html |archiveurl=https://web.archive.org/web/20170528214048/http://www.stuttgarter-zeitung.de/inhalt.querbahnsteig-fuer-stuttgart-21-neue-wege-in-den-hauptbahnhof.1d81e4c0-994d-4fe6-adb9-04bb2b86d47a.html|archivedate=28 May 2017|deadurl=no| title = Querbahnsteig für Stuttgart 21: Neue Wege in den Hauptbahnhof | first= Markus |last=Heffner | newspaper= Stuttgarter Zeitung | date = 21 October 2013 | accessdate= 13 June 2018|language=de}} 40. ^{{cite web | url = http://www.hauptbahnhof-stuttgart.eu/kleine_schalterhalle_00.html | title = Kleine Schalterhalle | first= Matthias |last=Roser | publisher= Arbeitsgemeinschaft Hauptbahnhof Stuttgart | accessdate= 13 June 2018|language=de}} 41. ^1 {{cite news | url = http://www.tagesspiegel.de/kultur/stuttgarter-hauptbahnhof-seitenfluegel-ohne-aufprallschutz/1640566.html |archiveurl=https://web.archive.org/web/20170518082832/http://www.tagesspiegel.de/kultur/stuttgarter-hauptbahnhof-seitenfluegel-ohne-aufprallschutz/1640566.html|archivedate=18 May 2017|deadurl=no| title = Seitenflügel ohne Aufprallschutz | first= Falk |last=Jaeger | newspaper= Der Tagesspiegel | accessdate= 13 June 2018|language=de | date = 29 November 2009}} 42. ^1 2 3 4 {{cite journal| url = http://www.cloud-cuckoo.net/journal1996-2013/inhalt/de/heft/ausgaben/108/Seeger/seeger.php | title = Architektur der Wege – Neue Wege der Architekturinterpretation am Beispiel des Stuttgarter Hauptbahnhofs | first= Ulrike |last=Seeger | journal=Wolkenkuckucksheim | date = May 2009 | accessdate= 14 June 2018|language=de}} 43. ^1 {{cite journal|title=Bonatz-Bau bleibt Empfangsgebäude für den Bahnhof |journal=Dialog 21|issue= 2 |date=September 2010 |url=http://www.bahnprojekt-stuttgart-ulm.de/mediathek/detail/download/dialog21-ausgabe-2/mediaParameter/download/Medium/ |archiveurl=https://web.archive.org/web/20131203040027/http://www.bahnprojekt-stuttgart-ulm.de/mediathek/detail/download/dialog21-ausgabe-2/mediaParameter/download/Medium/|archivedate=3 December 2013|deadurl=no|format=PDF; 1.0 MiB |page=3|language=de}} 44. ^{{cite web | url = http://www.hauptbahnhof-stuttgart.eu/posttrakt_01.html | title = Posttrakt | first= Matthias|last=Roser | publisher= Arbeitsgemeinschaft Hauptbahnhof Stuttgart | accessdate= 13 June 2018|language=de}} 45. ^{{cite news | url = http://www.stuttgarter-nachrichten.de/inhalt.post-ausgezogen-bahnhof-zum-teilabriss-bereit.83733b25-ced7-4ba2-8ddb-99439379b36b.html |archiveurl=https://web.archive.org/web/20100725112744/http://www.stuttgarter-nachrichten.de/inhalt.post-ausgezogen-bahnhof-zum-teilabriss-bereit.83733b25-ced7-4ba2-8ddb-99439379b36b.html|archivedate=25 July 2018|deadurl=no| title = Bahnhof zum Teilabriss bereit | first= Konstantin |last=Schwarz | newspaper= Stuttgarter Nachrichten | date = 26 July 2010 | accessdate= 13 June 2018|language=de}} 46. ^{{cite book | title= Amtlicher Plan der Landeshauptstadt Stuttgart | publisher= Stadtmessungsamt | location= Stuttgart | edition= 52 | date= 1978 | language= de}} 47. ^{{cite web | url = http://www.boa-bw.de/downloads/redbar//frei/bsz329826409/1/201006-LHS_OB-DrSchuster-PraesentationBahnprojektStuttgartUlm.html.pdf | title = Das Bahnprojekt Stuttgart-Ulm | first= Wolfgang |last=Schuster | publisher= Landeshauptstadt Stuttgart | format = PDF; 15.7 MiB | accessdate= 14 June 2018|language=de | page= 16}} 48. ^{{cite web | url = http://www.bahnprojekt-stuttgart-ulm.de/aktuell/newsdetail/news/bagger-beginnt-mit-dem-abtragen-der-mauern-des-nordfluegels-des-stuttgarter-hauptbahnhofs/newsParameter/detail/News/|archiveurl=https://web.archive.org/web/20120925152220/http://www.bahnprojekt-stuttgart-ulm.de/aktuell/newsdetail/news/bagger-beginnt-mit-dem-abtragen-der-mauern-des-nordfluegels-des-stuttgarter-hauptbahnhofs/newsParameter/detail/News/|archivedate=25 September 2012 | title = Bagger beginnt mit dem Abtragen der Mauern des Nordflügels des Stuttgarter Hauptbahnhofs | publisher= Bahnprojekt Stuttgart-Ulm | date = 25 August 2010 | accessdate= 14 June 2018|language=de}} 49. ^{{cite web | url = http://www.landesarchiv-bw.de/plink/?f=2-1945860 | title = K 412 IV DO 10891 Stuttgart Hbf: Empfangsgebäude Ludwigsburger Straße Grundriss 1. Obergeschoß über Bahnsteig | publisher = Landesarchiv Baden-Württemberg, Staatsarchiv Ludwigsburg | date = 1946 | accessdate= 14 June 2018|language=de}} 50. ^{{cite web | url = http://www.landesarchiv-bw.de/plink/?f=2-1945861 | title = K 412 IV DO 10892 Stuttgart Hbf: Empfangsgebäude Ludwigsburger Straße Grundriss 1. Obergeschoß über Bahnsteig | publisher = Landesarchiv Baden-Württemberg, Staatsarchiv Ludwigsburg | date = 1946 | accessdate= 14 June 2018|language=de}} 51. ^{{cite web | url = http://www.hauptbahnhof-stuttgart.eu/schlossgartenfluegel_00.html | title = Schlossgartenflügel | first= Matthias |last=Roser | publisher = Arbeitsgemeinschaft Hauptbahnhof Stuttgart | accessdate= 14 June 2018|language=de}} 52. ^1 {{cite web|url=http://www.bahnprojekt-stuttgart-ulm.de/uploads/tx_smediamediathek/201110-21_gute_Gruende.pdf|archiveurl=https://web.archive.org/web/20170629164228/http://www.bahnprojekt-stuttgart-ulm.de/uploads/tx_smediamediathek/201110-21_gute_Gruende.pdf|archivedate=29 June 2017|deadurl=no |title=21 Gute Gründe für Stuttgart 21|format=PDF; 1,7 MiB |publisher= Bahnprojekt Stuttgart-Ulm|accessdate= 14 June 2018|language=de}} 53. ^{{cite news | url = http://www.faz.net/aktuell/feuilleton/stuttgarts-hauptbahnhof-der-zug-der-zeit-11010357.html |archiveurl=https://web.archive.org/web/20170421091732/http://www.faz.net/aktuell/feuilleton/stuttgarts-hauptbahnhof-der-zug-der-zeit-11010357.html|archivedate=21 April 2017|deadurl=no| title = Der Zug der Zeit | first= Timo |last=John | newspaper= FAZ.NET | date = 31 July 2010 | accessdate= 14 June 2018|language=de}} 54. ^1 {{cite web| url = http://www.bahnprojekt-stuttgart-ulm.de/aktuell/news-archiv/news-archiv-detail/news/bahn-setzt-baumassnahmen-zu-stuttgart-21-fort/newsParameter/detail/News/datum/20120113/|archiveurl=https://web.archive.org/web/20130321202125/http://www.bahnprojekt-stuttgart-ulm.de/aktuell/news-archiv/news-archiv-detail/news/bahn-setzt-baumassnahmen-zu-stuttgart-21-fort/newsParameter/detail/News/datum/20120113/|archivedate=21 March 2013 | title = Bahn setzt Baumaßnahmen zu Stuttgart 21 fort | publisher= Bahnprojekt Stuttgart-Ulm | date = 13 January 2012 | accessdate= 15 June 2018|language=de}} 55. ^{{cite news | first= Jörg |last=Nauke | title= City-Verschönerung nur mit weniger Autos | newspaper= Stuttgarter Zeitung | volume= 73 | issue= 68 | page= 22 | date= 22 March 2017 | url= http://www.stuttgarter-zeitung.de/inhalt.verkehr-in-stuttgart-city-verschoenerung-nur-mit-weniger-autos.55169214-f999-4ca9-a918-5bddd9c91a19.html |archiveurl=https://web.archive.org/web/20170322075421/http://www.stuttgarter-zeitung.de/inhalt.verkehr-in-stuttgart-city-verschoenerung-nur-mit-weniger-autos.55169214-f999-4ca9-a918-5bddd9c91a19.html|archivedate=22 March 2017|deadurl=no|accessdate=15 June 2018|language=de}} 56. ^1 {{cite book | publisher= Deutsche Bahn AG, Geschäftsbereich Netz, Regionalbereich Stuttgart, Projekte | title = Das Synergiekonzept Stuttgart 21. Die Ergebnisse des Vorprojekts | location= Stuttgart | date = 1995 | pages= 14f | url= http://www.rosenstein-stuttgart.de/fileadmin/downloads/1995_Synergiekonzept_Vorprojekt_Brosch_DB/Synergiekonzept_Vorprojekt_Brosch_1995.pdf |archiveurl=http://www.rosenstein-stuttgart.de/fileadmin/downloads/1995_Synergiekonzept_Vorprojekt_Brosch_DB/Synergiekonzept_Vorprojekt_Brosch_1995.pdf|archivedate=17 September 2017|deadurl=no | format = PDF}} (brochure, 44 A4 pages) 57. ^{{cite journal | publisher= Landtag von Baden-Württemberg | title= Kleine Anfrage des Abg. Boris Palmer und Antwort des Ministeriums für Umwelt und Verkehr: Zustand der wichtigsten Bahnhöfe in Baden-Württemberg | issue= Drucksache 13/4069 | url= http://www.landtag-bw.de/files/live/sites/LTBW/files/dokumente/WP13/Drucksachen/4000/13_4069_D.pdf | format = PDF | date= 16 February 2005 | accessdate= 15 June 2018|language=de | page= 2}} 58. ^{{cite news | first= Oliver |last=Stortz | title= Land der Bahnfahrer | newspaper= Eßlinger Zeitung | date= 11 July 2015 | page= 6|language=de}} 59. ^{{cite web| url=https://gecms.region-stuttgart.org/gdmo/Download.aspx?id=73858 |title=S-Bahn Stuttgart: Modern. Mobil. Für die Region. |first=Dirk |last=Rothenstein |publisher=DB Regio AG |pages=24 f. |date=18 April 2018 |archiveurl=https://web.archive.org/web/20180404135011/https://gecms.region-stuttgart.org/gdmo/Download.aspx?id=73858 |archivedate=4 April 2018|deadurl=no | accessdate=17 June 2018|language=de |format=PDF }} 60. ^{{cite web | url = http://www.bahnprojekt-stuttgart-ulm.de/details/stadtentwicklung/das-europaviertel/ |archiveurl=https://web.archive.org/web/20120426075047/http://www.bahnprojekt-stuttgart-ulm.de/details/stadtentwicklung/das-europaviertel/|archivedate=26 April 2012| title = Das Europaviertel | publisher = Bahnprojekt Stuttgart-Ulm | accessdate= 17 June 2018 |language=de}} 61. ^{{cite web | url = http://www.bahnprojekt-stuttgart-ulm.de/uploads/tx_smediamediathek/PFA_1_1.pdf|archiveurl=https://web.archive.org/web/20121016145855/http://www.bahnprojekt-stuttgart-ulm.de/uploads/tx_smediamediathek/PFA_1_1.pdf|archivedate=16 October 2012 | title = Planfeststellungsbeschluss nach § 18 Abs. 1 Allgemeines Eisenbahngesetz (AEG) für den Umbau des Bahnknotens Stuttgart "Projekt Stuttgart 21" Planfeststellungsabschnitt 1.1 (Talquerung mit neuem Hauptbahnhof) von Bahn-km – 0,4- 42,0 bis Bahn-km + 0,4+32,0 in Stuttgart | publisher = Eisenbahn-Bundesamt Karlsruhe/Stuttgart | date = 18 January 2005 | accessdate= 17 June 2018 |language=de | format = PDF; 2.3 MiB}} 62. ^S21-Gegner scheitern bei Referendum (German) (27 November 2011) 63. ^{{cite web | url = http://www.bahnprojekt-stuttgart-ulm.de/details/neue-bahnhoefe/hauptbahnhof-stuttgart/infrastruktur/|archiveurl=https://web.archive.org/web/20120828180026/http://www.bahnprojekt-stuttgart-ulm.de/details/neue-bahnhoefe/hauptbahnhof-stuttgart/infrastruktur/|archivedate=28 August 2012 | publisher= Bahnprojekt Stuttgart-Ulm e. V. | title = Die Infrastruktur | accessdate= 18 June 2018|language=de}} 64. ^{{cite news | first= Armin |last=Käfer | title= Fachleute: Unterirdischer Bahnhof in Stuttgart kann gebaut werden | newspaper= Stuttgarter Zeitung | date= 17 January 1995|language=de}} 65. ^{{cite news|url=https://www.welt.de/welt_print/wirtschaft/article5494999/Stuttgart-21-soll-trotz-Mehrkosten-gebaut-werden.html|archiveurl=https://web.archive.org/web/20130927165612/https://www.welt.de/welt_print/wirtschaft/article5494999/Stuttgart-21-soll-trotz-Mehrkosten-gebaut-werden.html|archivedate=27 September 2013|deadurl=no |title=Stuttgart 21 soll trotz Mehrkosten gebaut werden |newspaper=Die Welt |date=11 December 2009|accessdate=18 June 2018|language=de}} 66. ^{{cite news | title = Versaute Verhältnisse | newspaper= Der Spiegel | issue= 24 | date = 10 June 2013 | issn = 0038-7452 | pages = 118–12 |language=de}} 67. ^{{cite web|publisher=Deutsche Bahn AG |url= http://www.vcd-bw.de/presse/2012/27-2012/Anlage_VCD-PM_27-2012_DBAG_S21_aktSachstand_10-12-2009.pdf |archiveurl=https://web.archive.org/web/20130927134234/http://www.vcd-bw.de/presse/2012/27-2012/Anlage_VCD-PM_27-2012_DBAG_S21_aktSachstand_10-12-2009.pdf|archivedate=27 September 2013|deadurl=no |title=Aktueller Sachstand Stuttgart 21 |format=PDF; 95 KiB |date=10 December 2009 |page=10}} (information bulletin (10 A4 pages) 68. ^{{cite book|chapter=Unter der Lupe: Wie das Planfeststellungsverfahren funktioniert |publisher=TurmForum Stuttgart 21 e. V. |title=Das Projekt Stuttgart 21. Begleitbuch zur Ausstellung im TurmForum Stuttgart 21 |pages=50 f.|language=de}} 69. ^{{cite news | first= Mathias |last=Bury | title= Bahn und Kritiker sehen sich bestätigt | newspaper= Stuttgarter Zeitung | date = 12 April 2003|language=de}} 70. ^{{cite web|url=http://www.bahnprojekt-stuttgart-ulm.de/mediathek/detail/media/die-beruecksichtigung-der-wasserwirtschaft-in-der-planung-eine-zwischenbilanz/mediaParameter/show/Medium/96ff6be7e0960baaafaae8cbc70b58b6/| first= Peter |last=Marquart | title = Die Entwicklung des Projektplanung | publisher = Regierungspräsidium Stuttgart | work= Projekt Stuttgart 21 und NBS Wendlingen–Ulm: Die Berücksichtigung der Wasserwirtschaft in der Planung – eine Zwischenbilanz –. Tagungsband | date = 26 September 2006 | pages= 6–13|language=de}} 71. ^1 {{cite journal | first= Rainer |last=Engel | title= Ungebremst ins schwarze Loch? | journal = Der Fahrgast | issn = 1619-1072 | issue = 2 | date = 2005 | pages = 29–32 | url = http://www.der-fahrgast.de/Archiv/2005/2005-2-29_32.pdf |archiveurl=https://web.archive.org/web/20070221074208/http://www.der-fahrgast.de/Archiv/2005/2005-2-29_32.pdf |archivedate=21 February 2007 | format = PDF | accessdate=19 June 2018|language=de}} 72. ^{{cite web | url = http://www.bahnprojekt-stuttgart-ulm.de/no_cache/mediathek/detail/media/pfa-11-talquerung-mit-hauptbahnhof-planfeststellungsbeschluss-planaenderungen/mediaParameter/show/Medium/ | title= Pfa 1.1 | publisher= Mediathek des Bahnprojekt Stuttgart-Ulm e.V | date = 23 April 2015 | accessdate=19 June 2018|language=de}} 73. ^{{cite news| first= Konstantin |last=Schwarz | title = Neuer Plan für Neckarbrücke | newspaper = Stuttgarter Nachrichten | issue= 155 | date= 9 July 2015 | page = 18 | url = http://www.stuttgarter-nachrichten.de/inhalt.stuttgart-21-neuer-plan-fuer-neckarbruecke.2e44546d-17a4-4791-9a11-5495d12780dc.html |archiveurl=https://web.archive.org/web/20150710053408/http://www.stuttgarter-nachrichten.de/inhalt.stuttgart-21-neuer-plan-fuer-neckarbruecke.2e44546d-17a4-4791-9a11-5495d12780dc.html|archivedate=10 July 2015|deadurl=no|accessdate=19 June 2018|language=de}} 74. ^{{cite web | url = http://direktzu.bahnprojekt-stuttgart-ulm.de/stuttgart21/messages/28772#id_answer_30053|archiveurl=https://web.archive.org/web/20160422122731/http://direktzu.bahnprojekt-stuttgart-ulm.de/stuttgart21/messages/28772|archivedate=22 April 2016|deadurl=no | title = Wie breit sind die Bahnsteige im Vergleich | first= Volker |last=Kefer | publisher = Direktzu Stuttgart21 | date = 29 December 2010 | accessdate = 20 January 2018|language=de}} 75. ^{{cite web | url = http://www.bahnprojekt-stuttgart-ulm.de/mediathek/detail/download/personenstromanalyse/mediaParameter/download/Medium/ |archiveurl=https://web.archive.org/web/20150923182311/http://www.bahnprojekt-stuttgart-ulm.de/mediathek/detail/download/personenstromanalyse/mediaParameter/download/Medium/|archivedate=23 September 2015|deadurl=no| title = 24.07.2012 UTA Stuttgart 21, Foliensatz zur Präsentation im Stuttgarter Gemeinderat | first= Sven |last=Hantel | publisher= DB Netze | date = 24 July 2012 | accessdate = 20 January 2018|language=de | format = PDF; 115 KiB | page = 11}} 76. ^1 {{cite journal|first=Ullrich |last=Martin |title=Stuttgart 21: Großprojekt europäischer Dimension |journal=Deine Bahn |issue= 7|date=2009 |pages=6–13|language=de}} 77. ^1 {{cite web|publisher=DBProjekte Süd GmbH |title=Stuttgart 21 spezial: Der Planfeststellungsabschnitt 1.1 Talquerung mit Hauptbahnhof|location=Stuttgart|date= January 2002 |page=10|language=de|type=16-page brochure}} 78. ^{{cite book | publisher = DB ProjektBau GmbH, Niederlassung Nordwest | title = Planfeststellungsunterlagen. Umgestaltung des Bahnknotens Stuttgart. Ausbau- und Neubaustrecke Stuttgart -Augsburg. Bereich Stuttgart - Wendlingen mit Flughafenanbindung. Abschnitt 1.5: Zuführung Feuerbach und Bad Cannstatt. Bau-km -4.0 -90.3 bis -0.4 -42.0 und -4.8 -64.4 bis -0.4 -42.0. Anlage 1: Erläuterungsbericht. Teil III: Beschreibung des Planfeststellungsbereiches | work = Document with situation as of 9 June 2006. Plan determined on 13 October 2009 by the Federal Railway Authority (Eisenbahn-Bundesamt), Karlsruhe/Stuttgart field office (file number 59160 PAP-PS21-PFA1.5) | date = 13 October 2009 | pages = 26f|language=de}} 79. ^1 {{cite journal|title=Hier sind doch keine Stümper am Werk|journal=Dialog 21|issue= 2|date= September 2010|language=de}} 80. ^{{cite news | first= Michael |last=Isenberg | title = Ein Podium der Besserwisser | newspaper = Stuttgarter Nachrichten | issue= 197 | date= 2010-08-27 | page= 16 | url= http://www.stuttgarter-nachrichten.de/inhalt.ingenieur-werner-sobek-ein-podium-der-besserwisser.2b684944-75c1-4839-96cd-60ee896cfc92.html |archiveurl=https://web.archive.org/web/20100827145353/http://www.stuttgarter-nachrichten.de/inhalt.ingenieur-werner-sobek-ein-podium-der-besserwisser.2b684944-75c1-4839-96cd-60ee896cfc92.html |archivedate=27 August 2010|deadurl=no|accessdate=20 June 2018|language=de}} 81. ^{{cite book | publisher = Deutsche Bahn AG, Geschäftsbereich Netz, Regionalbereich Stuttgart, Projekte | title = Das Synergiekonzept Stuttgart 21. Die Ergebnisse des Vorprojekts | location= Stuttgart | date = 1995 | pages = 26f |language=de|type=44-page brochure}} 82. ^{{cite book|publisher=DB Projekt Stuttgart 21 |title=Umgestaltung des Bahnknotens Stuttgart: Ausbau- und Neubaustrecke Stuttgart – Augsburg. Bereich Stuttgart–Wendlingen mit Flughafenanbindung. Planfeststellungsabschnitt 1.1 Talquerung mit Hauptbahnhof. Bau-km -0.4 -42.0 bis +0.4 +32.0|trans-title=Redesign of the Stuttgart railway node: Stuttgart–Augsburg upgraded and new line. Stuttgart–Wendlingen area with airport connection. Planning approval section 1.1: valley crossing with Hauptbahnhof. Construction-km -0.4 -42.0 to +0.4 +32.0. |chapter=Übersichtshöhenplan in Kilometrierungsachse Bau–km –1.5 bis Bau–km +1.5|trans-chapter=Overview altitude plan on kilometre axis, construction-km -1.5 to construction km +1.5 (planning status of 30 April 1999)| at=Annex 2.7, sheet 1 of 1 |date= 24 August 2001|language=de}} 83. ^{{cite book|publisher=Federal Railway Authority |title=Planfeststellungsbeschluss nach § 18 Abs. 1 Allgemeines Eisenbahngesetz (AEG) für den Umbau des Bahnknotens Stuttgart "Projekt Stuttgart 21" Planfeststellungsabschnitt 1.1 (Talquerung mit neuem Hauptbahnhof) von Bahn-km – 0,4- 42,0 bis Bahn-km + 0,4+32,0 in Stuttgart |trans-title=Planning approval pursuant to § 18 para. 1, General Railway Act for the rebuilding of the Stuttgart railway node, planning determination for section 1.1 of the "Stuttgart 21 Project" (valley crossing and new Hauptbahnhof) from track-km – 0.4- 42.0 to track-km + 0.4+32.0 in Stuttgart | location=Stuttgart |date= 28 January 2005 |page=372 f.|language=de}} 84. ^{{cite news | url = http://www.stuttgarter-nachrichten.de/inhalt.stuttgart-21-genehmigung-fuer-gleisneigung-noetig.b9719c1c-4d16-4b72-9c42-b52ab8a6c96e.html |archiveurl=https://web.archive.org/web/20170315004659/http://www.stuttgarter-nachrichten.de/inhalt.stuttgart-21-genehmigung-fuer-gleisneigung-noetig.b9719c1c-4d16-4b72-9c42-b52ab8a6c96e.html|archivedate=15 March 2017|deadurl=no| title = Stuttgart 21: Genehmigung für Gleisneigung nötig | newspaper= Stuttgarter Nachrichten | accessdate = 20 January 2018|language=de}} 85. ^{{cite journal | first= Sven |last=Andersen | title = Das Bahnsteiggleisgefälle in Stuttgart 21 im Blick der Vorschriften und der betrieblichen Praxis | journal = Eisenbahn-Revue International | issue = 6 | date = 2011 | issn = 1421-2811 | pages = 310–311 | url = http://www.boa-bw.de/downloads/frei/ce08e20d-934f-41f9-b25f-68ac963bba8c/0/kopfbahnhof-21.de/fileadmin/downloads/presseberichte/ERI_6_2011_andersen.pdf |archiveurl=https://web.archive.org/web/20160822200115/http://www.boa-bw.de/downloads/frei/ce08e20d-934f-41f9-b25f-68ac963bba8c/0/kopfbahnhof-21.de/fileadmin/downloads/presseberichte/ERI_6_2011_andersen.pdf|archivedate=22 August 2016|deadurl=no| format = PDF| accessdate = 20 January 2018|language=de}} 86. ^1 2 {{cite web | url = http://bauprojekte.deutschebahn.com/p/stuttgart-hbf|archiveurl=https://web.archive.org/web/20150925133017/http://bauprojekte.deutschebahn.com/p/stuttgart-hbf|archivedate=25 September 2015|deadurl=no | title = Hauptbahnhof Stuttgart (Bonatzbau): Modernisierung des Bonatzbaus sowie Neubau von unterirdischen Bahnhofsgebäuden und Vorplätzen | publisher= DB Station&Service AG | accessdate= 21 June 2018|language=de}} 87. ^{{cite book|chapter=Kurze Wege auf drei Ebenen: Schnelle Verkehrsströme im neuen Hauptbahnhof |publisher=TurmForum Stuttgart 21 e. V. |title=Das Projekt Stuttgart 21. Begleitbuch zur Ausstellung im TurmForum Stuttgart 21 |pages=66–69|language=de}} 88. ^1 2 3 {{cite web | url = http://direktzu.bahnprojekt-stuttgart-ulm.de/stuttgart21/messages/31794 |archiveurl=https://web.archive.org/web/20170518101629/http://direktzu.bahnprojekt-stuttgart-ulm.de/stuttgart21/messages/31794|archivedate=18 May 2017|deadurl=no| first= Volker |last=Kefer | title = Breite und Anordnung von Treppen (und Aufzügen) | publisher = Direktzu Stuttgart 21 | date = 8 April 2011 | accessdate= 22 June 2018|language=de}} 89. ^{{cite news|first=Konstantin |last=Schwarz |title=Juchtenkäfer bremst Stadtbahn-Bau aus |newspaper= Stuttgarter Nachrichten |issue=184 |date=10 August 2012|page=18 |url=http://www.schwarzwaelder-bote.de/inhalt.stuttgart-21-juchtenkaefer-bremst-stadtbahn-bau-aus.6684cb3d-fdbd-4fcc-80cd-35e0ae36c9bc.html|archiveurl=https://web.archive.org/web/20150618171924/http://www.schwarzwaelder-bote.de/inhalt.stuttgart-21-juchtenkaefer-bremst-stadtbahn-bau-aus.6684cb3d-fdbd-4fcc-80cd-35e0ae36c9bc.html|archivedate=18 June 2015|deadurl=no |accessdate= 22 June 2018|language=de}} 90. ^{{cite press release | url = http://www.bahnprojekt-stuttgart-ulm.de/aktuell/news-archiv/news-archiv-detail/news/stuttgart-21-baubeginn-nesenbachdueker/newsParameter/detail/News/datum/20150522/ |archiveurl=https://web.archive.org/web/20150618215723/http://www.bahnprojekt-stuttgart-ulm.de/aktuell/news-archiv/news-archiv-detail/news/stuttgart-21-baubeginn-nesenbachdueker/newsParameter/detail/News/datum/20150522/|archivedate=18 June 2015 | title = Stuttgart 21: Baubeginn Nesenbachdüker | publisher = Kommunikationsbüro des Bahnprojekts Stuttgart-Ulm e.V. | date = 22 May 2015 | accessdate= 22 June 2018|language=de}} 91. ^{{cite book|publisher=DBProjekt GmbH, Stuttgart 21 |title=Planfeststellungsunterlagen: Umgestaltung des Bahnknotens Stuttgart. Ausbau- und Neubaustrecke Stuttgart - Augsburg, Bereich Stuttgart - Wendlingen mit Flughafenanbindung: Abschnitt 1.1, Talquerung mit Hauptbahnhof. Bau-km -0.4 -42.0 bis +0.4 +32.0. |chapter=Erläuterungsbericht Teil I: Allgemeiner Teil|trans-title=Planning approval documents: Redesign of the Stuttgart railway node: Stuttgart–Augsburg upgraded and new line, Stuttgart–Wendlingen area with airport connection. Planning approval section 1.1: valley crossing with Hauptbahnhof. Construction-km -0.4 -42.0 to +0.4 +32.0. |trans-chapter=Explanatory Report Part I: General Part |type= planning document |date=28 January 2005 |pages=9, 16|language=de}} 92. ^{{cite web|publisher=DB ProjektBau GmbH|url=https://www.deutschebahn.com/site/shared/de/dateianhaenge/praesentationen/nbs__stuttgart__ulm.pdf |archiveurl=https://web.archive.org/web/20101122050318/https://www.deutschebahn.com/site/shared/de/dateianhaenge/praesentationen/nbs__stuttgart__ulm.pdf|archivedate=22 November 2010|title=Neubauprojekt Stuttgart–Ulm. Neue Strecken, neues Verkehrskonzept für die Region, Deutschland und Europa |format=PDF; 5.2 MiB|accessdate=23 June 2018|language=de}} 93. ^1 {{cite book|editor-first1=Kirstin |editor-last1=Feireiß |editor-first2=Hans-Jürgen |editor-last2=Commerell |title='Hauptbahnhof Stuttgart |type=Catalog for an exhibition in the Galerie Aedes East, in Berlin from 22 June to 1 August 1999 |location=Berlin|date=1999 |pages=36, 40|language=de}} 94. ^1 {{cite web|publisher=Deutsche Bahn AG, Geschäftsbereich Netz, Regionalbereich Stuttgart, Projekte |title=Projekt "Stuttgart 21". Die Machbarkeitsstudie |location=Stuttgart |date=c. 1995 |pages=13, 16, 26, 32 f |url=http://www.rosenstein-stuttgart.de/fileadmin/downloads/1994_Machbarkeitsstudie_DB/Machbarkeitsstudie_1996.pdf |archiveurl=https://web.archive.org/web/20170824220201/http://www.rosenstein-stuttgart.de/fileadmin/downloads/1994_Machbarkeitsstudie_DB/Machbarkeitsstudie_1996.pdf|archivedate=24 August 2017|deadurl=no|format=PDF; 14 MiB |language=de|accessdate=24 June 2018}} 95. ^1 {{cite book|publisher=DBProjekt GmbH Stuttgart 21|title=Projekt "Stuttgart 21": Das Raumordnungsverfahren |type=eight-page brochure|location=Stuttgart |date=c. 1997| page=1 f, 5|language=de}} 96. ^1 2 3 {{cite book|first=Christoph |last=Ingenhoven |chapter=Eine aus dem Ort heraus entwickelte Antwort: Realisierungswettbewerb zur Neugestaltung des Stuttgarter Hauptbahnhofs |publisher=TurmForum Stuttgart 21 e. V. |title=Das Projekt Stuttgart 21. Begleitbuch zur Ausstellung im TurmForum Stuttgart 21 |pages=56–59|language=de}} 97. ^1 {{cite journal | title = Ganz schön helle | journal = Stuttgart 21. Das Projektmagazin | issue = 3 | date = July 1998 | page = 7 |language=de}} 98. ^{{cite journal |title=Hauptbahnhof Stuttgart |journal=Bauwelt|issue= 1997 yearbook |page=1658 f.|language=de}} 99. ^{{cite journal|title=Stuttgart Hbf entschieden| journal=Eisenbahn-Revue International|issue=1/2 |date=1998 |issn=1421-2811 |page=6|language=de}} 100. ^{{cite news|title=Bahnhof verstehen |newspaper= Süddeutsche Zeitung |issue=257 |date=1997|issn=0174-4917|page=14|language=de}} 101. ^{{cite web | url = http://www.holcimfoundation.org/Awards/HolcimAwards200506/RegionalAwards/Europe2005/SilverMainStation/tabid/265/Default.aspx|archiveurl=https://web.archive.org/web/20070805122028/http://www.holcimfoundation.org/Awards/HolcimAwards200506/RegionalAwards/Europe2005/SilverMainStation/tabid/265/Default.aspx|archivedate=5 August 2007|deadurl=no | title = Holcim Awards 2005 – Europe – Silver: Main Station, Stuttgart, Germany | publisher= Holcim Stiftung | accessdate= 24 June 2018}} 102. ^{{cite web | url = http://www.holcimfoundation.org/T177/Gold-Germany.htm|archiveurl=https://web.archive.org/web/20070604170658/http://www.holcimfoundation.org/T177/Gold-Germany.htm|archivedate=4 June 2007| title = Global Holcim Awards Gold 2006: Main Station Stuttgart | publisher= Holcim Stiftung |accessdate= 24 June 2018}} 103. ^{{cite web | url = https://chi-athenaeum.org/assets/pdf_archives/intarch/archive-2007-International-Arch-awards.pdf|archiveurl=https://web.archive.org/web/20160518111210/https://chi-athenaeum.org/assets/pdf_archives/intarch/archive-2007-International-Arch-awards.pdf|archivedate=18 May 2016|deadurl=no | title = The International Architectural Awards 2007 Archive | publisher= The Chicago Athenaeum: Museum of Architecture and Design | accessdate= 24 June 2018}} 104. ^{{cite news|first=Michael |last=Ohnewald|title=Alte Liebe rostet nicht |newspaper= Stuttgarter Zeitung |issue= 232 |date= 7 October 2006 |page=36|language=de}} 105. ^{{cite journal | title= Versaute Verhältnisse | journal = Der Spiegel | issue= 24 | date = 10 June 2013 | issn = 0038-7452 | pages = 118–124 | url = http://www.spiegel.de/spiegel/print/d-97110561.html |archiveurl=https://web.archive.org/web/20131001025831/http://www.spiegel.de/spiegel/print/d-97110561.html|archivedate=1 October 2013|deadurl=no|accessdate=24 June 2018|language=de}} 106. ^1 2 {{cite journal|title=Neuer Stuttgarter Bahnhof komplett barrierefrei |journal=Dialog 21 |edition= 2 |date= September 2010 |page=1|language=de}} 107. ^{{cite web|url=http://www.schlichtung-s21.de/fileadmin/schlichtungs21/Redaktion/pdf/101130/2010-11-30_Schlichterspruch_Stuttgart_21_PLUS.pdf |archiveurl=https://web.archive.org/web/20110813010017/http://www.schlichtung-s21.de/fileadmin/schlichtungs21/Redaktion/pdf/101130/2010-11-30_Schlichterspruch_Stuttgart_21_PLUS.pdf/|archivedate=13 August 2011|deadurl=no|title=Schlichtung Stuttgart 21 PLUS |format=PDF; 82 KiB |date= 30 November 2010 |page=13|accessdate=24 June 2018|language=de}} 108. ^{{cite web|publisher=Eisenbahn-Bundesamt |url=http://www.eba.bund.de/SharedDocs/Publikationen/DE/PF/Beschluesse/Baden_W/23_Stg21_1.1_6.Paa.pdf?__blob=publicationFile&v=2 |archiveurl=https://web.archive.org/web/20160207143258/http://www.eba.bund.de/SharedDocs/Publikationen/DE/PF/Beschluesse/Baden_W/23_Stg21_1.1_6.Paa.pdf?__blob=publicationFile&v=2|archivedate=7 February 2016|title=Bescheid zur Änderung des Planfeststellungsbeschlusses vom 28. Januar 2005, (…) für das Vorhaben "Großprojekt Stuttgart 21", PFA 1.1, 6. PÄ – Änderung Zugangsschalen Hbf, Bahnsteigzugänge und Ausführung im Bereich der Lounge der Verkehrsstation sowie Entfall des Versorgungstunnels in Stuttgart Bahn-km -0,442 bis 0,432 der Strecke 4813|location=Stuttgart |date=23 April 2015|accessdate=24 June 2018|language=de}} 109. ^{{cite news | first= Christian |last=Milankovic | title = S 21: Unsicherheiten auch zur Halbzeit | newspaper = Stuttgarter Zeitung | volume= 73 | date = 1 June 2017 | page = 2 | url = http://www.stuttgarter-zeitung.de/inhalt.stuttgart-21-unsicherheiten-auch-zur-halbzeit.3eb73f4c-853a-4e96-9ec7-ab559c3fe28f.html |archiveurl=https://web.archive.org/web/20170604012658/http://www.stuttgarter-zeitung.de/inhalt.stuttgart-21-unsicherheiten-auch-zur-halbzeit.3eb73f4c-853a-4e96-9ec7-ab559c3fe28f.html |archivedate=4 June 2017|accessdate=24 June 2018|language=de}} 110. ^{{cite journal|journal=Der Spiegel| title=Zehn Jahre hätten gereicht |issue=51 |date=16 December 2017 |pages=118–121|url=https://magazin.spiegel.de/SP/2017/51/154831744/ |language=de}} 111. ^{{cite web | url = http://www.bahnprojekt-stuttgart-ulm.de/aktuell/newsdetail/news/jahrhundertprojekt-stuttgart-21-startet/newsParameter/detail/News/ |archiveurl=https://web.archive.org/web/20120925130340/http://www.bahnprojekt-stuttgart-ulm.de/aktuell/newsdetail/news/jahrhundertprojekt-stuttgart-21-startet/newsParameter/detail/News/|archivedate=25 September 2012 | title = Jahrhundertprojekt Stuttgart 21 startet | publisher = Bahnprojekt Stuttgart–Ulm e. V. | date = 2 February 2010 | accessdate = 25 January 2018|language=de}} 112. ^{{cite news | url = http://www.stuttgarter-zeitung.de/inhalt.stuttgart-21-proteste-am-samstag-fortgesetzt.5f6b9bd3-b496-4990-bcde-003d6a22bfad.html |archiveurl=https://web.archive.org/web/20131210082305/http://www.stuttgarter-zeitung.de/inhalt.stuttgart-21-proteste-am-samstag-fortgesetzt.5f6b9bd3-b496-4990-bcde-003d6a22bfad.html|archivedate=10 December 2013|deadurl=no | title = Abriss am Hauptbahnhof beginnt unter großem Polizeischutz | newspaper= Stuttgarter Zeitung | date = 30 July 2010 | accessdate = 25 January 2018|language=de}} 113. ^{{cite news | url = https://www.handelsblatt.com/politik/deutschland/stuttgart21-abriss-des-suedfluegels-hat-begonnen/6129578.html|archiveurl=https://web.archive.org/web/20120202025940/http://www.handelsblatt.com/politik/deutschland/stuttgart21-abriss-des-suedfluegels-hat-begonnen/6129578.html|archivedate=2 February 2012|deadurl=no | title = Abriss des Südflügels hat begonnen | newspaper = Handelsblatt | date = 30 January 2012 | accessdate = 25 January 2018|language=de}} 114. ^{{cite news | url = http://www.stuttgarter-nachrichten.de/inhalt.stuttgart-21-abriss-des-suedfluegels-ruht-fuer-monate.5f8c4082-0ec8-4bf2-a1f4-c34dc14a3834.html|archiveurl=https://web.archive.org/web/20120406031028/http://www.stuttgarter-nachrichten.de/inhalt.stuttgart-21-abriss-des-suedfluegels-ruht-fuer-monate.5f8c4082-0ec8-4bf2-a1f4-c34dc14a3834.html|archivedate=6 April 2012|deadurl=no | title = Abriss des Südflügels ruht für Monate | first= Jürgen |last=Bock | newspaper = Stuttgarter Nachrichten | date = 4 April 2012 | accessdate = 25 January 2018|language=de}} 115. ^{{cite news | url = http://www.stuttgarter-nachrichten.de/inhalt.nach-baggerunfall-suedfluegel-abriss-geht-weiter.05608985-580b-47c0-a543-2f4c3ba3507b.html|archiveurl= https://web.archive.org/web/20120415183517/http://www.stuttgarter-nachrichten.de/inhalt.nach-baggerunfall-suedfluegel-abriss-geht-weiter.05608985-580b-47c0-a543-2f4c3ba3507b.html |archivedate=15 April 2012|deadurl=no | title = Südflügel-Abriss geht weiter | first= Jürgen |last=Bock | newspaper = Stuttgarter Nachrichten | date = 12 April 2012 | accessdate = 25 January 2018|language=de}} 116. ^1 {{cite journal|title=Stuttgart 21 – Aktuelle Entwicklungen |journal= Bahn-Report |issue=5|date=2012 |page=67|language=de}} 117. ^{{cite news|first=Jörg |last=Nauke |url=http://www.stuttgarter-zeitung.de/inhalt.stuttgart-21-ist-der-neue-bahnhof-behindertengerecht.1135392e-67af-41b6-87c8-4f8a08324db7.html |archiveurl=https://web.archive.org/web/20110526044338/http://www.stuttgarter-zeitung.de/inhalt.stuttgart-21-ist-der-neue-bahnhof-behindertengerecht.1135392e-67af-41b6-87c8-4f8a08324db7.html|archivedate=26 May 2011|deadurl=no|title=Ist der neue Bahnhof behindertengerecht? |newspaper= Stuttgarter Zeitung |date=13 January 2011 | accessdate = 25 January 2018|language=de}} 118. ^{{cite news|url=http://www.stuttgarter-nachrichten.de/inhalt.stuttgart-21-steg-verbindet-schlossgarten-mit-querbahnsteig.7b1c6107-81eb-4f3e-be03-5b67054c4906.html |archiveurl=https://web.archive.org/web/20140407101425/http://www.stuttgarter-nachrichten.de/inhalt.stuttgart-21-steg-verbindet-schlossgarten-mit-querbahnsteig.7b1c6107-81eb-4f3e-be03-5b67054c4906.html|archivedate=7 April 2014|title=Steg verbindet Schlossgarten mit Querbahnsteig |newspaper= Stuttgarter Nachrichten |date=24 January 2014| accessdate = 25 January 2018|language=de}} 119. ^1 {{cite news|first=Markus |last=Heffner |title=Arbeiten am Tiefbahnhof beginnen 2013 |newspaper=Stuttgarter Zeitung |issue= 55|date= 6 March 2013 |page=19|language=de}} 120. ^1 {{cite news | first= Konstantin |last=Schwarz | title= Bahnsteigumbau: Im Hauptbahnhof wird es eng | newspaper= Stuttgarter Nachrichten | date = 25 May 2013 | page = 17 | url = http://www.stuttgarter-nachrichten.de/inhalt.stuttgart-21-bahnsteigumbau-im-hauptbahnhof-wird-es-eng.90d93b25-5122-4c69-9c00-e510309e223e.html |archiveurl=https://web.archive.org/web/20130612094039/http://www.stuttgarter-nachrichten.de/inhalt.stuttgart-21-bahnsteigumbau-im-hauptbahnhof-wird-es-eng.90d93b25-5122-4c69-9c00-e510309e223e.html|archivedate=12 June 2013|deadurl=no|accessdate = 26 January 2018|language=de}} 121. ^{{cite journal|url=http://ted.europa.eu/udl?uri=TED:NOTICE:303797-2012:TEXT:DE:HTML |deadurl=y|title=D-Stuttgart: Bauleistungen im Hochbau |issue=Document 2012/S 185-303797 |date= 26 September 2012 |journal=Supplement of the Official Journal of the European Union|language=de}} 122. ^{{cite news |url=http://www.stuttgarter-nachrichten.de/inhalt.bonatz-bau-stuttgarter-konzern-reisst-nordfluegel-ab.be6bcb9d-3507-4f89-b0f0-a5e592c5b376.html |archiveurl=https://web.archive.org/web/20100523102851/http://www.stuttgarter-nachrichten.de/inhalt.bonatz-bau-stuttgarter-konzern-reisst-nordfluegel-ab.be6bcb9d-3507-4f89-b0f0-a5e592c5b376.html|archivedate=23 May 2010|deadurl=no|title=Stuttgarter Konzern reißt Nordflügel am Bonatzbau ab|newspaper=Stuttgarter Nachrichten |date=22 May 2010|accessdate = 26 January 2018|language=de}} 123. ^{{cite press release|publisher=DB Mobility Logistics AG |title=DB vergibt Aufträge für Tunnelbauwerke und neuen Stuttgarter Tiefbahnhof von rund 800 Millionen Euro| date= 13 March 2012|language=de}} 124. ^1 {{cite journal|title=Brücken ins Land |journal=Bezug|issue=2|year=2012 |pages=4–8|language=de}} 125. ^{{cite journal|url=http://ted.europa.eu/udl?uri=TED:NOTICE:356149-2012:TEXT:DE:HTML |deadurl=y|title=D-Stuttgart: Bau von Bahnhöfen |issue=Document 2012/S 216-356149 |date=9 November 2012 |journal=Supplement of the Official Journal of the European Union|language=de}} 126. ^1 2 {{cite web|first=Volker|last= Kefer |title=Stuttgart 21 und NBS Wendlingen-Ulm Unterlage für den Prüfungs- und Complianceausschuss (PCA) der DB und den Lenkungskreis (LK) S21 |location= Berlin/Stuttgart |date= 23 March 2012 |url=http://www.bahnprojekt-stuttgart-ulm.de/uploads/tx_smedianews/20120323-Stuttgart21-Lenkungskreis.pdf |archiveurl=https://web.archive.org/web/20121020083243/http://www.bahnprojekt-stuttgart-ulm.de/uploads/tx_smedianews/20120323-Stuttgart21-Lenkungskreis.pdf|archivedate=20 October 2012|deadurl=no|format=PDF, 880 KiB |pages=5, 22|accessdate = 26 January 2018|language=de}} 127. ^1 {{cite news|title=Jede Generation muss Neues schaffen |newspaper= Stuttgarter Zeitung |date=22 May 2012 |page=22|language=de}} 128. ^{{cite journal | url = http://ted.europa.eu/udl?uri=TED:NOTICE:164539-2016:TEXT:DE:HTML&src=0 | title = Deutschland-Stuttgart: Bau von Bahnhöfen | issue = document 2016/S 092-164539|journal=Supplement of the Official Journal of the European Union|date=13 May 2016|accessdate=26 June 2018|language=de}} 129. ^{{cite journal | url = http://ted.europa.eu/udl?uri=TED:NOTICE:283069-2016:TEXT:DE:HTML&src=0|archiveurl=https://web.archive.org/web/20180626112549/http://ted.europa.eu/TED/notice/udl?uri=TED:NOTICE:283069-2016:TEXT:DE:HTML&src=0|archivedate=26 June 2018|deadurl=no | title = Deutschland-Stuttgart: Bau von Bahnhöfen | issue= Document 2016/S 156-283069 | journal=Supplement of the Official Journal of the European Union| date = 15 August 2016 | accessdate=26 June 2018|language=de}} 130. ^{{cite news|title=Baufirmen kämpfen um Milliardenaufträge|newspaper= Stuttgarter Nachrichten |issue=282|date=6 December 2010| page=17 |url=http://www.stuttgarter-nachrichten.de/inhalt.stuttgart-21-baufirmen-kaempfen-um-milliardenauftraege.74c46f18-7c94-485f-8be9-39592bb8315e.html |archiveurl=https://web.archive.org/web/20101208060909/http://www.stuttgarter-nachrichten.de/inhalt.stuttgart-21-baufirmen-kaempfen-um-milliardenauftraege.74c46f18-7c94-485f-8be9-39592bb8315e.html|archivedate=8 December 2010|deadurl=no| accessdate=26 June 2018|language=de}} 131. ^{{cite news | first= Michael |last=Isenberg | url = http://www.stuttgarter-nachrichten.de/inhalt.stuttgart-21-zueblin-soll-tiefbahnhof-bauen.a2e57778-1b7f-40a0-88fb-dff625a2c76d.html |archiveurl=https://web.archive.org/web/20120315225457/http://www.stuttgarter-nachrichten.de/inhalt.stuttgart-21-zueblin-soll-tiefbahnhof-bauen.a2e57778-1b7f-40a0-88fb-dff625a2c76d.html|archivedate=15 March 2012|deadurl=no| title = Züblin soll Tiefbahnhof bauen | newspaper= Stuttgarter Nachrichten | date =13 March 2012 | accessdate=26 June 2018|language=de}} 132. ^{{cite news|url=http://www.stuttgarter-zeitung.de/inhalt.lenkungskreis-stuttgart-21-debatte-ueber-mehrkosten.30d5ab47-6fe9-4d01-81ca-106dda388726.html |archiveurl=https://web.archive.org/web/20120324185117/http://www.stuttgarter-zeitung.de/inhalt.lenkungskreis-stuttgart-21-debatte-ueber-mehrkosten.30d5ab47-6fe9-4d01-81ca-106dda388726.html|archivedate=24 March 2012|title=Debatte über Mehrkosten |newspaper=Stuttgarter Zeitung | date= 22 March 2012| accessdate=26 June 2018|language=de}} 133. ^{{cite news|first=Rebecca |last=Müller|url=http://www.stuttgarter-zeitung.de/inhalt.unfall-in-stuttgart-testzug-entgleist-am-hauptbahnhof.3c5f5488-7f83-4172-a2b7-cc3193d1477b.html|archiveurl=https://web.archive.org/web/20121011060935/http://www.stuttgarter-zeitung.de/inhalt.unfall-in-stuttgart-testzug-entgleist-am-hauptbahnhof.3c5f5488-7f83-4172-a2b7-cc3193d1477b.html|archivedate=11 October 2012|deadurl=no |title=Testzug entgleist am Hauptbahnhof|newspaper= Stuttgarter Zeitung|date= 9 October 2012 | accessdate=26 June 2018|language=de}} 134. ^{{cite web | publisher= Eisenbahn-Unfalluntersuchungsstelle des Bundes | title =2012 Annual Report | location = Bonn | date = 2013 | pages = 20–24 | url= http://www.eisenbahn-unfalluntersuchung.de/SharedDocs/Publikationen/EUB/DE/Untersuchungsberichte/2012/053_Stuttgart%20Hbf.pdf?__blob=publicationFile&v=5|archiveurl=https://web.archive.org/web/20160821011311/http://www.eisenbahn-unfalluntersuchung.de/SharedDocs/Publikationen/EUB/DE/Untersuchungsberichte/2012/053_Stuttgart%20Hbf.pdf?__blob=publicationFile&v=5|archivedate=21 August 2016| format = PDF|accessdate=26 June 2018|language=de}} 135. ^{{cite news|title=Drei Gleise bleiben bis auf Weiteres gesperrt |newspaper= Stuttgarter Zeitung |issue=236 |date=11 October 2012|page=19 |url= http://www.stuttgarter-zeitung.de/inhalt.zug-entgleisung-drei-gleise-bleiben-bis-auf-weiteres-gesperrt.8fe8cb2e-1bf1-41a5-8b7c-4445b8c01cc8.html|archiveurl=https://web.archive.org/web/20121012000043/http://www.stuttgarter-zeitung.de/inhalt.zug-entgleisung-drei-gleise-bleiben-bis-auf-weiteres-gesperrt.8fe8cb2e-1bf1-41a5-8b7c-4445b8c01cc8.html|archivedate=12 October 2012|deadurl=no|accessdate=26 June 2018|language=de}} 136. ^{{cite news|title=Keine Lösung für gesperrtes Gleis 10 |newspaper= Stuttgarter Zeitung |volume= 68 |issue=283 |date=6 December 2012 |page=23|language=de}} 137. ^{{cite news | first= Konstantin |last=Schwarz | title= Bahn nimmt neu Anlauf für Notfahrplan | newspaper= Stuttgarter Nachrichten | date = 10 January 2013 | page = 21|language=de}} 138. ^1 2 {{cite news | first1= Thomas | last1=Faltin | first2=Wolfgang | last2=Schulz-Braunschmidt | title = Gleis 10 mit Auflagen wieder freigegeben | newspaper= Stuttgarter Zeitung | volume= 69 | issue = 20 | date = 24 January 2013 | page= 9 | url = http://www.stuttgarter-zeitung.de/inhalt.bahnhof-stuttgart-gleis-10-mit-auflagen-wieder-frei-gegeben.37e1a47e-f437-4e1f-9656-587703e0f51a.html |archiveurl=https://web.archive.org/web/20130127060743/http://www.stuttgarter-zeitung.de/inhalt.bahnhof-stuttgart-gleis-10-mit-auflagen-wieder-frei-gegeben.37e1a47e-f437-4e1f-9656-587703e0f51a.html|archivedate=27 January 2013|deadurl=no|accessdate=26 June 2018|language=de}} 139. ^{{cite news | first= Michael |last=Petersen | title= Das lange Warten auf die Pünktlichkeit | newspaper = Stuttgarter Zeitung | issue = 296 | date = 23 December 2014 | page= 5|language=de}} 140. ^1 {{cite news|first=Konstantin |last=Schwarz |title=Tiefbahnhof hat zwei Jahre Verspätung |newspaper= Stuttgarter Nachrichten |issue= 55 |date= 6 March 2012|page=18 |url=http://www.stuttgarter-nachrichten.de/inhalt.stuttgart-21-tiefbahnhof-hat-zwei-jahre-verspaetung.e89ec470-5290-4642-984e-9ebc7e70ffbe.html |archiveurl=https://web.archive.org/web/20120308203841/http://www.stuttgarter-nachrichten.de/inhalt.stuttgart-21-tiefbahnhof-hat-zwei-jahre-verspaetung.e89ec470-5290-4642-984e-9ebc7e70ffbe.html|archivedate=8 March 2012|accessdate=26 June 2018|language=de}} 141. ^{{cite news | first= Thomas |last=Durchdenwald | title= Bahn hebt erst Baugrube für den Tiefbahnhof aus | newspaper= Stuttgarter Zeitung | issue= 178 | date= 5 August 2014 | page = 19 | url = http://www.stuttgarter-zeitung.de/inhalt.stuttgart-21-bahn-hebt-erste-baugrube-fuer-den-tiefbahnhof-aus.35d1972b-dad9-4c26-bda7-fd35a68dae52.html |archiveurl=https://web.archive.org/web/20140807200123/http://www.stuttgarter-zeitung.de/inhalt.stuttgart-21-bahn-hebt-erste-baugrube-fuer-den-tiefbahnhof-aus.35d1972b-dad9-4c26-bda7-fd35a68dae52.html|archivedate=7 August 2014|deadurl=no|accessdate=26 June 2018|language=de}} 142. ^{{cite news | first = Christian |last=Milankovic | title = Bahn kämpft im S-21-Trog mit dem Zeitplan | newspaper= Stuttgarter Zeitung | issue = 184 | date = 12 August 2015| page = 19 | url = http://www.stuttgarter-zeitung.de/inhalt.stuttgart-21-bahn-kaempft-im-s-21-trog-mit-dem-zeitplan.13032600-f191-4b75-bb24-f582d6ce12a3.html |archiveurl=https://web.archive.org/web/20150813143034/http://www.stuttgarter-zeitung.de/inhalt.stuttgart-21-bahn-kaempft-im-s-21-trog-mit-dem-zeitplan.13032600-f191-4b75-bb24-f582d6ce12a3.html|archivedate=13 August 2015|deadurl=no|accessdate=26 June 2018|language=de}} 143. ^{{cite news | first= Christian |last=Milankovic | title = Fehlende Genehmigungen bremsen die Bahn | newspaper= Stuttgarter Zeitung | volume = 71 | issue = 242 | date = 20 October 2015 | url = http://www.stuttgarter-zeitung.de/inhalt.stuttgart-21-fehlende-genehmigungen-bremsen-die-bahn.0bb19488-e009-415c-8c64-0c0aa4cd1dae.html |archiveurl=https://web.archive.org/web/20151219015653/http://www.stuttgarter-zeitung.de/inhalt.stuttgart-21-fehlende-genehmigungen-bremsen-die-bahn.0bb19488-e009-415c-8c64-0c0aa4cd1dae.html|archivedate=19 December 2015|deadurl=no | accessdate=26 June 2018|language=de}} 144. ^{{cite news | first= Konstantin |last=Schwarz | title = Fluchttreppen im Bahnhof nur 30 Minuten sicher | newspaper = Stuttgarter Nachrichten | date = 20 March 2015 | page = 17 | url = http://www.stuttgarter-nachrichten.de/inhalt.stuttgart-21-fluchtwege-im-bahnhof-nur-30-minuten-sicher.345ecae6-8dba-4b52-9424-9983e6bac667.html |archiveurl=https://web.archive.org/web/20150322174150/http://www.stuttgarter-nachrichten.de/inhalt.stuttgart-21-fluchtwege-im-bahnhof-nur-30-minuten-sicher.345ecae6-8dba-4b52-9424-9983e6bac667.html|archivedate=22 March 2015|deadurl=no | accessdate=26 June 2018|language=de}} 145. ^{{cite news | first= Christian |last=Milankovic | title = Im Bahnhofstrog fließt der erste Beton | newspaper= Stuttgarter Zeitung | date = 27 January 2016 | page = 19 | url = http://www.stuttgarter-zeitung.de/inhalt.stuttgart-21-im-bahnhofstrog-fliesst-der-erste-beton.8f7c06a3-efca-4d04-b156-10ebac65add1.html |archiveurl=https://web.archive.org/web/20160128002738/http://www.stuttgarter-zeitung.de/inhalt.stuttgart-21-im-bahnhofstrog-fliesst-der-erste-beton.8f7c06a3-efca-4d04-b156-10ebac65add1.html|archivedate=28 January 2016|deadurl=no | accessdate=27 June 2018|language=de}} 146. ^{{cite web | url = http://www.bahnprojekt-stuttgart-ulm.de/no_cache/projekt/aktuell/archiv-suche/news-archiv-detail/news/1280-bahn-beginnt-mit-dem-bau-der-ersten-kelchstuetze-fuer-den-kuenftigen-stuttgarter-hauptbahnhof/newsParameter/detail/News/ |archiveurl=https://web.archive.org/web/20171201102227/http://www.bahnprojekt-stuttgart-ulm.de/no_cache/projekt/aktuell/archiv-suche/news-archiv-detail/news/1280-bahn-beginnt-mit-dem-bau-der-ersten-kelchstuetze-fuer-den-kuenftigen-stuttgarter-hauptbahnhof/newsParameter/detail/News/ |archivedate=1 December 2017 | title = Bau der ersten Kelchstütze: Der Fuß der Kelchstütze ist fertig bewehrt | publisher = Deutsche Bahn | date =19 May 2017 | accessdate=27 June 2018|language=de}} 147. ^{{cite news |first=Christian|last=Milankovic |url= https://www.stuttgarter-zeitung.de/inhalt.stuttgart-21-baudenkmal-ist-nun-unten-ohne.6a0a3f89-2cb7-4075-b8d7-8ef14769cafc.html|archiveurl=https://web.archive.org/web/20170729160537/https://www.stuttgarter-zeitung.de/inhalt.stuttgart-21-baudenkmal-ist-nun-unten-ohne.6a0a3f89-2cb7-4075-b8d7-8ef14769cafc.html|archivedate=29 July 2017|deadurl=no |title=Ehemalige Bahndirektion ist nun unten ohne |newspaper=Stuttgarter Zeitung |date=27 July 2017 |accessdate=27 June 2018|language=de}} 148. ^{{cite web | url = http://www.schlichtung-s21.de/fileadmin/schlichtungs21/Redaktion/pdf/101120/2010-11-20_Wortprotokoll.pdf |archiveurl=https://web.archive.org/web/20111018072214/http://www.schlichtung-s21.de/fileadmin/schlichtungs21/Redaktion/pdf/101120/2010-11-20_Wortprotokoll.pdf|archivedate=18 October 2011|deadurl=no | title = Schlichtungsverfahren zu Stuttgart 21 | date = 20 November 2010 | pages= 89ff | format = PDF; 668 KiB | type = Meeting record of 6th conciliation meeting|accessdate=28 June 2018 |language=de}} 149. ^{{cite web | publisher= Gaßner, Siederer, Neusüß | title = Zulassungsrechtliche Folgen des von der DB gestellten Antrags auf Verdoppelung der Grundwasserförder- und -entnahmemengen im Projekt "Stuttgart 21" | url = http://www.um.baden-wuerttemberg.de/servlet/is/82816/Gutachten.pdf?command=downloadContent&filename=Gutachten.pdf |archiveurl=https://web.archive.org/web/20131203181202/http://www.um.baden-wuerttemberg.de/servlet/is/82816/Gutachten.pdf?command=downloadContent&filename=Gutachten.pdf |archivedate= 3 December 2013 | accessdate=28 June 2018 |language=de | format = PDF}} 150. ^{{cite press release |publisher=BUND Baden-Württemberg: |url=http://www.bund-bawue.de/fileadmin/bawue/presse/pressemitteilungen/2011/06/Antragsschrift.pdf |archiveurl=https://web.archive.org/web/20111218000151/http://www.bund-bawue.de/fileadmin/bawue/presse/pressemitteilungen/2011/06/Antragsschrift.pdf|archivedate=18 December 2011|title=Antrag auf Erlass einer einstweiligen Anordnung |format=PDF; 297 KiB | type=Express application to the Administrative Court Stuttgart |date =20 June 2011| accessdate=28 June 2018 |language=de}} 151. ^{{cite news|first=Michael |last=Isenberg |title=Baustart des Tiefbahnhofs soll 2013 möglich sein |newspaper= Stuttgarter Nachrichten |issue=149|date=2012 |page=20|language=de}} 152. ^{{cite news|first1=Jörg |last1=Nauke|first2=Thomas |last2=Braun |title=Land bestätigt Zeitverzug beim Tiefbahnhof |newspaper= Stuttgarter Zeitung |issue=148|date= 29 June 2012 |page=23|language=de}} 153. ^{{cite book|publisher=Eisenbahn-Bundesamt |title=Bescheid gemäß (…) für die Vorhaben "Großprojekt Stuttgart 21: PFA 1.1, 7. PÄ, Planänderung Wasserrecht" (…) |location=Stuttgart |date=22 September 2014|language=de}} 154. ^{{cite web | publisher= Bahnprojekt Stuttgart–Ulm | url = http://www.bahnprojekt-stuttgart-ulm.de/uploads/tx_smediamediathek/PFA_1_1-Bautaktung.pdf |archiveurl=https://web.archive.org/web/20121016145918/http://www.bahnprojekt-stuttgart-ulm.de/uploads/tx_smediamediathek/PFA_1_1-Bautaktung.pdf |archivedate=16 October 2012 |deadurl=no | title = Stuttgart 21: Bautaktung PFA 1.1 | format = PDF; 1.2 MiB | date = June 2010 | accessdate=28 June 2018 |language=de}} 155. ^1 2 {{cite journal|title=Was passiert wann? | journal=Dialog 21 |issue= 3 |date=January 2011 |url=http://www.bahnprojekt-stuttgart-ulm.de/mediathek/detail/download/dialog21-ausgabe-3/mediaParameter/download/Medium/ |format=PDF|page=3|accessdate=29 June 2018 |language=de}} 156. ^{{cite news | first= Christian |last=Milankovic | title = Der nächste Stadtbahnumbau steht an | newspaper = Stuttgarter Zeitung | date = 26 August 2013 | page = 15 | url = http://www.stuttgarter-zeitung.de/inhalt.stuttgart-21-und-die-stadtbahn-der-naechste-stadtbahnumbau-steht-an.3dff9caf-b0df-4adf-a886-7e91109ca694.html |archiveurl=https://web.archive.org/web/20130829010629/http://www.stuttgarter-zeitung.de/inhalt.stuttgart-21-und-die-stadtbahn-der-naechste-stadtbahnumbau-steht-an.3dff9caf-b0df-4adf-a886-7e91109ca694.html|archivedate=29 August 2013|deadurl=no|accessdate=29 June 2018 |language=de}} 157. ^{{cite news | title = Stuttgart 21: Bisherige Trasse wird verlegt | newspaper = Stuttgarter Zeitung | url = http://www.stuttgarter-zeitung.de/inhalt.stuttgart-21-neubau-der-station-staatsgalerie-startet-page1.216b00a9-2f2f-416c-9983-53d2cb0fc4cd.html |archiveurl=https://web.archive.org/web/20141217122741/http://www.stuttgarter-zeitung.de/inhalt.stuttgart-21-neubau-der-station-staatsgalerie-startet-page1.216b00a9-2f2f-416c-9983-53d2cb0fc4cd.html|archivedate=17 December 2014 | deadurl=no|accessdate=29 June 2018 |language=de}} 158. ^{{cite web | publisher = Verband Region Stuttgart | title = Anlage 4.1 zur Vorlage 190 / 2013; Klausur des Verkehrsausschusses am 8. Mai 2013 | date = 8 May 2013 | pages = 2, 4 | postscript = (the figure of 103,000 results from the increase of 2,600 passengers expected between 2010 and 2025 (page 4) and the expected load of 105,900 passengers in 2025 (page 2)) | url = https://gecms.region-stuttgart.org/gdmo/Download.aspx?id=37911 | format = PDF|accessdate=29 June 2018 |language=de}} 159. ^{{cite web | title = Sitzungsvorlage Nr. 190/2013, Verkehrsausschuss am 8. Mai 2013: Fortschreibung des Regionalverkehrsplan - Ergebnisse der Verkehrsprognose zum Bezugsszenario 2025 | publisher = Verband Region Stuttgart | date = 8 May 2013 | page = 8 |url=http://www.region-stuttgart.org/i2ebridge/Download?docid=12246 | archiveurl= https://web.archive.org/web/20131003083221/http://www.region-stuttgart.org/i2ebridge/Download?docid=12246 |archivedate=3 October 2013 | format = PDF |accessdate=29 June 2018 |language=de}} 160. ^{{cite news | first = Christian |last=Milankovic | title = Privatbahner: 100 Züge täglich im Kopfbahnhof | newspaper = Stuttgarter Zeitung | volume = 70 |issue = 278 | date = 1 December 2015 | page = 19 | url = http://www.stuttgarter-zeitung.de/inhalt.hauptbahnhof-in-stuttgart-privatbahner-wollen-gleise-erhalten.444fee03-7bbf-4295-9f4f-d02b15a9441f.html |archiveurl=https://web.archive.org/web/20151204041226/http://www.stuttgarter-zeitung.de/inhalt.hauptbahnhof-in-stuttgart-privatbahner-wollen-gleise-erhalten.444fee03-7bbf-4295-9f4f-d02b15a9441f.html|archivedate=4 December 2015|deadurl=no|accessdate=29 June 2018 |language=de}} 161. ^{{cite book|first1=U|last1=Martin |first2=H. |last2=Dobeschinsky |first3=P. |last3=Breuer|first4= M. |last4=Haderer, |first5=N. |last5=Sonnenberg |chapter=Vergleich der Leistungsfähigkeiten und des Leistungsverhaltens des neuen Durchgangsbahnhofes (S21) und einer Variante umgestalteter Kopfbahnhof (K21) im Rahmen der Neugestaltung des Stuttgarter Hauptbahnhofes (Abschlussbericht) |publisher=Landeshauptstadt Stuttgart |title=Stuttgart 21 – Diskurs | location=Stuttgart |date=2007 |pages=2287–2369, especially 2330, 2332, 2337 f., 2341|language=de}} 162. ^{{cite journal | first= Christoph M. |last=Engelhardt | title = Stuttgart 21: Leistung von Durchgangs- und Kopfbahnhöfen | journal = Eisenbahn-Revue International | issue= 6 | date= 2011 | issn = 1421-2811 | pages= 306–309|language=de}} 163. ^{{cite press release|url=http://www.mvi.baden-wuerttemberg.de/servlet/is/104632/ |archiveurl=https://web.archive.org/web/20111127154946/http://www.mvi.baden-wuerttemberg.de/servlet/is/104632/|archivedate=27 November 2011|title=Kopfbahnhof könnte heute schon mehr Züge abwickeln als S 21 |publisher=Ministeriums für Verkehr und Infrastruktur in Baden-Württemberg |date=22 November 2011|accessdate=29 June 2018 |language=de}} Sources
| title = Planfeststellungsbeschluss nach § 18 Abs. 1 Allgemeines Eisenbahngesetz (AEG) für den Umbau des Bahnknotens Stuttgart "Projekt Stuttgart 21" Planfeststellungsabschnitt 1.1 (Talquerung mit neuem Hauptbahnhof) von Bahn-km – 0,4- 42,0 bis Bahn-km + 0,4+32,0 in Stuttgart |trans-title= Planning decision under s.18.1 of the General Railway Act for the conversion of rail node of Stuttgart, project "Stuttgart 21", zoning Section 1.1 (valley crossing with a new main station) from rail-km -0.4 – 42.0 to rail-km + 0.4 + 32.0 in Stuttgart| publisher= Eisenbahn-Bundesamt Karlsruhe/Stuttgart | date = 18 January 2005 | accessdate= 10 June 2018 | format = PDF; 2.3 MiB |language=de}} {{Authority control}} 4 : Railway stations in Stuttgart|Stuttgart S-Bahn stations|Railway stations opened in 1922|1922 establishments in Germany |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
随便看 |
|
开放百科全书收录14589846条英语、德语、日语等多语种百科知识,基本涵盖了大多数领域的百科知识,是一部内容自由、开放的电子版国际百科全书。