The Temengor Dam or Temengor Hydro-Electric Project or Temengor Power Station is a dam in Gerik, Perak, Malaysia. It is located on Perak River about 200 km northeast of Ipoh. Construction of the dam impounded Temenggor Lake.

Power station

The power station is a hydroelectric power station, using 4 Hitachi turbines of 87 MW installed capacity and the average annual energy generation 900 million units. The station is operated by Tenaga Nasional. Since 1987 Temenggor has been unmanned and is remotely operated via a SCADA system at the Bersia Group Control Centre. In the late 1990s, facilities were added to enable Automatic generation control by TNB's National Load Despatch Centre in Kuala Lumpur.

Overview

Construction started in January 1974 and completed in mid-1978. The first unit commissioned on 1 October 1977.

Technical specifications

The permanent dam components are as follows:

  • Main Dam
    • Maximum height above foundation of {{convert|128|m}}, and crest length of {{convert|537|m}}, volume of fill is 7.09 million cubic metres.
    • Crest elevation is {{convert|258|m}} above sea level (ASL), Full Supply Level (FSL) is at EL 248.42mSLE, average operating level is at EL244.00mSLE, minimum operating level for Unit 1, Unit 3 and Unit 4 is at EL 236.5mSLE. For Unit 2, it can go down to EL 221mSLE.
    • Reservoir area at {{convert|245|m}} ASL is {{convert|152|km²}}. Storage volume is 5,300 million cubic meters at EL 244.00mSLE. At FSL total storage is 6,050 million cubic meters.
  • Power Intake Structure - 4 bays.
  • Spillway- free flow spillway, weir with chute and flip bucket.
    • Maximum discharge capacity at Reservoir Flood Level at EL 252.00mSLE is 2830m3/s. At this elevation the dam is holding 890million cubic meters of flood water or equivalent to 3months of annual average rainfall. This water will be discharge to downstream gradually in not less than one month.
  • Power Tunnels - 4 tunnels.
    • Length about 850 ft
    • Average diameter 5.5m, steel lined
  • Powerhouse
    • surface powerhouse
    • with 4 penstocks to powerhouse comprising 4 turbines of 87MW each, 4 air-cooled generators of 100MVA each and 4 transformers of 100MVA each.
    • Turbine type is vertical Francis, manufactured by HITACHI of Japan. Turbine shaft rated output is about 90MW at rated gross head of 101m.
    • Maximum plant discharge is 4X100m3/s.
    • Plant rated annual energy production is 870GWh based on annual rainfall of 3,700 million cubic meters.

Notable facts

Temenggor Dam is now the third largest dam in Malaysia. It was once the largest dam and largest hydroelectric generation facility upon completion in 1979, before being overtaken by the Kenyir Dam in 1985. It holds a special place in the history of Malaysia for its military role in flooding the Upper Perak River and cutting off the communist terrorists' infiltration route from the Betong salient in Thailand.

The dam was built by Shawnigan Engineering from Canada and the contractor was Hazama Gumi from Japan.

See also

{{stack|{{Portal|Malaysia|Water|Renewable energy}}}}
  • Tenaga Nasional

References

{{Temengor Hydro-Electric Project, The resident engineer's completion report, Vol.1, Report 5067-01-80, June 1980}}

External links

TNB webpage  {{Dead link|date=June 2018 |bot=InternetArchiveBot |fix-attempted=no }}

{{coord|5|24|24|N|101|18|04|E|region:MY-08_type:waterbody_source:GoogleEarth|display=title}}{{Northern Corridor Economic Region}}{{Malaysia-struct-stub}}{{Asia-dam-stub}}

3 : Hydroelectric power stations in Malaysia|Dams in Malaysia|Dams completed in 1972

随便看

 

开放百科全书收录14589846条英语、德语、日语等多语种百科知识,基本涵盖了大多数领域的百科知识,是一部内容自由、开放的电子版国际百科全书。

 

Copyright © 2023 OENC.NET All Rights Reserved
京ICP备2021023879号 更新时间:2024/11/10 12:38:53