请输入您要查询的百科知识:

 

词条 Edinburgh to Glasgow Improvement Programme
释义

  1. Aims

  2. Timeline of planned improvements

  3. Previous proposals

  4. Criticism

  5. References

  6. External links

{{refimprove |date=April 2017}}{{Use dmy dates|date=February 2017}}{{Use Scottish English|date=February 2017}}

The Edinburgh Glasgow Improvement Programme or EGIP is an initiative funded by Transport Scotland on behalf of the Scottish Government to increase capacity on the main railway line between Edinburgh and Glasgow, with new, longer electric trains running by 2017 and full completion in 2019.[1] It is expected to cost £742 million and will be delivered by Network Rail.

The programme was initially announced by the Labour-Liberal Democrat coalition government in 2006[2], and was continued, although cut back from the original scheme, by the subsequent Scottish National Party governments.

Aims

The project will deliver the infrastructure to enable 8 car, electric trains to operate (an increase from the previous 6 car maximum) on Edinburgh - Glasgow services with a fastest journey time of 42 minutes.

The additional train carriages will allow a total increase in capacity of 30%.

It will also deliver electrification of 94 miles of track including diversionary routes through Cumbernauld and Falkirk.

Timeline of planned improvements

  • December 2013 - Haymarket Station Redevelopment opens.[3]
  • May 2014 - Glasgow - Cumbernauld electrification complete.[4]
  • May 2015 - Haymarket - Inverkeithing signalling renewals complete.
  • July 2015 - Winchburgh Tunnel clearance completed.[5]
  • April 2016 - 61 Bridges and structures cleared for electrification.
  • August 2016 - Glasgow Queen Street (High Level) tunnel track and trackbed replacement completion.
  • October 2016 - Platform extensions at Linlithgow, Croy, Polmont and Falkirk High.
  • December 2016 - Platform extensions at Edinburgh Waverley.
  • December 2016 - Electrification of the Edinburgh to Glasgow via Falkirk High Line.
  • December 2016 - Edinburgh Gateway station opened.[6]
  • 2017 - Millerhill Depot opens.
  • December 2017 - Delivery of first new Hitachi Class 385 trains.[7]
  • July 2018 - first Hitachi Class 385 EMUs enter service.[8]
  • December 2018 - Platform extensions at Glasgow Queen Street.
  • December 2018 - Electrification of the Cumbernauld - Falkirk line.
  • March 2019 - Glasgow Queen Street redevelopment complete.

Previous proposals

As originally announced in 2006, the project would have cost £1 billion and aimed to increase capacity by increasing service frequency to 6tph rather than by lengthening trains.[9]

Transport Scotland commissioned Jacobs to examine the project for potential savings and they identified that the a similar capacity increase could be achieved by increasing train length while maintaining a 4tph frequency. This had previously been thought to be impossible due to restrictions at Glasgow Queen Street station. The redevelopment of Buchanan Galleries allowed this option to be developed instead with a major rebuild and the lengthening of platforms at Queen St high level station.[10]

This enabled several major schemes to be dropped from the scope of EGIP as they were only required if an increase in train frequency took place:

  • Construction of turnback sidings at Abbeyhill Junction and {{Stnlnk|Croy}}.
  • Remodelling of Greenhill Junction to provide a non-conflicting junction;
  • Construction of a new chord line at Dalmeny to allow trains from the west to access the Haymarket north lines..

Another proposed scheme the Garngad Chord, near {{Stnlnk|Springburn}} had already been dropped from the scheme. It was intended to allow Glasgow-Cumbernauld services to use the North Clyde Line into Queen Street Low Level, thus freeing up capacity on the High Level station. Instead services started on this route in 2014 with a reversal in Springburn, creating a slightly longer journey time.

Electrification to Stirling, {{Stnlnk|Alloa}} and {{Stnlnk|Dunblane}} was originally reported to have been dropped as part of the changes to EGIP. Electrification is continuing and is expected to be complete by 2018; it has been carried out under the rolling programme of electrification, rather than as part of the EGIP programme.

Criticism

The new proposals were criticised by business and environmental groups.[11] Sustainable transport campaign group Transform Scotland described the cuts as 'a major step backwards' and suggested that the government's concurrent decision to bring forward a £3 billion project to dual the A9 road demonstrated a 'perverse set of priorities'.[12][13]

The fastest journey times between Glasgow and Edinburgh under the scheme will now be 42 minutes compared to the just over half an hour previously promised.[14]

One of the most disruptive elements of the project was the complete closure of Glasgow Queen Street (High Level) for a 20-week period between March and August 2016,[15] to allow replacement of the track in the Cowlairs Tunnel and the lowering of the track bed to accommodate the installation of overhead electrification equipment in the tunnel. ScotRail warned that the diversion works created a potential single point of failure which could paralyse Glasgow's rail network in the event of a train failure or other incident.[16]

References

1. ^{{cite web|url=http://www.egip.info |title=EGIP}}
2. ^http://www.heraldscotland.com/opinion/13064417.It_is_surely_time_to_jump-start_electrification_of_our_railways/
3. ^{{cite web |url=https://www.bbc.co.uk/news/uk-scotland-edinburgh-east-fife-25447093 |title=Haymarket Station officially opened by Transport Minister |work=BBC News |publisher=BBC |date=19 December 2013 |accessdate=24 December 2013}}
4. ^{{Cite web|title = Cumbernauld electrification completed|url = http://www.railwaygazette.com/news/infrastructure/single-view/view/cumbernauld-electrification-completed.html|accessdate = 2015-06-22|first = DVV|last = UK}}
5. ^{{Cite web|title = Winchburgh Tunnel completed|url = http://www.rail.co.uk/rail-news/2015/egip-winchburgh-tunnrl-reopens/|accessdate = 2016-01-21}}
6. ^{{cite news|title=New Edinburgh Gateway interchange opens in capital|url=https://www.bbc.co.uk/news/uk-scotland-edinburgh-east-fife-38265174|accessdate=11 December 2016}}
7. ^https://www.bbc.co.uk/news/uk-scotland-38275332
8. ^https://www.bbc.co.uk/news/uk-scotland-glasgow-west-44910925
9. ^{{cite web | url=http://www.transportscotland.gov.uk/rail/rail-improvements/EGIP-2014 | title=Rail Electrification Programme - Control Period 5 (2014-19) | work=Transport Scotland | accessdate=18 October 2013}}
10. ^{{cite web | url=http://www.railengineer.uk/2013/06/04/egip-cutback-or-transformation/ | title=EGIP: cutback or transformation? | work=Rail Engineer | accessdate=21 January 2016}}
11. ^{{cite news | url=https://www.bbc.co.uk/news/uk-scotland-glasgow-west-18690764 | title=Rail journey times to be cut between Glasgow and Edinburgh | work=BBC News | date=4 July 2012 | accessdate=18 October 2013}}
12. ^{{cite web|url=http://www.transformscotland.org.uk/scottish-government-egip-announcement.aspx |title=Cuts to key Scottish rail project a major step backwards |work=Transform Scotland |date=4 July 2012 |accessdate=18 October 2013 |deadurl=yes |archiveurl=https://web.archive.org/web/20131019145345/http://www.transformscotland.org.uk/scottish-government-egip-announcement.aspx |archivedate=19 October 2013 |df= }}
13. ^{{cite news | url=https://www.bbc.co.uk/news/uk-scotland-scotland-politics-19564702 | title=Minister transport priorities wrong: Transform Scotland | work=BBC News | date=11 September 2012 | accessdate=18 October 2013 | author=Miller, David}}
14. ^{{cite news | url=https://www.bbc.co.uk/news/uk-scotland-25917817 | title=Cost of improving Glasgow to Edinburgh rail line 'up by £90m | work=BBC | date=31 March 2013 | accessdate=27 January 2014}}
15. ^{{cite web|last1=Dalton|first1=Alistair|title=Four months of major rail disruption ahead at Glasgow Queen Street|url=http://www.scotsman.com/news/transport/four-months-of-major-rail-disruption-ahead-at-glasgow-queen-street-1-3998694|website=The Scotsman |date=12 January 2016 |accessdate=22 February 2017}}
16. ^{{cite web|title=A single failure could stop Glasgow trains during Queen Street closure – Verster|url=http://www.railtechnologymagazine.com/Rail-News/a-single-failure-could-stop-glasgow-trains-during-queen-street-closure-verster|website=Railway Technology Magazine |date=10 March 2016 |accessdate=22 February 2017}}

External links

  • {{Official website|http://www.egip.info}}
{{Current rail infrastructure projects in the United Kingdom}}{{Railway lines in Scotland}}

10 : Rail infrastructure in Scotland|Electrification|Railway lines in Scotland|Scottish Government|Transport in Edinburgh|Transport in Glasgow|2006 establishments in Scotland|Transport in Falkirk (council area)|Transport in East Dunbartonshire|Transport in West Lothian

随便看

 

开放百科全书收录14589846条英语、德语、日语等多语种百科知识,基本涵盖了大多数领域的百科知识,是一部内容自由、开放的电子版国际百科全书。

 

Copyright © 2023 OENC.NET All Rights Reserved
京ICP备2021023879号 更新时间:2024/11/12 6:01:18