词条 | Geothermal power in Indonesia |
释义 |
With an achievement of 1,924.5 MW it put Indonesia in second place in the world after the United States in utilizing geothermal power, shifting second position previously occupied by the Philippines[2]. In 2007, geothermal energy represented 1.9% of the country's total energy supply and 3.7% of its electric power.[3] At the 2010 World Geothermal Congress in Bali, President Susilo Bambang Yudhoyono announced a plan to build 44 new geothermal plants by 2014, more than tripling capacity to 4,000 MW. By 2025, Indonesia aims to produce more than 9,000 MW of geothermal power, becoming the world's leading geothermal energy producer.[1] This would account for 5% of Indonesia's total energy needs.[3] A detailed report on the geothermal sector in Indonesia issued in 2015 by the Asian Development Bank and World Bank, Unlocking Indonesia's Geothermal Potential, indicated that reforms in key areas of policy were likely to be needed to stimulate sustained expansion in the sector. HistoryThe first proposal on energy from volcanoes came in 1918 during the Dutch colonial era. In 1926, five test borings were drilled in Java's Kawah Kamojang field, the third being the first that was successful.[4] In the early 1980s, it was still discharging superheated steam from a depth of 66 metres at a temperature of 140 °C and a pressure of 3.5 to 4 bars. A prefeasibility study for electricity generation was initiated in 1972 by Geothermal Energy New Zealand.[5] The first generator was inaugurated in 1983 by President Suharto and subsequently expanded in 1987. Current capacity is 140 MW.[6] Since the mid-1980s, Chevron, the world's largest geothermal power producer, has operated two geothermal fields in West Java at Salak and Darajat[7] with a combined capacity of around 365 MW.[8] Between 1989 and 1997 explorations were conducted at the Sibayak geothermal field in northern Sumatra,[9] and subsequently a 12 MW plant has been placed in operation.[10] In 1991, the Indonesia Geothermal Association (Asosiasi Panasbumi Indonesia - API), a non-governmental organisation, was established to promote and advertise geothermal energy. It has approximately 500 members including geothermal experts, companies, and stakeholders.[3] The Wayang Windu Geothermal Power Station in West Java, owned by British Star Energy, has been in operation since 2000. It currently comprises two units with a total capacity of 227 MW. There are plans for a third unit of 127 MW which is expected to be on-stream by mid-2013.[11] Exploration and developmentExploration of the Bedugul Geothermal Field in Bali started in 1974[12] and though production capacity was estimated at 175 MW in 2008, the project is on hold after being opposed by local residents.[13] At the 2010 World Geothermal Congress in Bali, several companies were awarded the rights to develop geothermal fields and power plants: Golden Spike Indonesia won the tender to develop a power plant at Mount Ungaran in Central Java, Sokoria Geothermal Indonesia gained rights to develop a plant at Ende, on Flores island, while Supreme Energy was chosen to develop plants at Mount Rajabasa in Lampung and Solok in West Sumatra. These projects were estimated to require a total investment of US$1.68 billion.[14] As of 2010, a total of 265 potential sites for plants have been identified across the country.[1] Development of the industry, however, involves a range of complex policy issues, some of which are proving to be a continuing source of controversy.[15] In mid-2011, for example, the Indonesian Government issued an expected regulation providing certain guarantees for investors with the aim of encouraging increased investment in the geothermal sector. However, investor response was guarded, suggesting that key aspects had not been addressed in the regulation.[16] In late 2013, PT Pertamina Geothermal Energy (PGE) -- a geothermal business branch of state oil and gas company PT Pertamina—said that it planned to develop eight new geothermal plants with a total capacity of 655 MW (expected to require $2.0 bn of new investments). These included: {{Columns|col1=
|col2=
}} Of these, several were to be financed with loans from World Bank and Japan International Cooperation Agency.[17] In addition, work is starting on the Sarulla geothermal plant in North Sumatra with a total planned capacity of 320 MW. The plant has been on the books since the early 1990s but development was stalled over various issues. The plant, expected to cost around $1.65 billion, will be built with financial support from the Asian Development Bank along with the Japan Bank for International Cooperation and other lenders.[18] The first 110 MW started in 2017.[19] Installed capacityAccording to the Renewable Energy Policy Network's Renewables 2013 Global Status Report, Indonesia has the third largest installed generating capacity in the world in the geothermal sector. With 1.3 GW installed capacity, Indonesia trails only the United States (3.4 GW) and the Philippines (1.9 GW). However it leads Mexico (1.0 GW), Italy (0.9 GW), New Zealand (0.8 GW), Iceland (0.7 GW), and Japan (0.5 GW).[20] Recent developmentsIn recent years, the Indonesian Government has announced plans for two 'fast-track' increases in the total capacity of Indonesia's electricity generation network of 10,000 MW each. Under the second 10,000 MW fast-track plan it was forecast that a relatively large share of 3,970 MW would be installed in geothermal plants. But under the first 10,000 MW fast-track plan, investment in the geothermal sector appears to be lagging.
Policy issuesExpansion in the sector appears to be being held back by a range of factors including an uncertain regulatory environment (including, especially, uncertainty over land laws) and the perceived risks of development.[26] The Indonesian Government's plans for development of the geothermal sector rely largely on private sector investment.[27] But numerous reports indicate that private sector investors are concerned about a range of risks including technical (geological) risks, regulatory risks stemming from uncertain government policy, and financial risks arising from the pricing policies determined by the Indonesian Government.[28] For example, coal has been indirectly subsidised through the Domestic Market Obligation policy, which requires coal companies to sell at a government-specified, subsidised rate to the national utility.[29] By comparison, geothermal power has enjoyed relatively unfavourable tender processes and is sold at higher prices. This makes it difficult for geothermal plants to compete with conventional fuels.[30] There is disagreement within the Indonesian Government as to how to mitigate risks or, where that is not possible, who should bear these risks. Policy makers in the power sector, with an eye to meeting the government's official investment targets, are often inclined to the view that at least some of the risks should be borne by the Indonesian Government through the national budget managed by the Ministry of Finance.[31] Official policy from the Ministry of Finance has traditionally been cautious, resisting the suggestion that unspecified risks should be borne by the Indonesian budget. In response to reports about certain of the risks that private sector investors were concerned about, in mid-2011 the government issued a regulation intended to provide guarantees that the state electricity utility PLN would meet financial obligations to independent power producers (IPPs) who invested in the geothermal sector. But the regulation was quickly criticised by representatives of private investors as being too limited and for failing to clarify important concerns.[32] Pricing policyPrices have been another important policy issue in the sector. In an effort to encourage private sector investment, the Indonesian government has been establishing a feed-in tariff scheme by instructing state electricity utility PLN to purchase power from geothermal projects at various rates ranging from around 6.5 US cents to over 12 US cents per kWh.[33] The government is also preparing a regulation that is expected to specify the price that the PLN must purchase power from geothermal plans in the second 10,000 MW fast-track electricity sector program which the government has announced; this regulation is expected to be finalised by early 2012.[34] Environmental issuesAccording to the Ministry of Forestry, around 80% of geothermal reserves are located in designated conserved forest areas. The 2009 mineral and coal mining law lists geothermal exploration as a mining activity so a presidential decree would be required to allow geothermal activities conserved forest areas. According to the ministry, geothermal mining is unlikely to cause environmental harm.[35] In May 2011 the Indonesian government imposed a two-year moratorium on logging. However this excepts the energy sector, including geothermal activities.[36] See also{{Portal|Renewable energy|Indonesia}}
References1. ^1 2 Tom Allard: "Indonesia's hot terrain set to power its future", The Sydney Morning Herald, 1 May 2010, retrieved 25 August 2010 2. ^{{Cite web|url=http://www.thinkgeoenergy.com/indonesia-reaches-1925-mw-installed-geothermal-power-generation-capacity/|title=Indonesia reaches 1,925 MW installed geothermal power generation capacity|website=Think GeoEnergy - Geothermal Energy News|language=en-US|access-date=2019-01-10}} 3. ^1 2 International Energy Agency: Energy Policy Review of Indonesia, Paris, 2008 {{ISBN|978-92-64-04828-7}}, retrieved 26 August 2010 4. ^M. Neumann Van Padang:The steam borings in Kawah Kamodjang, in Bulletin of Volcanology, Volume 23, Number 1, 251-255, {{doi|10.1007/BF02596652}}, retrieved 25 August 2010 5. ^Wilson, Raymond: Stage 1 Development of the Kamojang Geothermal Power Station and Steamfield - West Java, Indonesia, Offshore South East Asia Show, Singapore, 1982, retrieved 26 August 2010 6. ^Indonesia Power: Kamojang Generation Business Unit {{webarchive|url=https://web.archive.org/web/20101102054135/http://indonesiapower.co.id/index.php?option=com_content&view=article&id=151%3Aunit-bisnis-pembangkitan-kamojang&catid=64%3Abusiness-unit&Itemid=92 |date=2010-11-02 }}, retrieved 26 August 2010 7. ^[https://www.nytimes.com/2010/07/27/business/global/27iht-renindo.html?_r=1&ref=geothermal-power Hillary Brenhouse:Indonesia Seeks to Tap Its Huge Geothermal Reserves, in the New York Times, July 26, 2010], retrieved 25 August 2010 8. ^[https://www.reuters.com/article/idUSJAK17573620071101 Reuters:Chevron Indonesia plans to expand geothermal power, Nov 1, 2007], retrieved 25 August 2010 9. ^Atmojo,J.O. et al: Evaluation of Reservoir Characteristics Using Well Data of Sibayak Geothermal Field, North Sumatra, Indonesia in Mem Fac Eng Kyushu Univ, Vol.60, No.3, 2000, retrieved 30 August 2010 10. ^PT Pertamina: Working Area Maps {{webarchive|url=https://web.archive.org/web/20110715072007/http://pgeindonesia.com/index.php?lang=en&option=com_content&view=article&id=27&Itemid= |date=2011-07-15 }} {{id}}, retrieved 30 August 2010 11. ^www.power-technology.com: Wayang Windu Geothermal Power Station, retrieved 25 August 2010{{Unreliable source?|reason=domain on WP:BLACKLIST|date=June 2016}} 12. ^Hochstein, M. P. et al.:The Bedugul Geothermal Field, Bali, in International Geothermal Association (IGA) News, No.59, 2005 {{webarchive|url=https://web.archive.org/web/20080807134121/http://www.geothermal.org/IGANews/IGANews0305.pdf |date=2008-08-07 }}, retrieved 11 August 2010 13. ^[https://www.reuters.com/article/idUSJAK14417520080630 Davies, Ed and Lema, Karen:Geothermal-rich SE Asia struggles to tap earth's power, in Reuters Jun 28, 2008], retrieved 11 August 2010 14. ^Indonesian Embassy, Rome, retrieved 30 August 2010 15. ^Surya Darma, Sugiharto Harsoprayitno, Herman Darnel Ibrahim, Agusman Effendi, Agus Triboesono (2010), 'Geothermal in Indonesia: Government Reguatlions and Power Utilities, Opportunities and Challenges of its Development', in Proceedings World Geothermal Congress 2010, Bali Indonesia, 25–30 April. 16. ^Rangga D. Fadillah, Govt guarantee for IPP projects is 'unclear', The Jakarta Post, 13 September 2011. 17. ^Yessar Rosendar:Pertamina Geothermal Receives $1b In Loans to Develop 3 Power Plants, in Jakarta Globe, December 14, 2009, retrieved 30 August 2010 18. ^Raras Chahyafitri, 'Sarulla plant construction set for March', The Jakarta Post, 27 November 2013. 19. ^http://www.power-technology.com/projects/sarullgeothermalpowe/ 20. ^Renewables 2013 Global Status Report{{dead link|date=October 2017 |bot=InternetArchiveBot |fix-attempted=yes }} 21. ^Rangga D. Fadillah, 'Electricity: Delays may hit several geothermal projects', The Jakarta Post, 1 October 2011. 22. ^Rabby Pramudatama, 'PLN's geothermal plants likely to miss deadline', The Jakarta Post, 26 July 2012. 23. ^Slamet Susanto, 'RI's geothermal energy still "untouched"', The Jakarta Post, 13 June 2013, and {http://www.thejakartapost.com/news/2013/06/13/govt-set-raise-prices-geothermal-power.html Govt set to raise prices of geothermal power'], The Jakarta Post, 13 June 2013. 24. ^Amal S. Azwar, 'Protests freeze out Lampung geothermal power plant', The Jakarta Post, 20 June 2013. 25. ^Raras Cahyafitri, 'Legal barrier to geothermal development removed', The Jakarta Post, 27 August 2014. 26. ^Hanan Nugroho, 'Geothermal: Challenges to keep the development on track', The Jakarta Post, 23 October 2013. 27. ^A comment on the issues holding geothermal issues back from the private sector point of view is in an interview with a senior Chevron executive at 'Executive Column: Better pricing structure needed for geothermal development: Cheveron', The Jakarta Post, 5 May 2014. 28. ^Rangga D. Fadillah, 'Geothermal firm awaiting govt contract assurance', The Jakarta Post, 18 August 2011 29. ^{{Cite journal|last=Chattopadhyay D, Jha S|date=2014|title=The impact of energy subsidies on the power sector in Southeast Asia|url=https://www.sciencedirect.com/science/article/pii/S1040619014000839|journal=The Electricity Journal|volume=27 |issue=4|pages=70–83|via=|doi=10.1016/j.tej.2014.04.007}} 30. ^{{Cite journal|last=Colenbrander S, Gouldson A, Sudmant AH, Papargyropoulou E|date=2015|title=The economic case for low-carbon development in rapidly growing developing world cities: A case study of Palembang, Indonesia|url=https://www.sciencedirect.com/science/article/pii/S030142151500021X#bib14|journal=Energy Policy|volume=80|pages=24–35|via=|doi=10.1016/j.enpol.2015.01.020}} 31. ^See the suggestions for reducing risk for private investors from the president director of the Indonesian electricity company in Rangga D. Fadillah, 'Electricity: Delays may hit several geothermal projects', The Jakarta Post, 1 October 2011. 32. ^Rangga D. Fadillah, 'Govt guarantee for IPP projects is 'unclear' ', The Jakarta Post, 13 September 2011. 33. ^'Power deals signed to up electrification rate', The Jakarta Post, 4 November 2011. See also Kemal Azis Stamboel, 'Fuel mix policy and energy security', The Jakarta Post, 2 January 2012. 34. ^Rangga D. Fadillah, 'More regulations planned to boost geothermal use', The Jakarta Post, 8 November 2011. 35. ^Rangga D Fadillah, 'Govt to allow geothermal mining activities in conserved forests' in The Jakarta Post, 13 January 2011 36. ^Reuters, 20 May 2011 External links
2 : Geothermal energy in Indonesia|Energy in Indonesia |
随便看 |
|
开放百科全书收录14589846条英语、德语、日语等多语种百科知识,基本涵盖了大多数领域的百科知识,是一部内容自由、开放的电子版国际百科全书。