词条 16th Street Bridge (Washington, D.C.)
释义

  1. Description

  2. Construction

     Authorization of the first span  Constructing the first span  Designs and selection of contractor   8-hour day law dispute  Completion  Construction of the second span 

  3. Operation

     Effects  Renovations 

  4. References

     Notes  Citations  Bibliography 

  5. External links

{{Infobox bridge
| bridge_name = 16th Street Bridge
| image = West Elevation-16th Street Bridge over Piney Branch-Washington DC 1993.jpg
| image_size =
| alt = Looking slightly up at a black and white image of a Neoclassical concrete bridge over a road
| caption = Looking at the west side of the 16th Street Bridge from Piney Branch Parkway NW
| other_name = Piney Branch Bridge
| carries = 16th Street NW
| crosses = Piney Branch and Piney Branch Parkway
| locale = Washington, D.C., U.S.
| owner = District of Columbia Department of Transportation
| maint = District of Columbia Department of Transportation
| architect = J.J. Morrow and W.J. Douglas
| length = {{convert|272|ft|m}}
| width = {{convert|61|ft|m}}
| mainspan = {{convert|125|ft|m}}
| spans = 1
| load = {{convert|40|ST|MT}}
| builder = Pennsylvania Bridge Company (first span);
Cranford Paving Company (second span)
| begin = September 1905 (first span);
June 1909 (second span)
| complete = January 1908 (first span);
April 1910 (second span)
| cost = $165,000 (${{formatnum:{{inflation|US|165000|1910}}}} in {{Inflation-year|US}} dollars)
| open = {{Start date|1910|04|15}}
| traffic = 30,000 vehicles per day
| coordinates = {{coord|38.9382|-77.0364|region:US-DC_type:landmark|display=inline,title}}
| references =
}}

The 16th Street Bridge, also known as the Piney Branch Bridge, is an automobile and pedestrian bridge that carries 16th Street NW over Piney Branch and Piney Branch Parkway in Washington, D.C. It was the first parabolic arch bridge in the United States. Construction on the first span began in 1905 as part of the northward extension of 16th Street, and was finished in 1907 but was never opened to traffic. The second span began construction in 1909 and was completed in 1910. The bridge was renovated in 1990, and again beginning in October 2014.

The bridge, which spans the Piney Branch addition to Rock Creek Park, sits at the corner of four Washington, D.C., neighborhoods: Sixteenth Street Heights, Crestwood, Columbia Heights, and Mount Pleasant.

Description

The 16th Street Bridge is {{convert|272|ft|m}} long.[1]{{sfn|Myer|1974|page=74}} Its span is {{convert|125|ft|m}} in length, and has a rise of {{convert|45|ft|m}}.[2] The span is a parabolic arch, the first built in the United States[3]{{sfn|Myer|1974|page=73}} and the longest in the world at the time, according to its designer, W.J. Douglas.[2] The abutments and substructure of the bridge are of reinforced concrete;[1][2][7] the arch itself is not reinforced with steel.[2] The interior of the bridge is hollow. Square vertical interior columns {{convert|2|ft|m}} in length on each side support the road deck. A latticework of horizontal square beams, each {{convert|1|sqft|m2}} in size, intersect the columns and are set perpendicular to one another. This system of columns and beams compress the arch and keep it stable as well push outward against the walls.[9]{{sfn|Myer|1974|page=73}} The bridge's abutments are hollow.[1][2] The abutments are stabilized by soil pressing against them from the outside, and the system of beams and columns on the interior of the bridge.[1][9]

The walls of the bridge and the abutments are {{convert|2|ft|m}} thick.[2] A bluish crushed diorite was added to the concrete used to pour the walls of the abutments and the spandrel walls, which were left unfinished, and reflect the texture of the wooden forms used to create them.{{sfn|Sullivan|1908|page=156}} However, the archivolt, balustrade, and pilasters, whose concrete includes yellow sand and crushed granite, have a much different texture.{{sfn|Sullivan|1908|page=156}} These elements were removed from their molds before the concrete was fully hardened, then roughened with stiff brushes, helping to expose the granite particles within and make them glitter in the sun.{{sfn|Piney Branch Bridge Finished|1910|page=878}}

The bridge superstructure rests on walls and columns.[2] The {{convert|25|ft|m|adj=on}} wide spans[1] are of reinforced concrete.[2] Steel beams, their ends resting on the walls of the two bridges, close the gap between the spans.[2] Reinforced concrete slabs lie atop these beams to create a unified deck.[2] Concrete balustrades and newels create a railing on the east and west sides of the bridge.[7]{{sfn|Piney Branch Bridge Finished|1910|page=878}} The road is {{convert|45|ft|m}} wide, and {{convert|8|ft|m|adj=on}} sidewalks are on either side of the roadway.{{sfn|Myer|1974|page=74}} Granite curbs define the cement sidewalk.{{sfn|Piney Branch Bridge Finished|1910|page=878}} The deck is topped by asphalt.[2]{{sfn|Piney Branch Bridge Finished|1910|page=878}} At {{convert|65|ft|m}} in width (roadway and sidewalks), the deck was the widest in the city when built and could support {{convert|40|ST|MT}}.[7]

The bridge has four ornamental cast iron lampposts.[7] The ends of the bridge are flanked by two bronze reclining tigers on concrete pedestals.[24] The archivolt consists of three arch rings, and is of smoothed concrete.{{sfn|Myer|1974|page=74}} Pilasters flank the arch on the sides of the bridge. Stylistically, the bridge is Neoclassical in design.{{sfn|Myer|1974|page=74}}

The bridge cost about $135,000 to build.{{sfn|Myer|1974|page=74}}

Construction

Authorization of the first span

On March 30, 1899, the United States Congress authorized the extension of 16th Street NW from Morris Road NW (now Monroe Street NW) to the D.C.-Maryland line. Condemnation proceedings to obtain land began on December 2, 1900, were completed on May 27, 1901, and were approved by the Supreme Court of the District of Columbia on April 19, 1902.[1] By November 1903, work had almost reached the stream known as Piney Branch, which runs through a valley about {{convert|60|ft|m}} below the grade of the street. On December 10, 1903, the Commissioners of the District of Columbia{{Efn|Beginning in 1874, the District of Columbia was run by three commissioners, two of which were appointed by the President of the United States with the approval of the Senate and a third member who was selected by the United States Army Corps of Engineers (and who had oversight over the city's public works). One of the civilian members was chosen to act as president of the city commission.}}{{sfn|Crew|Webb|Wooldridge|1892|page=159}} asked Congress for a {{convert|300|ft|m|adj=on}} bridge to carry one or two lanes of 16th Street NW over Piney Branch. The bridge, whose cost was estimated at $50,000 (${{formatnum:{{inflation|US|50000|1903}}}} in {{Inflation-year|US}} dollars), would be long enough to permit a parkway to pass beneath it.[2]

In March 1904, the commissioners' request finally saw action. Senator Jacob Gallinger (R-New Hampshire) offered an amendment to the Senate's 1905 District of Columbia appropriations bill which both authorized the city to construct the bridge and appropriated{{Efn|In public budgeting, a program must be authorized by law first. Often, an authorization sets the maximum amount of funds a program may expend in a single year. This does not mean the program is actually funded. An appropriation is needed to actually given the authorized program access to funds. Appropriations may be less than, equal to, or more than the authorization.}}{{sfn|Lee|Johnson|Joyce|2013|pages=315–318}} $50,000 (${{formatnum:{{inflation|US|50000|1904}}}} in {{Inflation-year|US}} dollars) for this purpose.[3] The House D.C. appropriations bill also contained the same language, but this provision was stricken from the bill on the floor of the house on March 18.[4] Undeterred, the Senate Committee on the District of Columbia included the bridge authorization in the 1905 D.C. appropriations bill just five days later. The legislation, however, authorized a $50,000 concrete bridge but appropriated only $20,000 (${{formatnum:{{inflation|US|20000|1904}}}} in {{Inflation-year|US}} dollars) for its construction.[5] Half the money came from the federal government, and half from the city.[6]

A fight erupted on the floor of the Senate over the bridge provision. Both the Senate Appropriations Committee and the Senate Committee on the District of Columbia approved the bridge.[7] But many Senators were unhappy that the federal budget was increasing rapidly. The bill was held up for 10 months, while Senators worked behind the scenes to resolve these differences. The D.C. appropriations bill did not reach the Senate floor for another 10 months. When the bill did reach the chamber floor on February 15, 1905, Senator Stephen B. Elkins (R-West Virginia) demanded that the bridge provision be removed. Senator William B. Allison (R-Iowa) rose to support the expenditure.[6] Their floor fight lasted three full days. Elkins claimed on February 16 that no citizens of the city wanted the bridge, and he demanded a full Senate vote on the bridge amendment.[8] Senator Allison replied on February 17 by bringing in petitions from the Brightwood Citizens Association and the Mt. Pleasant Citizens Association asking for construction of the bridge, and pointing out that these petitions had been delivered to the Senate some months ago.[9] Although Elkins won a vote on the amendment, the Senate overwhelmingly approved its inclusion in the final bill on February 17, ending the three-day floor fight.[10]

A conference committee was now appointed by the House and Senate to reconcile the two different D.C appropriations bills. The House voted on February 18 to instruct its conferees to oppose the bridge amendment.[11] The conference began meeting the week of February 20.[12] On Sunday, February 26, the conferees agreed to include the bridge authorization and expenditure in the 1905 D.C. appropriations bill.[13] The conference bill was introduced in the Senate on February 28, and hours later it approved the legislation.[14] The House unanimously approved it on the afternoon of March 1.[15] President Theodore Roosevelt signed the bill into law a few days later.

Constructing the first span

Designs and selection of contractor

At the time the bridge was approved, Piney Branch was nearly impassable. A rough pine bridge existed at the site of the new bridge to permit pedestrian traffic, while horses and wagons used a nearby ford.[16]

With four months to prepare architectural designs for the bridge before the federal funds became available, the city was ready to build the bridge in July 1905. Major J.J. Morrow, Assistant Engineer Commissioner for the District of Columbia, and W.J. Douglas, Engineer of Bridges for the District of Columbia, submitted sketches of the bridge to the commissioners on July 12.[17] The bridge's final design was by Douglas and city engineer William N. Reynolds (who was also the engineer in charge of construction).{{sfn|Piney Branch Bridge Finished|1910|page=878}} H.T. Pratt was the architectural draughtsman.[18] Stylistically, the 16th Street Bridge was to look like the Connecticut Avenue Bridge (built between 1897 and 1907).[19] Their design for the concrete bridge showed a span {{convert|125|ft|m}} long and a road deck {{convert|20|to|25|ft|m}} wide,[17][20] and with as much ornamentation as budget would allow.[20] By early August, the plans for the bridge were complete. The bridge would be {{convert|272|ft|m}} long, with a {{convert|25|ft|m|adj=on}} wide road deck. The {{convert|125|ft|m|adj=on}} long span would rise {{convert|60|ft|m}} above the valley floor. The bridge would be made of reinforced concrete and steel, with hollow spandrels between the arch and abutments. The roof and walls of the arch and the walls of the abutments ranged from {{convert|10|to|20|in|cm}} in thickness. Square columns, {{convert|2|ft|m}} in length on each side, supported the road deck, and were linked internally by a latticework of {{convert|1|sqft|m2}} horizontal concrete beams (which helped to compress the arch and keep it stable as well push outward against the walls).[21]

Although the Piney Branch Bridge (as it was then known) was designed to carry two lanes of traffic and be a completed structure, the D.C. Commissioners expected to build a second span as soon as possible.[2][21] This would expand the road deck to {{convert|70|ft|m}}.[21] Subsequently, the first span was built {{convert|20|ft|m}} off the centerline of 16th Street.[2][22]

Engineers estimated the foundations for the bridge would be complete before the onset of cold weather in December.[21] Construction bids were advertised on August 26, 1905,[23] and six bids were received by the September 16 deadline.[16][24] The Pennsylvania Bridge Company was selected to construct the bridge.[25]{{sfn|Myer|1974|page=74}} Although Congress had appropriated only $20,000 for the job, the city issued a contract worth $42,731 (${{formatnum:{{inflation|US|42731|1905}}}} in {{Inflation-year|US}} dollars).[26]

8-hour day law dispute

In 1892, Congress enacted an eight-hour day law which applied to contractors doing work on behalf of the federal government. As the District of Columbia was a creature of the federal government, the law also applied to city workers and contractors engaged in work for the city.{{sfn|Committee on Education and Labor|1902|page=47}}

In July 1906, a broad investigation into violation of the eight-hour day law by the Pennsylvania Bridge Company was begun by federal inspectors.[27] The company was indicted on July 28, and plead not-guilty.[28] On October 1, city attorneys charged the company with additional violations of the eight-hour law. Initially, John Meigs, the civil engineer in charge of the work, refused to surrender the company's accounting books to the grand jury investigating the alleged crime. The grand jurors complained to D.C. criminal court, which threatened the company with contempt of court. After a discussion between company lawyers and the city, the books were released to the grand jury.[29] The company was again indicted, and again plead not guilty.[30]

The Pennsylvania Bridge Company admitted it had forced workers to stay on the job nine and sometimes 10 hours a day. But it offered two defenses. First, the company said that the District of Columbia had set such stringent deadlines for construction that the company had no choice but to violate the law. Second, the company said that many skilled workers would not work for less than 10 hours a day, and it had acceded to their demands. Neither argument was persuasive to the jury, and the company was found guilty. A $1,500 fine (${{formatnum:{{inflation|US|1500|1906}}}} in {{Inflation-year|US}} dollars) was imposed on the firm.[31]

Completion

With the bridge's foundations and abutments underway, additional federal funds were needed to complete the span and road deck. In October 1905, the D.C. Commissioners requested another $30,000 (${{formatnum:{{inflation|US|30000|1905}}}} in {{Inflation-year|US}} dollars) from Congress.[32] The Subcommittee of the House Appropriations Committee added the $30,000 appropriation, and legislation making the appropriation passed on April 17, 1906.[33] By June 30, the end of the fiscal year, $15,000 (${{formatnum:{{inflation|US|15000|1906}}}} in {{Inflation-year|US}} dollars) had been expended on the bridge's construction.[34]

The bridge was poured in place.{{sfn|Myer|1974|page=74}} By mid-November 1906, the bridge was halfway completed, and construction officials estimated it would be finished in early 1907.[35] This estimate proved significantly over-optimistic. On December 1, company officials declared the bridge "almost ready", except for the approaches.[36]{{Efn|Approaches are the portion of a roadway connecting with a bridge which has no reasonable other use than as a means of connecting to the bridge. Approahces may be nonexistent in some cases, while in others they may consist of embankments, ramps, and other elements.}} Yet, a month later, the bridge was still under construction.[37] By mid-March 1907, construction was still not finished.[38]

Finally, on June 9, contractors said the bridge would be completed on July 1, 1907.[39][40] The approaches, however, were not complete. D.C. officials had only just received seven bids for their construction, and awarded the $28,000 contract (${{formatnum:{{inflation|US|28000|1907}}}} in {{Inflation-year|US}} dollars) to Hoffman Construction.[40] The total cost of the structure was estimated to be between $44,000[41] and $60,000 (${{formatnum:{{inflation|US|44000|1907}}}} to ${{formatnum:{{inflation|US|60000|1907}}}} in {{Inflation-year|US}} dollars).[42]

Work on grading the approaches was still going on in October 1907.[43] At that time, Hoffman Construction estimated they would be done by January 1, 1908.[44] Grading was nearly complete by early December 1907.[45]

The 16th Street Bridge was completed and ready to accept traffic on December 27, 1907. Commissioners Henry B.F. Macfarland and J.J. Morrow drove over the bridge to inaugurate it informally.[46] The bridge was not, however, actually opened to traffic. It remained complete but closed.[41][47]

Construction of the second span

By 1908, the economizing mood of Congress had lessened. D.C. officials sought permission to complete the second span of the 16th Street Bridge, and on April 28, 1908, Senator Thomas H. Carter (R-Montana) offered an amendment to the D.C. appropriations bill to authorize construction of a second span and widen the bridge to a full {{convert|60|ft|m}}. No funds were appropriated for this purpose, however.[48] The amendment was not accepted, and the 1909 fiscal year started without them.

in December 1908, the D.C. Commissioners again asked Congress for permission to build a second span. The roadway would not be {{convert|65|ft|m}}, and the span's cost estimated at $85,000 (${{formatnum:{{inflation|US|85000|1908}}}} in today's dollars).[49] The House Appropriations Committee approved the funding request on January 6, 1909.[50] The Subcommittee on the District of Columbia of the Senate Appropriations Committee followed suit on February 2.[51] A House–Senate conference committee approved the funding on February 27,[52] and President Theodore Roosevelt signed the legislation into law.[41]

The D.C. Commissioners advertised for construction bids on May 8, 1909.[53] Eight bids were received,[54] with Cranford Paving Company receiving the contract.{{sfn|Myer|1974|page=74}} Design of the second span was nearly the identical to the first, and Captain Edward M. Markham (assistant to the engineer commissioner) and C.B. Hunt (D.C. Engineer of Highways) oversaw the construction. The estimated time for completion of the span was January 1, 1910.[55]

As with the first span, the second span was poured in place.{{sfn|Myer|1974|page=74}} Although construction of the first span had occurred without any reported accidents, construction on the second span did not proceed as safely. On August 14, 1906, an African American worker had his hand crushed on the job site.[56] Despite the accident, construction officials still estimated the time of completion at January 1.[57]

On September 22, 1909,{{sfn|Commissioners of the District of Columbia|1910|page=294}} the city entered into a contract with sculptor A. Phimister Proctor to sculpt four reclining tigers in bronze to adorn the ends of the bridge.[22] It is not clear how Proctor was chosen for the job. As models, Proctor studied tigers at the Bronx Zoo, and he sculpted the statues in his New York City studio. The Gorham Company cast the statues, each of which was {{convert|10|ft|m}} long and weighed {{convert|1|ST|MT}}.{{Efn|Proctor cast four tigers for the Piney Branch Bridge. After slightly changing the models, two more were cast for placement outside Nassau Hall at Princeton University.}}[58][59]

In October 1909, the city advertised bids for lighting for the bridge. Four ornamental lampposts, in either bronze or cast iron, were required. Five bids were received in November,[60] R. L. Watmaugh, a Washington architect, received the lighting contract.{{sfn|Piney Branch Bridge Finished|1910|page=878}} The lamps were incandescent lights which used a tungsten filament. An armored steel cable, run under the granite curb, provided power to the lights.{{sfn|Allen|1910|page=401}} Each light gave off 100 watts or 78.48 candela. The lamppost had three globes: A {{convert|24|in|cm|adj=on}} central globe and two {{convert|17|in|cm|adj=on}} side globes. The central globe was {{convert|20|ft|m}} above the roadway, and each lamppost was {{convert|160|ft|m}} apart.{{sfn|Allen|1910|page=405}}

A second accident occurred during the construction of the second span on March 16, 1909. Howard Hurley, a 43-year-old African American worker, died instantly when a wooden beam fell on his skull, crushing it.[61]

As the bridge neared completion, D.C. architect R. L. Watmaugh won a contract to design and manufacture ornamental concrete balustrades for either side of the bridge.[22] The two separate spans were linked as construction ended. Holes were cut in the top of the western wall of the first span. Steel beams were laid at intervals across the open space, the ends of each beam resting on the wall of the span. A concrete slab was then laid across the beams to create the roadway's sub-deck.[36] The 16th Street Bridge opened to traffic on April 15, 1909. The total cost of both spans was estimated at $140,000 (${{formatnum:{{inflation|US|140000|1910}}}} in today's dollars).[22]

Operation

Effects

A few weeks after the bridge opened, contractors completed a $30,000 (${{formatnum:{{inflation|US|30000|1910}}}} in today's dollars) road project that extended 16th Street several blocks north of the 16th Street Bridge.[39]

The impact of the 16th Street Bridge was substantial. The Mt. Pleasant Heights subdivision opened shortly after construction of the first span, and building lots sold briskly.[39] The price of land along 16th Street NW skyrocketed by 500 percent from 1904 to 1910.[62] In December 1911, the Sixteenth Street Heights subdivision opened. Developers reported that they had seen a 200 percent increase in property values since the second span opened.[63]

Renovations

In 1990, the 16th Street Bridge underwent its first renovation. The extent of the work was not clear, but the $3 million (${{formatnum:{{inflation|US|3000000|1990}}}} in {{Inflation-year|US}} dollars) project took 15 months to complete. At least one lane of the bridge was closed during rush hour.[64] The Proctor tigers were regilded during the renovation.[19]

References

Notes

{{notelist}}

Citations

1. ^{{cite news|title=His Annual Report|newspaper=The Evening Star|date=November 11, 1902|page=7}}
2. ^{{cite news|title=Engineer Department|newspaper=The Evening Star|date=November 10, 1903|page=13}}
3. ^{{cite news|title=Judges Want Increase|newspaper=The Evening Star|date=March 7, 1904|page=7}}
4. ^{{cite news|title=On the District Bill|newspaper=The Evening Star|date=March 18, 1904|page=8}}
5. ^{{cite news|title=Reported to Senate|newspaper=The Evening Star|date=March 23, 1904|page=2}}
6. ^{{cite news|title=Money For District|newspaper=The Evening Star|date=February 15, 1905|page=1}}
7. ^{{cite news|title=The District Bill|newspaper=The Evening Star|date=April 25, 1904|page=1}}
8. ^{{cite news|title=Municipal Building|newspaper=The Evening Star|date=February 16, 1905|page=2}}
9. ^{{cite news|title=The Piney Branch Bridge|newspaper=The Evening Star|date=February 17, 1905|page=1}}
10. ^{{cite news|title=A Three Days' Fight|newspaper=The Evening Star|date=February 17, 1905|page=1}}
11. ^{{cite news|title=The District Bill|newspaper=The Evening Star|date=February 18, 1905|page=1}}
12. ^{{cite news|title=The Week Ending Feb. 25, 1905|newspaper=The Evening Star|date=February 25, 1905|page=3}}
13. ^{{cite news|title=The District Bill|newspaper=The Evening Star|date=February 28, 1905|page=1}}
14. ^{{cite news|title=Liberal to District|newspaper=The Washington Post|date=March 1, 1905|page=5}}
15. ^{{cite news|title=The District Bill|newspaper=The Evening Star|date=March 1, 1905|page=1}}
16. ^{{cite news|title=Piney Branch Bridge|newspaper=The Evening Star|date=September 16, 1905|page=16}}
17. ^{{cite news|title=Bridge Over Piney Branch|newspaper=The Washington Post|date=July 13, 1905|page=12}}
18. ^{{cite news|title=Orders Issued By Commissioners|newspaper=The Evening Star|date=January 13, 1906|page=6}}
19. ^{{cite news|last=Bisbort|first=Alan|title=The Draw of Bridges|newspaper=The Washington Post|date=April 10, 1992|pages=A8-A9}}
20. ^{{cite news|title=Bridge Across Piney Branch|newspaper=The Evening Star|date=July 13, 1905|page=12}}
21. ^{{cite news|title=Piney Branch Bridge|newspaper=The Evening Star|date=August 3, 1905|page=6}}
22. ^{{cite news|title=Bridge Nearly Ready|newspaper=The Washington Post|date=March 25, 1910|page=16}}
23. ^{{cite news|title=Proposals|newspaper=The Washington Post|date=August 26, 1905|page=B3}}
24. ^{{cite news|title=Bids for new Bridge Opened|newspaper=The Washington Post|date=September 17, 1905|page=5}}
25. ^{{cite news|title=Concrete Bridge Contract|newspaper=The Washington Post|date=September 21, 1905|page=10}}
26. ^{{cite news|title=Affairs of the District|newspaper=The Evening Star|date=December 5, 1905|pages=17, 21–22}}
27. ^{{cite news|title=Probing Violations of the 'Eight-Hour Law'|newspaper=The Washington Post|date=July 24, 1906|page=4|postscript=none}}; {{cite news|title=District of Columbia: Death of Col. Samuel Donelson, A Former Doorkeeper of the House|newspaper=The Baltimore Sun|date=July 24, 1906|page=2}}
28. ^{{cite news|title=Hogan Demands Jury Trial|newspaper=The Washington Post|date=July 29, 1906|page=E1}}
29. ^{{cite news|title=Bridge Builders Indicted|newspaper=The Washington Post|date=October 2, 1906|page=9|postscript=none}}; {{cite news|title=Violating the 8-Hour Law|newspaper=The Evening Star|date=October 2, 1906|page=7}}
30. ^{{cite news|title=Pleads Not Guilty|newspaper=The Evening Star|date=October 13, 1906|page=6|postscript=none}}; {{cite news|title=District of Columbia: Religious Disagreement Causes a Suit for Limited Divorce|newspaper=The Baltimore Sun|date=October 13, 1906|page=2}}
31. ^{{cite news|title=Penn Company Fined $1,500|newspaper=The Washington Post|date=October 18, 1906|page=2}}
32. ^{{cite news|title=Annual Estimates|newspaper=The Evening Star|date=October 10, 1905|page=2}}
33. ^{{cite news|title=Cut by $2,330,233|newspaper=The Washington Post|date=April 17, 1906|page=4}}
34. ^{{cite news|title=Big Bridge Ready Soon|newspaper=The Washington Post|date=October 11, 1906|page=2}}
35. ^{{cite news|title=Board of Trade Elects Directors|newspaper=The Evening Star|date=November 13, 1906|page=9}}
36. ^10 11 12 13 14 {{cite news|title=One of the Finest|newspaper=The Sunday Star|date=December 2, 1906|page=15}}
37. ^{{cite news|title=District Government|newspaper=The Evening Star|date=January 1, 1907|page=10}}
38. ^{{cite news|title=For County Roads|newspaper=The Evening Star|date=March 16, 1906|page=18}}
39. ^{{cite news|title=Finishing New Bridge|newspaper=The Washington Post|date=June 9, 1907|page=R2}}
40. ^{{cite news|title=Award of Contract|newspaper=The Evening Star|date=June 9, 1907|page=28}}
41. ^{{cite news|title=Bridge To Be Finished|newspaper=The Washington Post|date=May 21, 1909|page=3}}
42. ^{{cite news|title=Bridge Increases Values|newspaper=The Washington Post|date=August 4, 1907|page=F4}}
43. ^{{cite news|title=Argyle Park Homes|newspaper=The Evening Star|date=October 19, 1907|page=18}}
44. ^{{cite news|title=Lots Sell in Argyle|newspaper=The Washington Post|date=October 27, 1907|page=R5}}
45. ^{{cite news|title=Annual Report of the Commissioners of the District|newspaper=The Evening Star|date=December 3, 1907|pages=22–23}}
46. ^{{cite news|title=Inspection of City Improvements|newspaper=The Evening Star|date=December 28, 1907|page=8}}
47. ^{{cite news|title=To Widen a Bridge|newspaper=The Evening Star|date=January 25, 1908|page=20}}
48. ^{{cite news|title=Raise District Bill|newspaper=The Washington Post|date=April 29, 1908|page=1}}
49. ^{{cite news|title=Local Estimates Sent to Congress|newspaper=The Evening Star|date=December 7, 1908|pages=1, 9}}
50. ^{{cite news|title=District Bill Is Reported to House|newspaper=The Evening Star|date=January 6, 1909|pages=1, 4|postscript=none}}; {{cite news|title=Local Budget Cut|newspaper=The Washington Post|date=January 7, 1909|page=4}}
51. ^{{cite news|title=Big Increase In the District Bill Reported Today|newspaper=The Evening Star|date=February 2, 1909|page=4}}
52. ^{{cite news|title=Accept With Thanks|newspaper=The Washington Post|date=February 28, 1909|page=7}}
53. ^{{cite news|title=Proposals|newspaper=The Evening Star|date=May 8, 1909|page=10}}
54. ^{{cite news|title=Autos for District use|newspaper=The Washington Post|date=May 23, 1909|page=2}}
55. ^{{cite news|title=Extending 16th Street|newspaper=The Evening Star|date=June 13, 1909|page=24}}
56. ^{{cite news|title=His Hand Crushed|newspaper=The Evening Star|date=August 14, 1909|page=16}}
57. ^{{cite news|title=New Suburban Highway Soon|newspaper=The Evening Star|date=September 8, 1908|page=9|postscript=none}}; {{cite news|title=New Bridge Ready By Jan. 1|newspaper=The Washington Post|date=September 9, 1909|page=16}}
58. ^{{cite news|title=Six Bronze Tigers Together|newspaper=The Washington Post|date=June 12, 1910|page=11}}
59. ^{{cite journal|title=The Architectural League's Exhibition|journal=Art and Progress|date=March 1911|page=153|url=https://books.google.com/books?id=cl8oAAAAYAAJ&dq=%22Piney%20Branch%20Bridge%22%20proctor&pg=PA153#v=onepage&q=%22Piney%20Branch%20Bridge%22%20proctor&f=false}}
60. ^{{cite news|title=Bids for Fancy Lamps|newspaper=The Evening Star|date=November 6, 1909|page=2}}
61. ^{{cite news|title=Timber Crushes His Head|newspaper=The Evening Star|date=March 16, 1910|page=16}}
62. ^{{cite news|title=Sixteenth Street Extended Show Rapid Development|newspaper=The Evening Star|date=October 9, 1910|page=15}}
63. ^{{cite news|title=Construction at Piney Branch Bridge – List of Persons Planning to Build Fine Houses|newspaper=The Washington Post|date=December 3, 1911|page=R5}}
64. ^{{cite news|title=Work Planned on 16th Street Bridge|newspaper=The Washington Post|date=September 8, 1990|page=B5}}

Bibliography

{{refbegin|30em}}
  • {{cite journal|ref=harv|last=Allen|first=Walter C.|title=New Street Lighting in Washington, D.C.|journal=The Illuminating Engineer|date=October 1910|pages=401–405|url=https://books.google.com/books?id=ZSUVAQAAMAAJ&dq=%22Piney%20Branch%20Bridge%22%20lights&pg=PA401#v=onepage&q=%22Piney%20Branch%20Bridge%22%20lights&f=false}}
  • {{cite book|ref=harv|author=Commissioners of the District of Columbia|title=Annual Report of the Commissioners of the District of Columbia, Year Ended June 30, 1910. Volume II: Engineer Department Reports|location=Washington, D.C.|publisher=Government Printing Office|date=1910|url=https://books.google.com/books?id=7_ckxYI1p5sC&dq=%22Piney%20Branch%20Bridge%22%20proctor&pg=PA294#v=onepage&q=%22Piney%20Branch%20Bridge%22%20proctor&f=false}}
  • {{cite book|ref=harv|author=Committee on Education and Labor|title=Eight Hours for Laborers on Government Work. U.S. Senate. 57th Cong., 1st sess|location=Washington, D.C.|publisher=Government Printing Office|date=1902|url=https://books.google.com/books?id=bGwvAAAAMAAJ&dq=district%20of%20columbia%20eight-hour%20day%201892&pg=PA47#v=onepage&q=district%20of%20columbia%20eight-hour%20day%201892&f=false}}
  • {{cite book|ref=harv|last1=Crew|first1=Harvey W.|last2=Webb|first2=William Bensing|last3=Wooldridge|first3=John|title=Centennial History of the City of Washington, D.C., With Full Outline of the Natural Advantages, Accounts of the Indian Tribes, Selection of the Site, Founding of the City ... to the Present Time|location=Dayton, Ohio|publisher=United Brethren Pub. House|date=1892|url=https://books.google.com/books?id=s1lIAAAAYAAJ&dq=%22Concordia%20Church%22%20DC&pg=PA580#v=onepage&q&f=false}}
  • {{cite book|ref=harv|last1=Lee|first1=Robert D.|last2=Johnson|first2=Ronald Wayne|last3=Joyce|first3=Philip G.|title=Public Budgeting Systems|location=Burlington, Mass.|publisher=Jones & Bartlett Learning|date=2013|isbn=9781449627904|url=https://books.google.com/books?id=XVGNGB-SWDEC&lpg=PA316&dq=budgeting%20authorization&pg=PA315#v=onepage&q=budgeting%20authorization&f=false}}
  • {{cite book|ref=harv|last=Myer|first=Donald Beekman|title=Bridges and the City of Washington|location=Washington, D.C.|publisher=United States Commission of Fine Arts|date=1974}}
  • {{cite journal|ref={{harvid|Piney Branch Bridge Finished|1910}} |title=Piney Branch Bridge Finished|journal=Municipal Journal and Engineer|date=June 15, 1910|page=878|url=https://books.google.com/books?id=FZcfAQAAMAAJ&dq=%22Piney%20Branch%20Bridge%22%20lamps&pg=PA878#v=onepage&q=%22Piney%20Branch%20Bridge%22%20lamps&f=false}}
  • {{cite book|ref=harv|last=Sullivan|first=Francis P.|chapter=Concrete Forms and Concrete Surfaces|title=The Architectural Annual, 1907|editor-last=Hynes|editor-first=J.P.|location=Washington, D.C.|publisher=Architectural League of America|date=1908|pages=153–159|url=https://books.google.com/books?id=07QgAAAAMAAJ&dq=%22Piney%20Branch%20Bridge%22%20lamps&pg=PA153#v=onepage&q=%22Piney%20Branch%20Bridge%22%20lamps&f=false}}
{{refend}}

External links

{{Commons category multi|16th Street Bridge|16th Street Bridge Lions}}
  • Replacement of 16th Street NW Bridge over Military Road NW – DC Dept. of Transportation

9 : Bridges completed in 1907|Bridges completed in 1910|Neoclassical architecture in Washington, D.C.|Historic American Engineering Record in Washington, D.C.|Road bridges in Washington, D.C.|Rock Creek (Potomac River)|Concrete bridges in the United States|Arch bridges in the United States|Rock Creek Park